Show Job Controls
Bid Cobra

TRAVIS CR (0914-04-271)

Items: 75

County: TRAVIS
Length: N/A
Highway: CR
District: AUSTIN
Control Number: 0914-04-271
DBE Goal: N/A
Project: BR 1502(647)
Guaranty: N/A
Time: 141 WORKING DAYS
Engineer's Estimate: $935,814.35
Date: 05/08/2019 (7 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE & APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$935,814.35
$1,078,645.16
Over/Under Est: 15.26% $142,830.81
$1,084,884.75
Over/Under Est: 15.93% $149,070.40
Amt Left: 0.58% $6,239.59
$1,133,450.25
Over/Under Est: 21.12% $197,635.90
Amt Left: 5.08% $54,805.09
Delta: -4.48% -$48,565.50
Over/Under Est: 32.85% $307,433.27
Amt Left: 15.26% $164,602.46
Delta: -9.69% -$109,797.37
Over/Under Est: 35.28% $330,160.95
Amt Left: 17.37% $187,330.14
Delta: -1.83% -$22,727.68
Over/Under Est: 51.63% $483,153.25
Amt Left: 31.55% $340,322.44
Delta: -12.08% -$152,992.30

Bid Items & Bid Tabulations

75 Total 0 of 75
TRAVIS  |  CR  |  AUSTIN  |  0914-04-271  |  05/08/2019  |  $935,814.35  |  BR 1502(647)  |  REPLACE BRIDGE & APPROACHES  |  141 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SB CONTRACTORS LLC
CHASCO CONSTRUCTORS
DAN WILLIAMS COMPANY
CAPITAL EXCAVATION COMPANY
PROJECT ALLIED RESOURCES, LLC
ANGEL BROTHERS HOLDINGS CORP.
PREPARING ROW
AC 0.240 $6,400.000 $15,000.000 $30,000.000 $50,000.000 $20,000.000 $15,900.000 $50,000.000
PREPARING ROW
STA 4.000 $3,100.000 $3,000.000 $6,000.000 $15,000.000 $20,000.000 $23,900.000 $25,500.000
REMOVING CONC (DRIVEWAYS)
SY 80.000 $13.460 $15.000 $25.000 $15.000 $34.800 $23.100 $30.000
REMOVING CONC (MISC)
SY 12.000 $20.000 $20.000 $200.000 $35.000 $143.780 $54.000 $30.000
REMOVING STAB BASE AND ASPH PAV (2"-6")
SY 513.000 $3.750 $4.000 $15.000 $5.000 $5.390 $4.100 $15.000
EXCAVATION (ROADWAY)
CY 300.000 $6.690 $10.000 $40.000 $25.000 $35.840 $19.600 $12.000
EXCAVATION (CHANNEL)
CY 2,381.000 $10.660 $12.000 $25.000 $15.000 $22.650 $15.600 $35.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 200.000 $6.750 $10.000 $40.000 $25.000 $38.620 $19.800 $23.000
FURNISHING AND PLACING TOPSOIL (4")
SY 268.000 $0.730 $6.000 $6.000 $2.500 $19.560 $11.200 $12.000
BROADCAST SEED (TEMP) (WARM)
SY 268.000 $0.100 $1.870 $2.000 $1.700 $1.680 $1.420 $2.000
CELL FBR MLCH SEED(PERM)(URBAN)(CLAY)
SY 1,454.000 $0.320 $0.350 $1.000 $0.600 $0.550 $0.980 $0.600
VEGETATIVE WATERING
MG 8.000 $14.930 $55.000 $500.000 $15.000 $81.440 $252.000 $45.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 268.000 $0.900 $1.500 $2.000 $1.500 $1.500 $1.320 $1.600
SOIL RETENTION BLANKETS (CL 2) (TY F)
SY 1,186.000 $3.600 $6.000 $2.000 $1.500 $1.350 $2.160 $1.400
D-GR HMA(SQ) TY-B PG64-22
TON 422.000 $80.000 $125.000 $100.000 $110.000 $105.000 $114.000 $113.000
D-GR HMA(SQ) TY-D SAC-B PG70-22
TON 53.000 $109.720 $235.000 $190.000 $420.000 $190.000 $157.000 $200.000
CEM STABIL BKFL
CY 100.000 $116.350 $135.000 $160.000 $150.000 $160.000 $247.000 $200.000
TRENCH EXCAVATION PROTECTION
LF 360.000 $3.500 $5.000 $5.000 $1.000 $5.000 $4.850 $40.000
