PREPARING ROW
|
STA
|
53.000
|
$5,000.000
|
$5,350.000
|
$1,163.000
|
$8,000.000
|
$4,700.000
|
$6,500.000
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
3,196.000
|
$10.000
|
$14.000
|
$8.000
|
$30.000
|
$24.500
|
$50.000
|
|
|
REMOVING CONC (HEADWALL)
|
CY
|
10.000
|
$600.000
|
$110.000
|
$71.000
|
$500.000
|
$1,050.000
|
$2,500.000
|
|
|
REMOVING CONCRETE(MOW STRIP)
|
LF
|
1,199.000
|
$10.000
|
$6.500
|
$3.000
|
$20.000
|
$17.500
|
$16.000
|
|
|
REMOVING STAB BASE AND ASPH PAV (2"-6")
|
SY
|
5,748.000
|
$8.000
|
$12.000
|
$1.000
|
$20.000
|
$14.000
|
$12.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
9,426.000
|
$17.000
|
$26.000
|
$21.000
|
$20.000
|
$38.500
|
$55.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
3,943.000
|
$20.000
|
$14.000
|
$27.000
|
$35.000
|
$38.500
|
$75.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
22,233.000
|
$2.000
|
$3.250
|
$2.500
|
$6.000
|
$3.880
|
$5.000
|
|
|
DRILL SEEDING (PERM) (RURAL) (CLAY)
|
SY
|
22,233.000
|
$0.300
|
$0.400
|
$0.400
|
$1.000
|
$0.350
|
$0.400
|
|
|
BROADCAST SEED (TEMP)(WARM OR COOL)
|
SY
|
11,117.000
|
$0.400
|
$0.300
|
$0.310
|
$1.000
|
$0.270
|
$0.350
|
|
|
VEGETATIVE WATERING
|
MG
|
3,307.000
|
$12.000
|
$33.000
|
$8.000
|
$25.000
|
$31.500
|
$35.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY B)
|
SY
|
22,233.000
|
$1.200
|
$1.250
|
$1.320
|
$5.000
|
$1.180
|
$1.500
|
|
|
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
|
CY
|
2,411.000
|
$56.000
|
$77.000
|
$93.000
|
$60.000
|
$117.700
|
$150.000
|
|
|
PRIME COAT (MULTI OPTION)
|
GAL
|
2,170.000
|
$5.500
|
$4.500
|
$4.000
|
$6.000
|
$7.900
|
$5.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
|
SY
|
500.000
|
$50.190
|
$100.000
|
$30.000
|
$75.000
|
$136.400
|
$108.000
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
24,564.000
|
$5.000
|
$1.500
|
$1.500
|
$6.000
|
$3.230
|
$1.500
|
|
|
CUT & RESTORING PAV
|
SY
|
520.000
|
$125.000
|
$150.000
|
$105.000
|
$200.000
|
$190.420
|
$650.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
580.000
|
$5.000
|
$10.000
|
$12.000
|
$10.000
|
$89.860
|
$25.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
10,551.000
|
$20.000
|
$4.750
|
$12.000
|
$35.000
|
$45.070
|
$50.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
191.000
|
$635.000
|
$460.000
|
$1,400.000
|
$500.000
|
$768.150
|
$1,000.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(24 IN)
|
CY
|
142.300
|
$250.000
|
$240.000
|
$310.000
|
$250.000
|
$286.700
|
$115.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
172.000
|
$600.000
|
$570.000
|
$729.000
|
$550.000
|
$795.800
|
$800.000
|
|
|
CONC BOX CULV (3 FT X 3 FT)
|
LF
|
124.000
|
$420.000
|
$560.000
|
$1,335.000
|
$650.000
|
$697.830
|
$1,200.000
|
|
|
CONC BOX CULV (4 FT X 4 FT)
|
LF
|
88.000
|
$480.000
