Show Job Controls
Bid Cobra

TOM GREEN VA (0907-00-223)

Items: 11

County: TOM GREEN
Length: N/A
Highway: VA
District: SAN ANGELO
Control Number: 0907-00-223
DBE Goal: N/A
Project: F 2021(513)
Guaranty: N/A
Time: 28 WORKING DAYS
Engineer's Estimate: $1,121,543.42
Date: 05/05/2021 (5 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (10)
E
Engineer's Estimate
$1,121,543.42
$1,017,759.60
Over/Under Est: -9.25% -$103,783.82
$1,050,740.10
Over/Under Est: -6.31% -$70,803.32
Amt Left: 3.24% $32,980.50
$1,097,757.00
Over/Under Est: -2.12% -$23,786.42
Amt Left: 7.86% $79,997.40
Delta: -4.47% -$47,016.90
Over/Under Est: -1.66% -$18,591.22
Amt Left: 8.37% $85,192.60
Delta: -0.47% -$5,195.20
$1,104,730.20
Over/Under Est: -1.5% -$16,813.22
Amt Left: 8.55% $86,970.60
Delta: -0.16% -$1,778.00
Over/Under Est: 0.37% $4,109.93
Amt Left: 10.6% $107,893.75
Delta: -1.89% -$20,923.15
Over/Under Est: 0.61% $6,873.84
Amt Left: 10.87% $110,657.66
Delta: -0.25% -$2,763.91
$1,138,369.77
Over/Under Est: 1.5% $16,826.35
Amt Left: 11.85% $120,610.17
Delta: -0.88% -$9,952.51
Over/Under Est: 12.25% $137,380.28
Amt Left: 23.7% $241,164.10
Delta: -10.59% -$120,553.93
Over/Under Est: 23.65% $265,247.08
Amt Left: 36.26% $369,030.90
Delta: -10.16% -$127,866.80

Bid Items & Bid Tabulations

11 Total 0 of 11
TOM GREEN  |  VA  |  SAN ANGELO  |  0907-00-223  |  05/05/2021  |  $1,121,543.42  |  F 2021(513)  |  HAZARD ELIM & SAFETY  |  28 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PMI PAVEMENT MARKING, LLC
L&L COMPANY
STRIPE-A-ZONE, INC.
CENTERLINE TECHNOLOGIES, LLC
STRIPE LINES, INC.
D. I. J. CONSTRUCTION, INC.
DOUBLE A CONTRACTING, L.P.
BATTERSON, LLP
TRP CONSTRUCTION GROUP, LLC
INTERSTATE BARRICADES & MARKINGS, INC.
MOBILIZATION
LS 1.000 $100,000.000 $2,000.000 $1.000 $14,000.000 $1.000 $10,000.000 $10,000.000 $92,000.000 $20,000.000 $30,000.000 $50,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $3,000.000 $125.000 $1.000 $1.000 $1.000 $250.000 $100.000 $1.000 $1.000 $500.000 $1,500.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 422.000 $0.710 $1.500 $2.000 $0.750 $1.000 $0.500 $0.600 $0.980 $0.860 $1.000 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 779.000 $6.000 $6.500 $5.000 $6.000 $7.000 $6.000 $6.450 $5.000 $5.000 $10.000 $10.000
PAVEMENT SEALER 24"
LF 195.000 $1.000 $8.500 $4.000 $1.500 $1.000 $1.500 $2.500 $2.000 $1.150 $5.000 $5.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 1,290.000 $0.220 $0.850 $2.000 $0.450 $0.400 $0.500 $0.330 $0.450 $0.310 $0.500 $0.350
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 1,394,300.000 $0.390 $0.405 $0.400 $0.420 $0.420 $0.410 $0.430 $0.380 $0.420 $0.470 $0.450
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 138,060.000 $0.400 $0.410 $0.410 $0.425 $0.420 $0.420 $0.440 $0.445 $0.420 $0.520 $0.450
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 733,600.000 $0.400 $0.405 $0.410 $0.425 $0.420 $0.420 $0.420 $0.405 $0.420 $0.470 $0.450
PREFORMED CENTERLINE RUMBLE STRIP
LF 38,050.000 $3.000 $2.100 $3.350 $3.200 $3.800 $3.950 $3.700 $3.750 $4.250 $3.750 $8.000
TMA (MOBILE OPERATION)
DAY 70.000 $50.000 $125.000 $1.000 $1.000 $1.000 $5.000 $1.000 $1.000 $1.000 $50.000 $1.000
Totals: $1,121,543.420 $1,017,759.600 $1,050,740.100 $1,097,757.000 $1,102,952.200 $1,104,730.200 $1,125,653.350 $1,128,417.260 $1,138,369.770 $1,258,923.700 $1,386,790.500