DRILL SHAFT (36 IN)
LF 241.000 $152.150 $210.000 $250.000 $225.000 $220.000 $251.000 $300.000
CL C CONC (ABUT)
CY 43.600 $848.950 $800.000 $850.000 $900.000 $900.000 $1,230.000 $1,000.000
CL C CONC (BENT)
CY 30.800 $850.000 $900.000 $1,100.000 $1,150.000 $1,700.000 $1,380.000 $1,000.000
CL C CONC (COLUMN)
CY 10.210 $858.300 $1,100.000 $1,600.000 $1,150.000 $1,000.000 $1,220.000 $1,400.000
REINF CONC SLAB
SF 6,120.000 $18.000 $19.000 $20.000 $20.000 $18.000 $19.300 $25.000
APPROACH SLAB
CY 67.000 $450.000 $400.000 $430.000 $500.000 $550.000 $674.000 $650.000
PRESTR CONC GIRDER (TX28)
LF 720.000 $129.000 $175.000 $156.000 $165.000 $140.000 $153.000 $182.000
RIPRAP (CONC)(4 IN)
CY 1.650 $414.860 $1,200.000 $1,750.000 $1,200.000 $850.000 $743.000 $750.000
RIPRAP (STONE PROTECTION)(21 IN)
CY 281.000 $120.000 $135.000 $125.000 $130.000 $160.000 $163.000 $165.000
RIPRAP (MOW STRIP)(4 IN)
CY 14.050 $440.490 $400.000 $475.000 $450.000 $700.000 $640.000 $530.000
RAIL (TY T223)
LF 404.000 $95.500 $110.000 $115.000 $110.000 $90.000 $142.000 $118.000
ARMOR JOINT (SEALED)
LF 70.000 $85.000 $80.000 $95.000 $95.000 $100.000 $138.000 $125.000
CMP (GAL STL 24 IN)
LF 83.000 $85.240 $65.000 $75.000 $55.000 $70.000 $109.000 $100.000
SET (TY II) (24 IN) (CMP) (4: 1) (P)
EA 2.000 $1,125.000 $1,800.000 $1,800.000 $800.000 $1,300.000 $1,690.000 $2,700.000
REMOV STR (PIPE)
LF 53.000 $21.950 $21.000 $50.000 $16.000 $30.000 $22.200 $35.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $25,000.000 $15,000.000 $29,323.000 $15,000.000 $34,000.000 $27,200.000 $30,000.000
MOBILIZATION
LS 1.000 $68,520.090 $100,000.000 $90,000.000 $100,000.000 $120,000.000 $140,000.000 $120,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $1,000.000 $4,000.000 $1,500.000 $6,500.000 $1,000.000 $1,350.000 $600.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 80.000 $27.780 $25.000 $25.000 $28.000 $27.500 $56.000 $29.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 155.000 $45.000 $45.000 $45.000 $55.000 $55.000 $63.000 $55.000
ROCK FILTER DAMS (REMOVE)
LF 235.000 $9.640 $13.000 $5.000 $15.000 $15.000 $16.100 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 1,055.000 $17.850 $15.000 $20.000 $12.000 $12.000 $10.000 $12.000
CONSTRUCTION EXITS (REMOVE)
SY 1,055.000 $7.870 $10.000 $5.000 $10.000 $10.000 $3.640 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 805.000 $2.400 $4.000 $4.000 $2.150 $2.150 $4.480 $2.200
TEMP SEDMT CONT FENCE (REMOVE)
LF 805.000 $0.630 $0.750 $0.500 $0.500 $0.150 $1.070 $0.200
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 176.000 $16.800 $5.000 $5.000 $4.500 $4.500 $5.900 $4.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 176.000 $1.350 $1.000 $0.500 $0.500 $0.500 $1.260 $0.500
DRIVEWAYS (CONC)
SY 56.000 $70.000 $60.000 $96.000 $95.000 $150.000 $110.000 $130.000
MTL W-BEAM GD FEN (TIM POST)
LF 250.000 $20.630 $20.000 $21.000 $18.500 $18.000 $21.600 $22.000
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $1,320.740 $900.000 $950.000 $875.000 $850.000 $1,020.000 $1,000.000