|
$540.000
|
$1,066.000
|
$700.000
|
$974.290
|
$1,600.000
|
|
|
CONC BOX CULV (11 FT X 11 FT)
|
LF
|
112.000
|
$1,500.000
|
$2,100.000
|
$3,470.000
|
$2,000.000
|
$2,898.700
|
$3,200.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
200.000
|
$80.000
|
$87.000
|
$129.000
|
$85.000
|
$214.410
|
$145.000
|
|
|
RC PIPE (ARCH)(CL III)(DES 4)
|
LF
|
48.000
|
$320.000
|
$260.000
|
$315.000
|
$300.000
|
$473.490
|
$440.000
|
|
|
RC PIPE (ARCH)(CL III)(DES 5)
|
LF
|
176.000
|
$450.000
|
$480.000
|
$1,077.000
|
$400.000
|
$633.990
|
$890.000
|
|
|
HEADWALL (CH - PW - A - 0) (DES= 5)
|
EA
|
1.000
|
$10,000.000
|
$45,000.000
|
$9,008.000
|
$25,000.000
|
$30,502.270
|
$25,000.000
|
|
|
WINGWALL (FW - 0) (HW=6 FT)
|
EA
|
1.000
|
$15,000.000
|
$36,000.000
|
$15,623.000
|
$25,000.000
|
$20,285.110
|
$32,000.000
|
|
|
WINGWALL (PW - 1) (HW=13 FT)
|
EA
|
2.000
|
$55,000.000
|
$58,000.000
|
$81,000.000
|
$60,000.000
|
$82,430.650
|
$105,000.000
|
|
|
WINGWALL (PW - 1) (HW=5 FT)
|
EA
|
1.000
|
$20,000.000
|
$28,000.000
|
$12,000.000
|
$28,500.000
|
$21,133.090
|
$26,000.000
|
|
|
WINGWALL (PW - 1) (HW=8 FT)
|
EA
|
2.000
|
$36,000.000
|
$46,000.000
|
$26,500.000
|
$35,000.000
|
$42,981.720
|
$42,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
8.000
|
$1,250.000
|
$5,400.000
|
$2,000.000
|
$1,850.000
|
$2,907.670
|
$2,600.000
|
|
|
SET (TY II) (DES 4) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$5,500.000
|
$9,100.000
|
$5,236.000
|
$6,500.000
|
$12,475.350
|
$5,100.000
|
|
|
SET (TY II) (DES 5) (RCP) (3: 1) (C)
|
EA
|
1.000
|
$6,000.000
|
$19,000.000
|
$7,600.000
|
$7,500.000
|
$19,821.680
|
$5,200.000
|
|
|
REMOV STR (SET)
|
EA
|
10.000
|
$600.000
|
$1,000.000
|
$1,518.000
|
$850.000
|
$1,912.100
|
$1,500.000
|
|
|
REMOV STR (PIPE)
|
LF
|
872.000
|
$20.000
|
$20.000
|
$36.000
|
$50.000
|
$159.630
|
$33.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$400,000.000
|
$400,000.000
|
$325,000.000
|
$580,000.000
|
$444,607.270
|
$730,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
14.000
|
$8,000.000
|
$9,500.000
|
$7,557.000
|
$8,500.000
|
$6,747.430
|
$10,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
60.000
|
$36.000
|
$35.000
|
$41.000
|
$30.000
|
$35.530
|
$45.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 4)
|
LF
|
131.000
|
$55.000
|
$50.000
|
$59.000
|
$50.000
|
$51.370
|
$64.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
191.000
|
$20.000
|
$32.000
|
$12.000
|
$15.000
|
$32.650
|
$41.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
5,195.000
|
$6.000
|
$5.000
|
$5.000
|
$18.000
|
$4.670
|
$6.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
5,195.000
|
$2.000
|
$0.600
|
$0.620
|
$9.000
|
$0.550
|
$0.700
|
|
|
DRIVEWAYS (CONC)
|
SY
|
209.000
|
$115.000
|
$130.000
|
$118.000
|
$85.000
|
