TRAVIS SL 1 (3136-01-197)

Items: 32

County: TRAVIS
Length: N/A
Highway: SL 1
District: AUSTIN
Control Number: 3136-01-197
DBE Goal: N/A
Project: C 3136-1-197
Guaranty: N/A
Time: 51 WORKING DAYS
Engineer's Estimate: $653,418.28
Date: 04/05/2023 (3 years ago)
Contract Number: N/A
Type: LANDSCAPE DEVELOPMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$653,418.28
Over/Under Est: -5.63% -$36,755.58
Over/Under Est: 1.36% $8,886.26
Amt Left: 7.4% $45,641.84
Over/Under Est: 15.12% $98,771.32
Amt Left: 21.98% $135,526.90
Delta: -13.57% -$89,885.06
Subcontractor Percentage Amount
CERTIFIED ARBOR CARE, INC. 3.06% $18,869.88
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC 0.70% $4,316.64
Total: 3.76% $23,186.52

Bid Items & Bid Tabulations

32 Total 0 of 32
TRAVIS  |  SL 1  |  AUSTIN  |  3136-01-197  |  04/05/2023  |  $653,418.28  |  C 3136-1-197  |  LANDSCAPE DEVELOPMENT  |  51 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
APEX LANDSCAPE & IRRIGATION, LLC
USA DT SERVICES, INC.
ENCINO LANDSCAPE, INC.
GENERAL USE COMPOST (4")
SY 2,888.000 $4.500 $3.550 $20.000 $5.000
IRRIGATION SYSTEM LOCATION B
LS 1.000 $60,000.000 $68,000.000 $53,373.760 $100,000.000
WILDFLOWER SEEDING
AC 10.000 $1,200.000 $1,000.000 $3,350.000 $2,000.000
PLANT MATERIAL (1-GAL)
EA 1,207.000 $8.000 $12.000 $10.520 $15.000
PLANT MATERIAL (5-GAL)
EA 628.000 $40.000 $34.000 $21.900 $35.000
PLANT MATERIAL (15-GAL)
EA 9.000 $130.000 $200.000 $585.940 $200.000
PLANT MATERIAL (30-GAL)
EA 19.000 $260.000 $210.000 $438.700 $275.000
MULCH
SY 2,888.000 $4.000 $2.850 $20.000 $5.000
LANDSCAPE EDGE
LF 6,189.000 $30.000 $22.500 $8.650 $20.000
PLANT MATERIAL (45 GAL) (TREE)
EA 110.000 $525.000 $480.000 $537.360 $450.000
PLANT MATERIAL (100 GAL) (TREE)
EA 35.000 $1,200.000 $1,150.000 $685.310 $900.000
PLANT MATERIAL (MIN 3" CAL) (B&B)
EA 6.000 $500.000 $400.000 $822.830 $500.000
PLANT BED PREP (TYPE I)
SY 1,099.000 $3.500 $1.750 $12.500 $3.000
PLANT BED PREP (TYPE II)
SY 1,789.000 $2.750 $1.750 $12.500 $6.000
PLANT MAINTENANCE
MO 24.000 $800.000 $2,500.000 $1,800.000 $3,000.000
IRRIGATION SYSTEM OPER AND MAINT
MO 24.000 $500.000 $2,000.000 $810.000 $1,000.000
TRENCH EXCAVATION PROTECTION
LF 50.000 $10.000 $0.100 $9.380 $1.000
TEMPORARY SPL SHORING
SF 50.000 $12.000 $0.100 $18.050 $1.000
CL B CONC (MISC)
CY 5.000 $800.000 $1.000 $250.000 $1,000.000
RIPRAP (CONC)(5 IN)
CY 5.000 $1,100.000 $1.000 $250.000 $1,000.000
MOBILIZATION
LS 1.000 $58,038.030 $61,000.000 $35,000.000 $70,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $5,000.000 $3,100.000 $16,500.000 $3,000.000
SANDBAGS FOR EROSION CONTROL
EA 50.000 $7.000 $0.100 $6.110 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 50.000 $3.500 $0.100 $3.940 $1.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 50.000 $1.000 $0.100 $8.490 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 10,860.000 $4.000 $1.400 $5.730 $8.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 10,860.000 $0.750 $0.300 $0.160 $0.010
TREE REMOVAL (18" - 24" DIA)
EA 6.000 $900.000 $500.000 $125.000 $1,000.000
TREE TRIMMING AND BRUSH REMOVAL
LF 200.000 $20.000 $35.000 $25.000 $50.000
TREE TRIMMING
EA 109.000 $150.000 $250.000 $45.000 $150.000
TREE PROTECTION
EA 89.000 $200.000 $50.000 $35.000 $200.000
TMA (STATIONARY)
DAY 30.000 $275.000 $10.000 $417.000 $400.000
Totals: $653,418.280 $616,662.700 $662,304.540 $752,189.600