Show Job Controls
Bid Cobra

TYLER US0190 (6383-17-001)

Items: 30

County: TYLER
Length: N/A
Highway: US0190
District: BEAUMONT
Control Number: 6383-17-001
DBE Goal: N/A
Project: RMC - 638317001
Guaranty: N/A
Time: 43 W
Engineer's Estimate: $791,175.65
Date: 11/03/2021 (4 years ago)
Contract Number: N/A
Type: MILL AND INLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (3)
E
Engineer's Estimate
$791,175.65
Over/Under Est: -10.53% -$83,277.35
Over/Under Est: -6.61% -$52,327.10
Amt Left: 4.37% $30,950.25
Over/Under Est: -5.85% -$46,317.06
Amt Left: 5.22% $36,960.29
Delta: -0.81% -$6,010.04

Bid Items & Bid Tabulations

30 Total 0 of 30
TYLER  |  US0190  |  BEAUMONT  |  6383-17-001  |  11/03/2021  |  $791,175.65  |  RMC - 638317001  |  MILL AND INLAY  |  43 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
MOORE BROTHERS CONSTRUCTION COMPANY
DREWERY CONSTRUCTION COMPANY, INCORPORATED
TEXAS MATERIALS GROUP, INC.
REMOVING CONC (RIPRAP)
SY 8.000 $150.000 $110.000 $414.000 $105.000
D-GR HMA(SQ) TY-C SAC-B PG76-22
TON 3,776.000 $125.000 $112.800 $110.000 $121.270
TACK COAT
GAL 3,432.000 $4.000 $3.900 $4.850 $3.060
PLANE ASPH CONC PAV (2")
SY 34,317.000 $1.500 $1.950 $1.250 $2.080
RIPRAP (CONC)(FLUME)
CY 4.000 $1,275.000 $1,755.000 $1,596.000 $997.500
RIPRAP (MOW STRIP)(4 IN)
CY 13.000 $650.000 $1,780.000 $1,600.000 $661.500
RETROFIT RAIL (TY SSTR)
LF 160.000 $600.000 $230.000 $202.000 $178.500
REMOVE STR (RAIL)
LF 160.000 $65.000 $51.500 $46.000 $24.150
MOBILIZATION
LS 1.000 $72,000.000 $65,000.000 $63,525.000 $51,764.220
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $3,000.000 $4,200.000 $20,300.000 $15,274.880
MTL W-BEAM GD FEN (TIM POST)
LF 50.000 $27.500 $41.800 $35.500 $39.900
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,650.000 $2,185.000 $3,300.000 $2,084.250
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 3.000 $1,750.000 $1,550.000 $1,506.000 $1,470.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $265.000 $275.000 $197.000 $262.500
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $2,750.000 $3,405.000 $4,140.000 $3,249.750
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $21.000 $16.000 $22.000 $15.750
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $35.000 $40.000 $45.000 $37.800
INSTL OM ASSM (OM-2Z)(WFLX)SRF(BI)
EA 5.000 $100.000 $160.000 $96.000 $157.500
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 2,550.000 $0.250 $0.400 $0.700 $0.680
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 9,528.000 $0.300 $0.400 $0.700 $0.680
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 715.000 $1.500 $1.250 $3.500 $2.260
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 482.000 $1.500 $1.250 $3.500 $2.630
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 2,550.000 $0.550 $0.880 $0.800 $0.800
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 1,092.000 $0.550 $0.880 $0.800 $0.800
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 9,528.000 $0.550 $0.880 $0.800 $0.800
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 146.000 $13.000 $13.750 $23.000 $23.630
REFL PAV MRKR TY I-C
EA 123.000 $4.250 $8.000 $5.000 $5.250
REFL PAV MRKR TY II-A-A
EA 126.000 $4.250 $8.000 $5.000 $5.250
TMA (STATIONARY)
DAY 40.000 $250.000 $25.000 $270.000 $262.500
TMA (MOBILE OPERATION)
DAY 3.000 $500.000 $100.000 $350.000 $367.500
Totals: $791,175.650 $707,898.300 $738,848.550 $744,858.590