Show Job Controls
Bid Cobra

TOM GREEN VA (0907-00-201)

Items: 63

County: TOM GREEN
Length: N/A
Highway: VA
District: SAN ANGELO
Control Number: 0907-00-201
DBE Goal: N/A
Project: C 907-00-201
Guaranty: N/A
Time: 498 WORKING DAYS
Engineer's Estimate: $4,359,164.98
Date: 08/06/2020 (5 years ago)
Contract Number: N/A
Type: SIDEWALKS AND CURB RAMPS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$4,359,164.98
$3,905,830.24
Over/Under Est: -10.4% -$453,334.74
$4,194,950.10
Over/Under Est: -3.77% -$164,214.88
Amt Left: 7.4% $289,119.86
$4,790,041.50
Over/Under Est: 9.88% $430,876.52
Amt Left: 22.64% $884,211.26
Delta: -14.19% -$595,091.40
$5,539,676.89
Over/Under Est: 27.08% $1,180,511.91
Amt Left: 41.83% $1,633,846.65
Delta: -15.65% -$749,635.39
Over/Under Est: 39.03% $1,701,414.56
Amt Left: 55.17% $2,154,749.30
Delta: -9.40% -$520,902.65
Subcontractor Percentage Amount
JML CONSTRUCTION & SERVICES, LLC 9.67% $392,486.22
HRM LIBERTY CONCRETE & CONSTRUCTION, LLC 7.84% $318,210.13
FUTRA-VEST CONSTRUCTION 7.08% $287,363.23
2H STRIPING, LIMITED LIABILITY COMPANY 2.35% $95,381.86
FC TRAFFIC CONTROL, INC. 1.07% $43,429.19
Total: 28.01% $1,136,870.63

