TOM GREEN RM 584 (2574-01-050)
Items: 15
County: TOM GREEN
Length: N/A
Highway: RM 584
District: SAN ANGELO
Control Number: 2574-01-050
DBE Goal: N/A
Project: BR 2023(405)
Guaranty: N/A
Time: 143 WORKING DAYS
Engineer's Estimate: $3,162,999.00
Date: 02/02/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (9)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,162,999.00 | |||
| $3,706,380.00 |
17.18%
$543,381.00
|
|||
| $3,750,980.56 |
18.59%
$587,981.56
|
1.2%
$44,600.56
|
||
| $3,793,465.00 |
19.93%
$630,466.00
|
2.35%
$87,085.00
|
-1.13%
-$42,484.44
|
|
| $3,998,495.00 |
26.41%
$835,496.00
|
7.88%
$292,115.00
|
-5.40%
-$205,030.00
|
|
| $4,297,200.00 |
35.86%
$1,134,201.00
|
15.94%
$590,820.00
|
-7.47%
-$298,705.00
|
|
| $4,434,115.00 |
40.19%
$1,271,116.00
|
19.63%
$727,735.00
|
-3.19%
-$136,915.00
|
|
| $4,435,059.00 |
40.22%
$1,272,060.00
|
19.66%
$728,679.00
|
-0.02%
-$944.00
|
|
| $4,997,224.00 |
57.99%
$1,834,225.00
|
34.83%
$1,290,844.00
|
-12.68%
-$562,165.00
|
|
| $5,387,400.00 |
70.33%
$2,224,401.00
|
45.35%
$1,681,020.00
|
-7.81%
-$390,176.00
|
E
Engineer's Estimate
$3,162,999.00
1
Awarded
$3,706,380.00
Over/Under Est:
17.18%
$543,381.00
$3,750,980.56
Over/Under Est:
18.59%
$587,981.56
Amt Left:
1.2%
$44,600.56
$3,793,465.00
Over/Under Est:
19.93%
$630,466.00
Amt Left:
2.35%
$87,085.00
Delta:
-1.13%
-$42,484.44
$3,998,495.00
Over/Under Est:
26.41%
$835,496.00
Amt Left:
7.88%
$292,115.00
Delta:
-5.40%
-$205,030.00
$4,297,200.00
Over/Under Est:
35.86%
$1,134,201.00
Amt Left:
15.94%
$590,820.00
Delta:
-7.47%
-$298,705.00
$4,434,115.00
Over/Under Est:
40.19%
$1,271,116.00
Amt Left:
19.63%
$727,735.00
Delta:
-3.19%
-$136,915.00
$4,435,059.00
Over/Under Est:
40.22%
$1,272,060.00
Amt Left:
19.66%
$728,679.00
Delta:
-0.02%
-$944.00
$4,997,224.00
Over/Under Est:
57.99%
$1,834,225.00
Amt Left:
34.83%
$1,290,844.00
Delta:
-12.68%
-$562,165.00
$5,387,400.00
Over/Under Est:
70.33%
$2,224,401.00
Amt Left:
45.35%
$1,681,020.00
Delta:
-7.81%
-$390,176.00
| Subcontractor | Percentage | Amount |
|---|---|---|
| ROYAL BRIDGE INC. | 40.30% | $1,375,828.67 |
| Total: | 40.30% | $1,375,828.67 |
Bid Items & Bid Tabulations
15
Total
0 of 15