County: TRAVIS Highway: VA Date: 04/04/2023 (1 year ago) Engineer's Estimate: $1,898,500 Control Number: 0914-00-476
Project: C 914-00-476 District: AUSTIN Time: 87 WORKING DAYS Type: LANDSCAPE DEVELOPMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,898,499.60
TIGHT LINE CONSTRUCTION, LLC   $1,519,370.00 1
-19.97% | -$379,129.60
APEX LANDSCAPE & IRRIGATION, LLC   $1,669,299.30 2
-12.07% | -$229,200.30
9.87% | $149,929.30
ENCINO LANDSCAPE, INC.   $1,789,921.13 3
-5.72% | -$108,578.47
17.81% | $270,551.13
7.23% | $120,621.83
USA DT SERVICES, INC.   $2,064,069.13 4
8.72% | $165,569.53
35.85% | $544,699.13
15.32% | $274,148.00

Bid Items

Items: 29, 0 filtered
TRAVIS VA  |  AUSTIN  |  0914-00-476  |  04/04/2023  |  $1,898,500  |  C 914-00-476  |  LANDSCAPE DEVELOPMENT  |  87 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate TIGHT LINE CONSTRUCTION, LLC APEX LANDSCAPE & IRRIGATION, LLC ENCINO LANDSCAPE, INC. USA DT SERVICES, INC.
100 6008 PREPARING ROW (TREE) (0" TO 6" DIA) EA 14.000 $500.000 $550.000 $215.000 $500.000 $304.410
100 6010 PREPARING ROW (TREE)(10" TO 48" DIA) EA 3.000 $2,300.000 $5,000.000 $1,085.000 $2,000.000 $304.410
158 6006 SPEC EXCAV WORK (VEHICLE) CY 214.000 $120.000 $75.000 $45.000 $25.000 $18.570
160 6008 FURNISHING AND PLACING TOPSOIL (12") SY 30.000 $120.000 $150.000 $20.000 $100.000 $452.030
170 6002 IRRIGATION SYSTEM (TY I) LS 1.000 $262,500.000 $100,000.000 $240,000.000 $150,000.000 $129,558.290
170 6003 IRRIGATION SYSTEM (TY II) LS 1.000 $164,000.000 $100,000.000 $155,000.000 $250,000.000 $129,558.290
180 6001 WILDFLOWER SEEDING AC 168.000 $1,200.000 $1,000.000 $1,000.000 $1,500.000 $3,786.470
192 6007 PLANT MATERIAL (45-GAL) EA 44.000 $500.000 $400.000 $400.000 $450.000 $482.620
192 6016 PLANT BED PREPARATION SY 948.000 $5.000 $10.000 $25.000 $10.000 $18.570
192 6023 PLANT MATERIAL (15 GAL) (TREE) EA 40.000 $140.000 $150.000 $135.000 $150.000 $259.730
192 6024 PLANT MATERIAL (30 GAL) (TREE) EA 323.000 $280.000 $325.000 $290.000 $250.000 $473.750
192 6027 PLANT MATERIAL (100 GAL) (TREE) EA 78.000 $1,200.000 $1,500.000 $1,300.000 $900.000 $718.770
192 6028 PLANT MATERIAL (1 GAL) (SHRUB) EA 13,771.000 $15.000 $10.000 $12.000 $15.000 $9.977
192 6030 PLANT MATERIAL (3 GAL) (SHRUB) EA 82.000 $30.000 $30.000 $30.000 $30.000 $44.135
192 6031 PLANT MATERIAL (5 GAL) (SHRUB) EA 181.000 $50.000 $45.000 $40.000 $35.000 $36.970
192 6067 LANDSCAPE EDGE (TYPE I) LF 712.000 $20.000 $35.000 $25.000 $20.000 $6.980
192 6068 LANDSCAPE EDGE (TYPE II) LF 8,992.000 $50.000 $25.000 $32.400 $25.000 $6.980
192 6069 LANDSCAPE EDGE (TYPE III) LF 16.000 $70.000 $100.000 $28.000 $50.000 $6.980
193 6001 PLANT MAINTENANCE MO 24.000 $1,000.000 $3,500.000 $3,000.000 $4,000.000 $9,994.330
193 6006 VEGETATIVE WATERING MG 350.000 $45.000 $1.000 $10.100 $20.000 $124.000
193 6007 IRRIGATION SYSTEM OPER AND MAINT MO 24.000 $800.000 $4,000.000 $2,000.000 $2,000.000 $1,650.500
420 6005 CL A CONC (CURB OUTLET)(TY I) EA 3.000 $2,500.000 $1,500.000 $2,000.000 $2,000.000 $3,725.810
500 6001 MOBILIZATION LS 1.000 $169,863.600 $160,000.000 $162,000.000 $200,000.000 $196,457.630
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $5,000.000 $6,500.000 $10,000.000 $5,000.000 $10,000.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 1,113.000 $5.500 $8.000 $4.000 $10.000 $6.290
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 1,113.000 $1.500 $2.000 $0.500 $0.010 $0.180
752 6024 TREE TRIMMING (0"-12") EA 85.000 $300.000 $250.000 $50.000 $300.000 $305.000
752 6025 TREE TRIMMING (12"-24") EA 23.000 $600.000 $400.000 $100.000 $500.000 $305.000
6185 6002 TMA (STATIONARY) DAY 80.000 $180.000 $350.000 $5.000 $500.000 $520.000
Totals: $1,898,499.60 $1,519,370.00 $1,669,299.30 $1,789,921.13 $2,064,069.14