Bid Items & Bid Tabulations

63 Total 0 of 63
TOM GREEN  |  VA  |  SAN ANGELO  |  0907-00-201  |  08/06/2020  |  $4,359,164.98  |  C 907-00-201  |  SIDEWALKS AND CURB RAMPS  |  498 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SOUTH TEXAS ILLUMINATION, LLC
TI-ZACK CONCRETE, INC.
FNH CONSTRUCTION, LLC
ENCINO LANDSCAPE, INC.
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
PREP ROW (TREE)(LESS THAN 24" DIA)
EA 7.000 $1,500.000 $715.000 $750.000 $3,000.000 $1,000.000 $1,263.300
PREP ROW (TREE PRUNING)
EA 10.000 $1,000.000 $605.000 $100.000 $3,000.000 $800.000 $760.510
REMOVING CONC (DRIVEWAYS)
SY 4,745.000 $16.000 $15.130 $20.000 $20.000 $20.000 $33.490
REMOVING CONC (CURB OR CURB & GUTTER)
LF 2,921.000 $11.000 $12.850 $8.000 $20.000 $20.000 $7.770
REMOVING CONC (SIDEWALK OR RAMP)
SY 277.000 $18.000 $19.310 $20.000 $20.000 $20.000 $32.580
REMOVING CONC (FLUME)
SY 6.000 $12.000 $117.000 $100.000 $20.000 $20.000 $84.780
REMOVE CONC (MISC)
EA 1.000 $1,000.000 $2,500.500 $600.000 $200.000 $1,000.000 $4,998.210
REMOVING STAB BASE AND ASPH PAV(0"-16")
SY 1,768.000 $8.000 $19.310 $20.000 $20.000 $20.000 $43.570
EXCAVATION (SPECIAL)
CY 500.000 $15.000 $17.550 $12.000 $30.000 $20.000 $43.740
EMBANKMENT (VEHICLE)(ORD COMP)(TY A)
CY 100.000 $30.000 $39.780 $50.000 $35.000 $20.000 $61.320
FURNISHING AND PLACING TOPSOIL (4")
SY 277.000 $3.000 $4.140 $5.000 $8.000 $20.000 $15.570
CELL FBR MLCH SEED(PERM)(URBAN)(CLAY)
SY 21,756.000 $0.500 $0.940 $0.550 $0.500 $1.000 $1.970
LRA PAV TY-I GR-D
TON 100.000 $180.000 $140.800 $150.000 $200.000 $300.000 $259.920
CUT & RESTORE ASPH PAVING
SY 10.000 $150.000 $130.000 $100.000 $200.000 $400.000 $456.790
CL A CONC (MISC)
CY 35.000 $650.000 $751.600 $1,900.000 $1,500.000 $500.000 $921.250
CL B CONC (MISC)
CY 50.000 $651.000 $692.000 $650.000 $1,500.000 $500.000 $997.260
RETAINING WALL (CAST - IN - PLACE)
SF 4,086.000 $75.000 $110.000 $40.000 $85.000 $100.000 $50.220
RIPRAP (CONC)(4 IN)
CY 13.000 $600.000 $1,200.000 $650.000 $450.000 $500.000 $1,062.900
RIPRAP (CONC)(FLUME)
CY 12.000 $600.000 $1,200.750 $650.000 $450.000 $500.000 $1,134.850
STR STEEL (MISC NON - BRIDGE)
LB 24,911.000 $8.000 $5.500 $3.650 $12.000 $8.990 $11.160
RAIL (HANDRAIL)(TY A)
LF 1,061.000 $140.000 $56.920 $66.000 $185.000 $200.000 $111.510
INLET(COMPL)(CURB)(TY C)(MOD)
EA 1.000 $10,000.000 $147.000 $6,000.000 $8,500.000 $6,999.000 $13,782.380
REMOV STR (INLET)
EA 1.000 $1,000.000 $585.000 $1,500.000 $2,500.000 $1,000.000 $1,174.040
REMOV STR (RET WALL)
LF 29.000 $40.000 $115.000 $12.000 $50.000 $100.000 $40.480
MOBILIZATION
LS 1.000 $396,287.730 $255,000.000 $200,000.000 $450,000.000 $500,000.000 $947,562.250
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 28.000 $8,500.000 $5,850.000 $100.000 $6,000.000 $7,999.000 $2,309.650
SANDBAGS FOR EROSION CONTROL
EA 604.000 $7.000 $3.500 $1.000 $5.000 $5.000 $11.220
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 6,040.000 $7.000 $5.000 $0.100 $18.000 $5.000 $8.890
BIODEG EROSN CONT LOGS (REMOVE)
LF 6,040.000 $2.500 $0.950 $0.100 $9.000 $1.000 $2.010
CONC CURB (TY II)
LF 258.000 $30.000 $21.200 $45.000 $40.000 $30.000 $64.410
CONC CURB & GUTTER (TY II)
LF 1,620.000 $35.000 $30.750 $45.000 $40.000 $40.000 $28.730
CONC CURB (DOWEL) (TY II)
LF 136.000 $30.000 $23.000 $45.000 $40.000 $30.000 $61.540
DRIVEWAYS (CONC)
SY 7,974.000 $85.000 $80.750 $90.000 $80.000 $90.000 $134.800
CONC SIDEWALKS (4")
SY 24,700.000 $55.000 $58.230 $90.000 $52.000 $80.000 $78.720
CURB RAMPS (TY 1)
SY 360.000 $175.000 $80.000 $90.000 $200.000 $200.000 $275.190
CURB RAMPS (TY 2)
SY 275.000 $140.000 $84.000 $90.000 $200.000 $200.000 $247.060
CURB RAMPS (TY 3)
SY 70.000 $125.000 $84.000 $90.000 $200.000 $200.000 $282.980
CURB RAMPS (TY 6)
SY 10.000 $140.000 $89.000 $90.000 $200.000 $200.000 $626.880
CURB RAMPS (TY 7)
SY 839.000 $145.000 $88.000 $90.000 $200.000 $200.000 $255.850
CURB RAMPS (TY 10)
SY 128.000 $190.000 $88.000 $90.000 $200.000 $200.000 $260.470
CURB RAMPS (TY 21)
SY 65.000 $180.000 $88.000 $90.000 $200.000 $200.000 $303.390
CONC MEDIAN
SY 280.000 $110.000 $159.000 $90.000 $125.000 $200.000 $121.810
CONC DIRECTIONAL ISLAND
SY 21.000 $150.000 $155.000 $90.000 $125.000 $200.000 $303.260
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 1.000 $260.000 $205.000 $150.000 $850.000 $400.000 $233.150
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 157.000 $550.000 $205.000 $250.000 $650.000 $500.000 $508.400
REMOVE SM RD SN SUP&AM
EA 9.000 $90.000 $145.000 $50.000 $250.000 $100.000 $123.150
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 9,833.000 $7.000 $5.650 $5.000 $6.000 $9.000 $5.620
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 44.000 $60.000 $37.400 $37.000 $50.000 $250.000 $40.390
PAVEMENT SEALER 24"
LF 9,833.000 $2.750 $0.270 $0.250 $0.500 $4.000 $0.280
PAVEMENT SEALER (YLD TRI)
EA 44.000 $25.000 $11.000 $11.000 $20.000 $30.000 $13.990
ELIM EXT PAV MRK & MRKS (4")
LF 143.000 $1.000 $1.120 $1.000 $2.000 $1.000 $2.020
ELIM EXT PAV MRK & MRKS (12")
LF 100.000 $3.000 $2.210 $2.000 $3.000 $4.000 $3.520
ELIM EXT PAV MRK & MRKS (24")
LF 3,626.000 $4.000 $2.100 $2.000 $2.000 $6.000 $2.130
PAV SURF PREP FOR MRK (24")
LF 9,833.000 $1.500 $0.310 $0.300 $1.000 $2.000 $0.320
PAV SURF PREP FOR MRK (36")(YLD TRI)
EA 44.000 $9.000 $11.000 $10.000 $15.000 $150.000 $13.990
REMOVAL OF CONCRETE FOUNDATIONS
EA 6.000 $850.000 $117.000 $600.000 $850.000 $500.000 $718.890
REPLACE DOWN GUY AND ANCHOR W/GUARD
EA 9.000 $1,200.000 $265.000 $250.000 $2,000.000 $3,999.000 $2,395.570
TRANSPLANT PLANT MATERIAL
EA 25.000 $1,800.000 $29.000 $150.000 $1,000.000 $1,499.000 $517.600
RETROFIT DET WARN SURF(SURF APP OR CIP)
EA 2.000 $200.000 $477.000 $300.000 $5,000.000 $800.000 $1,946.830
PRECAST CONCRETE WHEEL STOPS
EA 16.000 $500.000 $240.000 $100.000 $150.000 $500.000 $240.580
MOVE AND RESET PRECAST CONC WHEEL STOPS
EA 7.000 $250.000 $115.000 $100.000 $100.000 $500.000 $220.880
GROUND BOX W/ APRON (ADJUST)
EA 3.000 $470.000 $500.000 $1,000.000 $500.000 $1,400.000 $1,098.900
TMA (STATIONARY)
DAY 200.000 $192.000 $200.000 $1.000 $350.000 $200.000 $280.040
Totals: $4,359,164.980 $3,905,830.240 $4,194,950.100 $4,790,041.500 $5,539,676.890 $6,060,579.540