$142.680
|
$130.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
414.000
|
$110.000
|
$150.000
|
$95.000
|
$55.000
|
$101.200
|
$110.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
3,630.000
|
$27.000
|
$27.000
|
$29.000
|
$25.000
|
$23.790
|
$37.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
6.000
|
$1,400.000
|
$1,700.000
|
$1,731.000
|
$1,850.000
|
$1,471.550
|
$2,300.000
|
|
|
MTL BM GD FEN (LONG SPAN SYSTEM)
|
LF
|
50.000
|
$38.000
|
$29.000
|
$31.000
|
$50.000
|
$25.590
|
$39.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,145.000
|
$4.000
|
$3.500
|
$3.000
|
$3.000
|
$3.150
|
$6.700
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
4.000
|
$250.000
|
$370.000
|
$377.000
|
$500.000
|
$320.450
|
$172.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
6.000
|
$3,500.000
|
$4,100.000
|
$4,201.000
|
$3,250.000
|
$3,571.080
|
$4,800.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
3.000
|
$350.000
|
$370.000
|
$377.000
|
$850.000
|
$320.450
|
$345.000
|
|
|
PIPE UNDERDRAINS (TY 8) (6")
|
LF
|
3,110.000
|
$32.000
|
$38.000
|
$71.000
|
$65.000
|
$87.310
|
$51.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
10.000
|
$800.000
|
$1,100.000
|
$960.000
|
$1,150.000
|
$777.000
|
$980.000
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
9.000
|
$700.000
|
$800.000
|
$960.000
|
$850.000
|
$777.000
|
$870.000
|
|
|
RELOCATE SM RD SN SUP&AM TY S80
|
EA
|
3.000
|
$800.000
|
$800.000
|
$960.000
|
$850.000
|
$777.000
|
$1,100.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
4.000
|
$64.000
|
$275.000
|
$95.000
|
$100.000
|
$77.000
|
$94.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
10,508.000
|
$0.250
|
$0.700
|
$0.500
|
$0.700
|
$0.450
|
$0.550
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
|
LF
|
2,627.000
|
$0.250
|
$0.700
|
$0.500
|
$0.750
|
$0.450
|
$0.550
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
10,508.000
|
$0.250
|
$0.700
|
$0.500
|
$0.750
|
$0.450
|
$0.550
|
|
|
WK ZN PAV MRK REMOV (W)(ARROW)
|
EA
|
10.000
|
$175.000
|
$230.000
|
$197.000
|
$250.000
|
$167.450
|
$200.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
7,880.000
|
$1.000
|
$2.300
|
$0.500
|
$6.000
|
$1.630
|
$1.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
8,406.000
|
$1.500
|
$2.300
|
$0.500
|
$6.000
|
$1.630
|
$2.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
400.000
|
$1.750
|
$2.000
|
$1.300
|
$2.000
|
$1.110
|
$1.300
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
10.000
|
$200.000
|
$350.000
|
$217.000
|
$350.000
|
$184.200
|
$220.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
1.000
|
$275.000
|
$375.000
|
$340.000
|
$350.000
|
$287.810
|
$342.000
|
|
REFL PAV MRK TY II (W) 6" (BRK)
|
LF
|
5,254.000
|
$0.300
|
$0.240
|
$0.400
|
$0.500
|
$0.360
|
$0.400
|
|
