Job Info for 0200-08-059

County: TYLER Highway: US 69 Date: 10/06/2022 (2 years ago) Engineer's Estimate: $1,533,803 Control Number: 0200-08-059
Project: C 200-8-59 District: BEAUMONT Time: 82 WORKING DAYS Type: INFRASTRUCTURE IMPROVEMENTS
HCS
Pay Estimate
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,533,803.39
DIGG COMMERCIAL, LLC   $1,846,631.83 1
20.4% | $312,828.44
A. L. HELMCAMP, INC.   $2,688,920.75 2
75.31% | $1,155,117.36
45.61% | $842,288.92
RAGLE CONSTRUCTION, INC.   $2,721,921.57 3
77.46% | $1,188,118.18
47.4% | $875,289.74
1.23% | $33,000.82

Bid Items

Items: 18, 0 filtered
TYLER US 69  |  BEAUMONT  |  0200-08-059  |  10/06/2022  |  $1,533,803  |  C 200-8-59  |  INFRASTRUCT IMPRVS  |  82 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate DIGG COMMERCIAL, LLC A. L. HELMCAMP, INC. RAGLE CONSTRUCTION, INC.
100 6001 PREPARING ROW AC 42.000 $11,000.000 $10,000.000 $20,000.000 $38,750.000
150 6001 BLADING STA 452.000 $155.000 $1,200.000 $150.000 $308.000
164 6030 CELL FBR MLCH SEED(TEMP)(WARM) AC 15.510 $1,312.000 $10,000.000 $1,870.000 $1,700.000
164 6032 CELL FBR MLCH SEED(TEMP)(COOL) AC 15.510 $1,312.000 $1.000 $1,870.000 $1,700.000
168 6001 VEGETATIVE WATERING MG 3,748.000 $20.000 $1.000 $15.000 $25.000
500 6001 MOBILIZATION LS 1.000 $128,379.200 $200,000.000 $400,000.000 $260,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $5,780.000 $5,000.000 $85,000.000 $45,000.000
506 6001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 100.000 $26.000 $150.000 $49.500 $45.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 100.000 $8.000 $50.000 $13.200 $12.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 1,580.000 $36.000 $50.000 $15.000 $25.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 1,580.000 $8.000 $10.000 $1.000 $5.000
506 6034 CONSTRUCTION PERIMETER FENCE LF 12,339.000 $4.000 $6.000 $7.500 $4.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 38,869.000 $4.000 $4.000 $3.850 $1.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 38,869.000 $1.250 $1.000 $0.550 $0.250
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 2,220.000 $6.000 $10.000 $7.150 $6.500
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 2,220.000 $1.500 $2.000 $0.550 $0.500
5027 6001 TEMPORARY CONSTRUCTION MATTING SY 5,129.110 $70.000 $12.000 $75.000 $12.000
6185 6002 TMA (STATIONARY) DAY 120.000 $175.000 $200.000 $500.000 $422.000
Totals: $1,533,803.39 $1,846,631.83 $2,688,920.75 $2,721,921.57