Job Info for 0015-11-063

County: TRAVIS Highway: SL 275 Date: 03/07/2017 (7 years ago) Engineer's Estimate: $167,902 Control Number: 0015-11-063
Project: BR 2017(787) District: AUSTIN Time: 40 WORKING DAYS Type: UPGRADE BRIDGE AND APPROACH RAILING

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $167,902.28
OPPORTUNITY EXCAVATION/CONCRETE, LLC   $213,085.50 1
26.91% | $45,183.22
TCB CONSTRUCTION, INC   $216,786.65 2
29.11% | $48,884.37
1.74% | $3,701.15
DAN WILLIAMS COMPANY   $225,000.00 3
34.01% | $57,097.72
5.59% | $11,914.50
3.79% | $8,213.35
RESTEK, INC.   $254,429.00 4
51.53% | $86,526.72
19.4% | $41,343.50
13.08% | $29,429.00
SCR CIVIL CONSTRUCTION, LLC   $294,949.30 5
75.67% | $127,047.02
38.42% | $81,863.80
15.93% | $40,520.30
BXB GROUP INCORPORATION   $296,439.30 6
76.55% | $128,537.02
39.12% | $83,353.80
0.51% | $1,490.00

Bid Items

Items: 33, 0 filtered
TRAVIS SL 275  |  AUSTIN  |  0015-11-063  |  03/07/2017  |  $167,902  |  BR 2017(787)  |  UPGRADE BRIDGE AND APPROACH RAILING  |  40 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate OPPORTUNITY EXCAVATION/CONCRETE, LLC TCB CONSTRUCTION, INC DAN WILLIAMS COMPANY RESTEK, INC. SCR CIVIL CONSTRUCTION, LLC BXB GROUP INCORPORATION
100 6001 PREPARING ROW AC 0.580 $9,500.000 $2,200.000 $15,000.000 $7,000.000 $15,000.000 $2,500.000 $18,100.000
132 6011 EMBANKMENT (ORIGINAL)(ORD COMP)(TY B) CY 19.800 $50.000 $30.000 $135.000 $80.000 $50.000 $50.000 $348.000
168 6001 VEGETATIVE WATERING MG 3.000 $50.000 $125.000 $100.000 $8.000 $150.000 $100.000 $200.000
169 6003 SOIL RETENTION BLANKETS (CL 1) (TY C) SY 44.000 $2.400 $3.750 $5.750 $8.000 $7.500 $10.000 $9.000
420 6074 CL C CONC (MISC) CY 11.800 $700.000 $350.000 $550.000 $750.000 $1,500.000 $3,600.000 $2,440.000
432 6003 RIPRAP (CONC)(6 IN) CY 3.100 $700.000 $500.000 $550.000 $900.000 $1,500.000 $1,300.000 $1,338.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 48.000 $470.000 $225.000 $550.000 $585.000 $750.000 $500.000 $445.000
450 6029 RAIL (TY C1W) LF 97.000 $200.000 $325.000 $216.130 $300.000 $280.000 $590.000 $272.000
450 6042 RAIL (TY PR1) LF 81.000 $89.000 $100.000 $103.680 $110.000 $135.000 $100.000 $190.000
451 6015 RETROFIT RAIL (TY T551) LF 10.000 $280.000 $350.000 $150.000 $225.050 $250.000 $800.000 $250.000
496 6099 REMOVE STR (RAIL) LF 72.000 $25.000 $50.000 $30.000 $15.000 $150.000 $20.000 $27.000
500 6001 MOBILIZATION LS 1.000 $15,300.080 $40,000.000 $22,000.000 $23,000.000 $10,000.000 $29,000.000 $29,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 $3,500.000 $2,500.000 $7,499.920 $7,500.000 $2,500.000 $2,000.000 $4,068.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 40.000 $5.000 $1.500 $5.000 $8.000 $7.500 $10.000 $13.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 40.000 $2.000 $1.000 $2.000 $1.500 $3.750 $2.500 $5.000
512 6009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) LF 220.000 $35.000 $75.000 $62.500 $30.000 $65.000 $60.000 $112.000
512 6010 PORT CTB (FUR & INST)(LOW PROF)(TY 2) LF 40.000 $35.000 $75.000 $72.500 $34.000 $75.000 $60.000 $162.000
512 6033 PORT CTB (MOVE)(LOW PROF)(TY 1) LF 160.000 $10.000 $30.000 $10.000 $15.000 $20.000 $40.000 $69.000
512 6034 PORT CTB (MOVE)(LOW PROF)(TY 2) LF 40.000 $15.000 $30.000 $10.000 $25.000 $25.000 $40.000 $59.000
512 6057 PORT CTB (REMOVE)(LOW PROF)(TY 1) LF 220.000 $15.000 $45.000 $15.000 $12.000 $20.000 $60.000 $37.000
512 6058 PORT CTB (REMOVE)(LOW PROF)(TY 2) LF 40.000 $15.000 $30.000 $15.000 $15.000 $25.000 $60.000 $58.000
531 6003 CONC SIDEWALKS (6") SY 126.700 $75.000 $85.000 $126.000 $75.000 $150.000 $219.000 $113.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 500.000 $19.000 $35.000 $25.000 $26.000 $28.200 $18.000 $23.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 5.000 $1,400.000 $1,800.000 $1,750.000 $2,500.000 $2,050.000 $1,200.000 $1,813.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 4.000 $1,050.000 $1,700.000 $1,000.000 $1,200.000 $1,350.000 $900.000 $1,250.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 657.000 $2.300 $5.000 $2.000 $3.000 $4.500 $1.000 $5.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 3.000 $170.000 $500.000 $175.000 $200.000 $187.500 $125.000 $240.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 3.000 $2,280.000 $2,700.000 $2,750.000 $2,700.000 $3,325.000 $2,350.000 $2,992.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 2.000 $300.000 $500.000 $500.000 $325.000 $337.500 $250.000 $407.000
658 6015 INSTL DEL ASSM (D-SW)SZ (BRF)GF1 EA 12.000 $22.000 $12.000 $20.000 $13.000 $20.000 $20.000 $17.000
658 6047 INSTL OM ASSM (OM-2Y)(WC)GND EA 4.000 $60.000 $18.000 $30.000 $40.000 $50.000 $55.000 $63.000
752 6008 TREE REMOVAL (24" - 30" DIA) EA 1.000 $1,500.000 $300.000 $3,750.000 $5,000.000 $1,500.000 $2,000.000 $1,100.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $7,000.000 $2,400.000 $6,750.000 $10,500.000 $12,250.000 $7,200.000 $12,700.000
Totals: $167,902.28 $213,085.50 $216,786.65 $225,000.00 $254,429.00 $294,949.30 $296,439.30