REFL PAV MRK TY II (W) 6" (SLD)
|
LF
|
10,508.000
|
$0.300
|
$0.350
|
$0.400
|
$0.500
|
$0.360
|
$0.400
|
|
REFL PAV MRK TY II (W) 8" (SLD)
|
LF
|
400.000
|
$0.550
|
$0.750
|
$0.400
|
$0.750
|
$0.450
|
$0.550
|
|
REFL PAV MRK TY II (W) (ARROW)
|
EA
|
12.000
|
$80.000
|
$100.000
|
$95.000
|
$100.000
|
$80.590
|
$96.000
|
|
REFL PAV MRK TY II (W) (WORD)
|
EA
|
1.000
|
$90.000
|
$120.000
|
$131.000
|
$125.000
|
$110.940
|
$132.000
|
|
REFL PAV MRK TY II (Y) 6" (BRK)
|
LF
|
4,515.000
|
$0.300
|
$0.220
|
$0.400
|
$0.500
|
$0.360
|
$0.400
|
|
REFL PAV MRK TY II (Y) 6" (SLD)
|
LF
|
11,108.000
|
$0.300
|
$0.350
|
$0.400
|
$0.500
|
$0.360
|
$0.400
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
|
LF
|
5,254.000
|
$0.750
|
$0.700
|
$0.800
|
$0.750
|
$0.730
|
$0.900
|
|
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
|
LF
|
4,515.000
|
$0.750
|
$0.700
|
$0.800
|
$0.750
|
$0.730
|
$0.900
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
11,108.000
|
$0.750
|
$1.180
|
$0.800
|
$1.250
|
$0.730
|
$0.900
|
|
|
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
|
LF
|
10,508.000
|
$0.800
|
$1.700
|
$2.000
|
$1.750
|
$1.500
|
$1.800
|
|
REFL PAV MRKR TY I-C
|
EA
|
151.000
|
$6.000
|
$14.000
|
$10.000
|
$15.000
|
$8.130
|
$9.700
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
344.000
|
$6.000
|
$11.500
|
$10.000
|
$15.000
|
$8.130
|
$9.700
|
|
|
D-GR HMA TY-B PG64-22 (EXEMPT)
|
TON
|
2,613.000
|
$115.000
|
$120.000
|
$123.000
|
$115.000
|
$141.500
|
$127.000
|
|
|
D-GR HMA TY-D PG 76-22 (EXEMPT)
|
TON
|
2,919.000
|
$135.000
|
$180.000
|
$185.000
|
$130.000
|
$152.500
|
$190.000
|
|
|
PFC-C PG76-22 SAC-A
|
TON
|
2,389.000
|
$185.000
|
$220.000
|
$228.000
|
$165.000
|
$217.400
|
$185.000
|
|
|
BONDING COURSE
|
GAL
|
2,169.000
|
$5.000
|
$4.500
|
$4.000
|
$6.000
|
$4.880
|
$5.000
|
|
|
UNDERSEAL COURSE
|
GAL
|
6,404.000
|
$5.000
|
$4.500
|
$4.000
|
$6.000
|
$6.700
|
$5.000
|
|
|
GEOGRID REINFORCE EMBANKMENTS (TY A)
|
SY
|
569.000
|
$5.000
|
$250.000
|
$97.000
|
$20.000
|
$23.800
|
$30.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
3.000
|
$10,000.000
|
$11,000.000
|
$30,000.000
|
$16,500.000
|
$9,742.500
|
$16,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
300.000
|
$170.000
|
$180.000
|
$185.000
|
$250.000
|
$265.210
|
$600.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
160.000
|
$95.000
|
$48.000
|
$95.000
|
$85.000
|
$83.350
|
$110.000
|
|
|
SUBSURFACE UTIL LOCATE (OUTSIDE RDBED)
|
EA
|
10.000
|
$1,500.000
|
$700.000
|
$2,000.000
|
$1,000.000
|
$1,500.000
|
$3,000.000
|
|
|
SUBSURFACE UTIL LOCATE (WITHIN RDBED)
|
EA
|
10.000
|
$3,500.000
|
$4,000.000
|
$2,000.000
|
$1,000.000
|
$3,000.000
|
$5,300.000
|
|
Totals: |
$4,492,163.700
|
$5,205,668.650
|
$5,351,122.530
|
$5,950,741.100
|
$6,527,364.730
|
$7,885,639.000
|