Show Job Controls
Bid Cobra

TOM GREEN CS (2574-01-049)

Items: 28

County: TOM GREEN
Length: N/A
Highway: CS
District: SAN ANGELO
Control Number: 2574-01-049
DBE Goal: N/A
Project: F 2021(716)
Guaranty: N/A
Time: 132 WORKING DAYS
Engineer's Estimate: $373,364.00
Date: 08/05/2021 (4 years ago)
Contract Number: N/A
Type: TRAFFIC SIGNAL IMPROVEMENTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (1)
E
Engineer's Estimate
$373,364.00
$538,601.00
Over/Under Est: 44.26% $165,237.00

Bid Items & Bid Tabulations

28 Total 0 of 28
TOM GREEN  |  CS  |  SAN ANGELO  |  2574-01-049  |  08/05/2021  |  $373,364.00  |  F 2021(716)  |  TRAF SIGNAL IMPRVS  |  132 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TI-ZACK CONCRETE, INC.
EMBANKMENT (FINAL)(ORD COMP)(TY D)
CY 0.500 $9.000 $65.000
CUT & RESTORE ASPH PAVING
SY 26.000 $140.000 $125.000
CL B CONC (MISC)
CY 5.000 $600.000 $1,500.000
RIPRAP (CONC)(4 IN)
CY 1.000 $798.000 $1,500.000
MOBILIZATION
LS 1.000 $39,000.000 $50,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $5,500.000 $2,000.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 140.000 $9.000 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 140.000 $2.000 $1.000
CONC CURB & GUTTER (TY II)
LF 9.000 $28.000 $85.000
CONC SIDEWALKS (5")
SY 29.500 $67.000 $185.000
CURB RAMPS (TY 1)
SY 72.000 $145.000 $225.000
CURB RAMPS (TY 7)
SY 15.000 $94.000 $225.000
CONDT (PVC) (SCH 40) (2")
LF 304.000 $20.000 $45.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 251.000 $50.000 $55.000
ELEC CONDR (NO.8) BARE
LF 654.000 $1.400 $3.500
GROUND BOX TY C (162911)W/APRON
EA 4.000 $1,200.000 $2,500.000
REMOVE GROUND BOX
EA 1.000 $250.000 $300.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 2,782.000 $6.500 $15.000
PAVEMENT SEALER 24"
LF 2,782.000 $1.500 $3.000
ELIM EXT PAV MRK & MRKS (24")
LF 3,572.000 $3.000 $7.000
PED SIG SEC (LED)(COUNTDOWN)
EA 52.000 $550.000 $850.000
TRF SIG CBL (TY A)(12 AWG)(2 CONDR)
LF 20.000 $1.600 $5.500
TRF SIG CBL (TY A)(12 AWG)(7 CONDR)
LF 2,547.000 $2.200 $11.000
PED POLE ASSEMBLY
EA 22.000 $2,600.000 $4,000.000
PED DETECT PUSH BUTTON (APS)
EA 56.000 $1,000.000 $1,500.000
PED DETECTOR CONTROLLER UNIT
EA 9.000 $3,800.000 $8,000.000
TMA (STATIONARY)
DAY 154.000 $200.000 $25.000
TMA (MOBILE OPERATION)
DAY 14.000 $200.000 $25.000
Totals: $373,364.000 $538,601.000