Job Info for 2718-01-015

County: TRAVIS Highway: RM 2769 Date: 01/04/2024 (10 months ago) Engineer's Estimate: $2,597,385 Control Number: 2718-01-015
Project: C 2718-1-15 District: AUSTIN Time: 53 WORKING DAYS Type: RESURFACE ROADWAY
Bidder's List
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,597,385.31
TEXAS MATERIALS GROUP, INC.   $2,979,802.82 1
14.72% | $382,417.51
LONE STAR PAVING COMPANY   $3,837,137.83 2
47.73% | $1,239,752.52
28.77% | $857,335.01
HUNTER INDUSTRIES, LTD.   $4,892,144.48 3
88.35% | $2,294,759.17
64.18% | $1,912,341.66
27.49% | $1,055,006.65
Subcontractor Percentage Amount
ENVIRONMENTAL SAFETY SERVICES, INC. 5.03% $149,884.08
ROADWAY SPECIALTIES, INC. 4.88% $145,414.38
D. I. J. CONSTRUCTION, INC. 3.85% $114,722.41
TEXOP CONSTRUCTION 2.51% $74,793.05
BROTHERS RDC PAVING, LLC 2.16% $64,363.74
TRP CONSTRUCTION GROUP, LLC 2.01% $59,894.04
ROADWAY TRAFFIC CONTROL LLC 0.23% $6,853.55
Total: 20.67% $615,925.25

Bid Items

Items: 53, 0 filtered
TRAVIS RM 2769  |  AUSTIN  |  2718-01-015  |  01/04/2024  |  $2,597,385  |  C 2718-1-15  |  RESURF ROADWAY  |  53 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate TEXAS MATERIALS GROUP, INC. LONE STAR PAVING COMPANY HUNTER INDUSTRIES, LTD.
104 6009 REMOVING CONC (RIPRAP) SY 210.000 $19.800 $100.000 $95.000 $52.500
134 6001 BACKFILL (TY A) STA 327.000 $200.000 $150.000 $360.000 $242.000
351 6002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 1,200.000 $51.000 $94.000 $175.000 $132.830
354 6043 PLANE ASPH CONC PAV (1") SY 134,880.000 $1.680 $2.250 $1.850 $3.230
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 23.400 $717.500 $1,125.000 $750.000 $666.630
500 6001 MOBILIZATION LS 1.000 $282,111.460 $225,000.000 $375,000.000 $488,950.870
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $7,000.000 $15,000.000 $90,000.000 $17,021.270
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 100.000 $7.920 $20.000 $10.500 $10.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 100.000 $2.700 $10.000 $5.250 $5.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 100.000 $7.000 $20.000 $10.500 $10.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 100.000 $2.370 $10.000 $5.250 $5.000
530 6011 INTRSCT, DRVWAYS, & TURNOUT (ACP) SY 2,470.000 $42.000 $52.000 $75.000 $126.500
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 1,860.000 $25.980 $30.670 $34.000 $30.320
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $2,301.710 $2,303.210 $3,225.000 $3,375.000
540 6014 SHORT RADIUS LF 25.000 $187.140 $754.700 $1,075.000 $966.560
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 6.000 $1,700.000 $1,488.610 $1,850.000 $1,645.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 2,160.000 $5.280 $6.000 $5.500 $5.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 4.000 $523.000 $553.920 $215.000 $190.870
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 4.000 $291.500 $355.100 $535.000 $476.930
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 6.000 $3,600.000 $4,018.200 $3,515.000 $3,124.500
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 8.000 $424.000 $482.420 $535.000 $476.700
658 6061 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 EA 146.000 $32.400 $47.750 $45.000 $42.520
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 897.000 $1.680 $2.000 $1.500 $1.630
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 3,194.000 $1.590 $2.000 $1.500 $1.630
666 6030 REFL PAV MRK TY I (W)8"(DOT)(100MIL) LF 1,358.000 $1.060 $2.200 $2.200 $2.200
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 4,343.000 $2.040 $1.500 $1.500 $1.500
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 263.000 $14.310 $13.650 $13.650 $13.650
666 6054 REFL PAV MRK TY I (W)(ARROW)(100MIL) EA 24.000 $286.180 $195.000 $195.000 $195.000
666 6057 REFL PAV MRK TY I(W)(DBL ARROW)(100MIL) EA 1.000 $293.280 $210.000 $210.000 $210.000
666 6078 REFL PAV MRK TY I (W)(WORD)(100MIL) EA 24.000 $302.000 $210.000 $210.000 $210.000
666 6102 REF PAV MRK TY I(W)36"(YLD TRI)(100MIL) EA 41.000 $55.500 $45.000 $45.000 $45.000
666 6171 REFL PAV MRK TY II (W) 6" (BRK) LF 2,263.000 $0.390 $0.220 $0.220 $0.220
666 6174 REFL PAV MRK TY II (W) 6" (SLD) LF 70,513.000 $0.430 $0.210 $0.210 $0.210
666 6176 REFL PAV MRK TY II (W) 8" (DOT) LF 1,358.000 $0.770 $0.800 $0.800 $0.800
666 6178 REFL PAV MRK TY II (W) 8" (SLD) LF 4,343.000 $0.910 $0.500 $0.500 $0.500
666 6182 REFL PAV MRK TY II (W) 24" (SLD) LF 263.000 $4.570 $3.250 $3.250 $3.250
666 6184 REFL PAV MRK TY II (W) (ARROW) EA 24.000 $84.000 $60.000 $60.000 $60.000
666 6185 REFL PAV MRK TY II (W) (DBL ARROW) EA 1.000 $142.000 $70.000 $70.000 $70.000
666 6192 REFL PAV MRK TY II (W) (WORD) EA 24.000 $100.000 $70.000 $70.000 $70.000
666 6199 REFL PAV MRK TY II (W) 36" (YLD TRI) EA 41.000 $22.400 $15.000 $15.000 $15.000
666 6210 REFL PAV MRK TY II (Y) 6" (SLD) LF 65,014.000 $0.620 $0.210 $0.210 $0.210
666 6306 RE PM W/RET REQ TY I (W)6"(BRK)(100MIL) LF 2,263.000 $0.900 $0.790 $0.790 $0.790
666 6343 REF PROF PAV MRK TY I(W)6"(SLD)(100MIL) LF 70,513.000 $1.150 $0.940 $0.940 $0.940
666 6347 REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL) LF 65,014.000 $1.060 $0.940 $0.940 $0.940
672 6007 REFL PAV MRKR TY I-C EA 12.000 $6.450 $15.500 $16.000 $15.500
672 6009 REFL PAV MRKR TY II-A-A EA 817.000 $8.270 $5.200 $5.200 $5.200
672 6010 REFL PAV MRKR TY II-C-R EA 322.000 $7.240 $7.000 $6.450 $6.450
3081 6008 TOM-C PG76-22 SAC-B TON 7,621.000 $155.000 $196.000 $230.000 $361.900
3084 6001 BONDING COURSE GAL 12,139.000 $4.140 $6.500 $3.750 $4.640
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 220.000 $155.000 $65.000 $50.000 $160.000
6056 6002 PREFORMED CENTERLINE RUMBLE STRIP LF 20,604.000 $4.300 $4.300 $4.350 $4.300
6185 6002 TMA (STATIONARY) DAY 96.000 $400.000 $175.000 $306.000 $250.000
6185 6005 TMA (MOBILE OPERATION) DAY 20.000 $813.000 $200.000 $306.000 $320.000
Totals: $2,597,385.31 $2,979,802.82 $3,837,137.83 $4,892,144.48