Show Job Controls
Bid Cobra

TRAVIS RM 2244 (2102-01-074)

Items: 24

County: TRAVIS
Length: N/A
Highway: RM 2244
District: AUSTIN
Control Number: 2102-01-074
DBE Goal: N/A
Project: NH 2019(826)
Guaranty: N/A
Time: 57 WORKING DAYS
Engineer's Estimate: $251,381.50
Date: 05/07/2019 (7 years ago)
Contract Number: N/A
Type: LANDSCAPING AND IRRIGATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$251,381.50
$229,999.37
Over/Under Est: -8.51% -$21,382.13
Over/Under Est: 1.63% $4,088.75
Amt Left: 11.07% $25,470.88
Over/Under Est: 20.06% $50,419.50
Amt Left: 31.22% $71,801.63
Delta: -18.14% -$46,330.75
Over/Under Est: 22.06% $55,453.51
Amt Left: 33.41% $76,835.64
Delta: -1.67% -$5,034.01
Over/Under Est: 26.16% $65,770.50
Amt Left: 37.89% $87,152.63
Delta: -3.36% -$10,316.99
Over/Under Est: 47.03% $118,212.50
Amt Left: 60.69% $139,594.63
Delta: -16.54% -$52,442.00

Bid Items & Bid Tabulations

24 Total 0 of 24
TRAVIS  |  RM 2244  |  AUSTIN  |  2102-01-074  |  05/07/2019  |  $251,381.50  |  NH 2019(826)  |  LANDSCAPING AND IRRIGATION  |  57 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HAM-BAR, L.L.C.
ENCINO LANDSCAPE, INC.
CLASSIC IRRIGATION & LANDSCAPE LLC
APEX LANDSCAPE & IRRIGATION, LLC
TEXAS ROAD CONSTRUCTION, LLC
TIGHT LINE CONSTRUCTION, LLC
GENERAL USE COMPOST (4")
SY 1,131.000 $4.500 $9.330 $3.000 $35.000 $3.400 $6.000 $5.000
IRRIGATION SYSTEM
LS 1.000 $16,500.000 $14,857.710 $20,000.000 $25,000.000 $50,000.000 $10,000.000 $45,000.000
PLANT MATERIAL (5-GAL)
EA 412.000 $25.000 $39.770 $30.000 $28.000 $25.000 $25.000 $30.000
PLANT MATERIAL (15-GAL)
EA 405.000 $130.000 $118.790 $100.000 $65.000 $145.000 $175.000 $130.000
PLANT MATERIAL (30-GAL)
EA 325.000 $240.000 $149.120 $225.000 $150.000 $260.000 $300.000 $300.000
MULCH
SY 1,131.000 $3.500 $8.990 $3.000 $35.000 $4.000 $6.000 $5.000
PLANT BED PREPARATION
SY 1,131.000 $3.500 $9.550 $1.000 $25.000 $2.000 $5.000 $3.000
PLANT MAINTENANCE
MO 24.000 $250.000 $300.000 $1,000.000 $300.000 $1,650.000 $1,200.000 $1,250.000
PLANT REPLACEMENT (5-GAL)
EA 50.000 $20.000 $39.000 $30.000 $28.000 $0.100 $15.000 $1.000
IRRIGATION SYSTEM OPER AND MAINT
MO 24.000 $450.000 $300.000 $1,000.000 $250.000 $550.000 $500.000 $1,250.000
PLANT REPLACEMENT (15 GAL)
EA 100.000 $130.000 $115.000 $0.010 $65.000 $0.100 $75.000 $100.000
PLANT REPLACEMENT (30 GAL)
EA 10.000 $240.000 $110.000 $0.010 $150.000 $0.010 $200.000 $1.000
TRENCH EXCAVATION PROTECTION
LF 50.000 $20.000 $10.250 $0.010 $20.000 $0.010 $10.000 $1.000
TEMPORARY SPL SHORING
SF 50.000 $35.000 $3.000 $0.010 $40.000 $0.010 $10.000 $1.000
RIPRAP (CONC)(5 IN)
CY 1.000 $1,000.000 $600.000 $1,000.000 $750.000 $0.010 $300.000 $1.000
MOBILIZATION
LS 1.000 $20,000.000 $19,999.000 $25,000.000 $20,000.000 $25,000.000 $25,000.000 $55,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $1,800.000 $1,000.000 $3,000.000 $2,500.000 $2,000.000 $2,500.000 $2,000.000
SANDBAGS FOR EROSION CONTROL
EA 50.000 $8.000 $3.000 $1.000 $5.000 $0.010 $10.000 $5.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 700.000 $2.500 $3.000 $1.000 $2.000 $0.100 $5.000 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 700.000 $0.750 $1.000 $1.000 $1.000 $0.100 $2.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,600.000 $4.000 $3.000 $7.000 $4.000 $1.170 $6.000 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,600.000 $0.500 $1.750 $0.010 $1.500 $0.250 $2.000 $1.000
TREE PROTECTION
EA 7.000 $450.000 $200.000 $200.000 $35.000 $100.000 $100.000 $10.000
TMA (STATIONARY)
DAY 15.000 $250.000 $300.000 $0.010 $1,000.000 $250.000 $200.000 $100.000
Totals: $251,381.500 $229,999.370 $255,470.250 $301,801.000 $306,835.010 $317,152.000 $369,594.000