SHORT RADIUS
LF 70.000 $36.550 $25.000 $25.000 $26.500 $26.000 $31.200 $28.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,146.110 $925.000 $975.000 $1,000.000 $950.000 $1,140.000 $1,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $2,667.300 $2,630.000 $2,775.000 $2,500.000 $2,390.000 $2,870.000 $2,800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 3.000 $539.020 $555.000 $580.000 $600.000 $450.000 $509.000 $600.000
REMOVE SM RD SN SUP&AM
EA 6.000 $81.700 $125.000 $130.000 $125.000 $50.000 $78.000 $100.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 8.000 $21.960 $13.000 $15.000 $20.000 $10.000 $24.000 $14.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 3.000 $15.000 $16.250 $17.000 $22.000 $10.000 $26.400 $17.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 918.000 $0.330 $1.500 $3.000 $1.750 $3.000 $3.600 $3.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 1,000.000 $0.340 $1.500 $3.000 $1.750 $3.000 $3.600 $3.000
RE PM W/RET REQ TY II (W) 4" (SLD)
LF 918.000 $0.110 $1.200 $1.000 $1.250 $0.500 $2.580 $0.500
RE PM W/RET REQ TY II (Y) 4" (SLD)
LF 1,000.000 $0.120 $1.200 $1.000 $1.250 $0.500 $2.580 $0.500
REFL PAV MRKR TY II-A-A
EA 26.000 $2.880 $50.000 $10.000 $55.000 $10.000 $24.000 $10.000
ELIM EXT PAV MRK & MRKS (4")
LF 22.000 $0.440 $50.000 $10.000 $55.000 $10.000 $18.000 $10.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $17,000.000 $2,800.000 $7,000.000 $8,724.450 $20,400.000 $8,500.000
TMA (STATIONARY)
EA 2.000 $5,000.000 $5,000.000 $750.000 $1.000 $30,000.000 $706.000 $3,000.000
TMA (MOBILE OPERATION)
DAY 164.000 $150.000 $150.000 $1.000 $1.000 $100.000 $1.000 $75.000
JACK BORE ASTM A134 STEEL MIN THICK 3/8
LF 110.000 $600.000 $525.000 $600.000 $750.000 $600.000 $312.000 $720.000
PIPE, 2" DIA. HDPE (ALL DEPTHS)
LF 6.000 $40.000 $50.000 $65.000 $150.000 $200.000 $181.000 $390.000
PIPE, 6" DIA. DI CLASS 350 (ALL DEPTHS)
LF 14.000 $85.000 $70.000 $100.000 $250.000 $150.000 $202.000 $200.000
FCT RESTR JT PIPE,12"DIA. CL 350 DI
LF 360.000 $165.000 $155.000 $150.000 $125.000 $150.000 $149.000 $280.000
WET CONNECTIONS, 12" DIA. X 12" DIA.
EA 2.000 $5,000.000 $8,500.000 $2,500.000 $3,500.000 $6,300.000 $8,060.000 $3,000.000
DUCTILE IRON FITTINGS 4" THROUGH 12"
TON 0.350 $7,450.000 $9,000.000 $20,000.000 $10,000.000 $7,000.000 $18,100.000 $32,000.000
VALVES, GATE VALVE TYPE, 6" DIA.
EA 1.000 $1,650.000 $2,500.000 $1,150.000 $1,200.000 $2,500.000 $1,400.000 $1,500.000
VALVES, GATE VALVE TYPE, 12" DIA.
EA 1.000 $2,700.000 $3,500.000 $2,500.000 $3,500.000 $3,500.000 $15,100.000 $4,300.000
FIRE HYDRANTS
EA 1.000 $4,800.000 $6,500.000 $3,500.000 $5,500.000 $5,000.000 $8,900.000 $5,200.000
AUTO COMBO AIR AND VAC RELEASE VALVE 2"
EA 1.000 $4,000.000 $2,500.000 $3,500.000 $3,500.000 $4,500.000 $1,260.000 $3,300.000
ADDITIONAL BURY DEPTH(2" ARV AND 6" FH)
LF 18.000 $800.000 $120.000 $150.000 $150.000 $120.000 $204.000 $210.000
Totals: $935,814.346 $1,078,645.160 $1,084,884.750 $1,133,450.250 $1,243,247.620 $1,265,975.300 $1,418,967.600