TYLER US 287 (0341-04-074)
Items: 68
County: TYLER
Length: 12.4830 MILES
Highway: US 287
District: BEAUMONT
Control Number: 0341-04-074
DBE Goal: 0.0%
Project: F 2026(497)
Guaranty: $100,000.00
Time: 294 WORKING DAYS
Engineer's Estimate: $20,662,478.00
Date: 04/08/2026 (2 months ago)
Contract Number: 4263206
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00196681
Contract Type: Federal
Project Description: US 287 (RUSSELL CREEK BRIDGE, SOUTH TO US 69) FULL DEPTH BASE REPAIR AND SP-C
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DAVE COLLINS
RICHARD BRADLEY
TYLER US 287 (0341-04-074)
Project Name: N/A
Project: F 2026(497)
Length: 12.4830 MILES
Project Type: CONSTRUCTION
Limits From: RUSSELL CREEK BRIDGE, SOUTH
Limits To: US 69
Project Description: US 287 (RUSSELL CREEK BRIDGE, SOUTH TO US 69) FULL DEPTH BASE REPAIR AND SP-C
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$20,662,478.00 | |||
| $20,919,240.07 |
1.24%
$256,762.07
|
|||
| $21,505,037.20 |
4.08%
$842,559.20
|
2.8%
$585,797.13
|
||
| $21,991,336.81 |
6.43%
$1,328,858.81
|
5.12%
$1,072,096.74
|
-2.26%
-$486,299.61
|
|
| $23,859,354.57 |
15.47%
$3,196,876.57
|
14.05%
$2,940,114.50
|
-8.49%
-$1,868,017.76
|
|
| $24,947,070.85 |
20.74%
$4,284,592.85
|
19.25%
$4,027,830.78
|
-4.56%
-$1,087,716.28
|
E
Engineer's Estimate
$20,662,478.00
$20,919,240.07
Over/Under Est:
1.24%
$256,762.07
$21,505,037.20
Over/Under Est:
4.08%
$842,559.20
Amt Left:
2.8%
$585,797.13
$21,991,336.81
Over/Under Est:
6.43%
$1,328,858.81
Amt Left:
5.12%
$1,072,096.74
Delta:
-2.26%
-$486,299.61
$23,859,354.57
Over/Under Est:
15.47%
$3,196,876.57
Amt Left:
14.05%
$2,940,114.50
Delta:
-8.49%
-$1,868,017.76
$24,947,070.85
Over/Under Est:
20.74%
$4,284,592.85
Amt Left:
19.25%
$4,027,830.78
Delta:
-4.56%
-$1,087,716.28
Bid Items & Bid Tabulations
68
Total
0 of 68
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $3,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| Total: | $13,000.00 |