TOM GREEN BU 67-H (0077-09-010)

Items: 55

County: TOM GREEN
Length: N/A
Highway: BU 67-H
District: SAN ANGELO
Control Number: 0077-09-010
DBE Goal: N/A
Project: STP 2022(508)HES
Guaranty: N/A
Time: 282 WORKING DAYS
Engineer's Estimate: $1,702,267.13
Date: 05/04/2022 (4 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (4)
E
Engineer's Estimate
$1,702,267.13
1
$1,746,965.98
Over/Under Est: 2.63% $44,698.85
$1,874,036.31
Over/Under Est: 10.09% $171,769.18
Amt Left: 7.27% $127,070.33
$1,898,927.90
Over/Under Est: 11.55% $196,660.77
Amt Left: 8.7% $151,961.92
Delta: -1.33% -$24,891.59
Over/Under Est: 38.65% $657,936.12
Amt Left: 35.1% $613,237.27
Delta: -24.29% -$461,275.35

Bid Items & Bid Tabulations

55 Total 0 of 55
TOM GREEN  |  BU 67-H  |  SAN ANGELO  |  0077-09-010  |  05/04/2022  |  $1,702,267.13  |  STP 2022(508)HES  |  HAZARD ELIM & SAFETY  |  282 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
3LW CIVIL LLC
RELMCO, INC.
ENCINO LANDSCAPE, INC.
SCR CIVIL CONSTRUCTION, LLC
REMOVING CONC (RIPRAP)
SY 605.000 $29.000 $30.000 $30.000 $20.000 $83.000
REMOVING CONC (DRIVEWAYS)
SY 13.000 $23.000 $28.000 $100.000 $20.000 $100.000
REMOVING CONC (CURB AND GUTTER)
LF 83.000 $19.000 $16.000 $50.000 $20.000 $150.000
REMOVING CONCRETE(MOW STRIP)
LF 120.000 $9.180 $10.000 $50.000 $20.000 $66.000
REMOVING STAB BASE & ASPH PAV (12")
SY 98.000 $6.500 $14.000 $50.000 $20.000 $83.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY A)
CY 171.000 $62.000 $95.000 $80.000 $50.000 $380.000
LRA PAV TY-I GR-D
TON 31.000 $223.320 $300.000 $250.000 $100.000 $760.000
CL A CONC (MISC)
CY 2.000 $1,833.000 $1,500.000 $938.000 $1,000.000 $1,500.000
CL C CONC (RAIL FOUNDATION)
CY 3.000 $1,853.420 $900.000 $2,800.000 $1,400.000 $1,500.000
CL C CONC (RAC-R)
CY 16.000 $1,820.000 $1,500.000 $2,310.000 $1,400.000 $5,500.000
RETAINING WALL (CAST - IN - PLACE)
SF 669.000 $129.000 $90.000 $65.000 $100.000 $181.500
RIPRAP (CONC)(5 IN)
CY 56.000 $593.000 $500.000 $425.000 $500.000 $637.000
RIPRAP (CONC)(FLUME)
CY 9.000 $630.000 $500.000 $800.000 $500.000 $700.000
RIPRAP (MOW STRIP)(4 IN)
CY 615.000 $604.000 $500.000 $465.000 $500.000 $690.000
STR STEEL (MISC NON - BRIDGE)
LB 2,112.000 $11.000 $16.000 $12.000 $20.000 $12.250
RAIL (TY SSTR)
LF 20.000 $154.540 $100.000 $420.000 $100.000 $219.000
RAIL (HANDRAIL)(TY F)
LF 165.000 $134.000 $120.000 $246.970 $200.000 $215.000
RETROFIT RAIL (TY SSTR)
LF 458.000 $190.000 $100.000 $195.000 $300.000 $219.000
CONC BOX CULV (4 FT X 4 FT)(EXTEND)
LF 2.000 $575.000 $3,500.000 $5,180.000 $600.000 $10,335.000
WINGWALL (PW - 1) (HW=6 FT)
EA 1.000 $20,484.000 $25,000.000 $16,240.000 $19,999.000 $17,000.000
MOBILIZATION
LS 1.000 $150,000.000 $150,000.000 $165,000.000 $150,000.000 $235,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $8,000.000 $19,493.000 $12,000.000 $4,000.000 $14,500.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 10.000 $8.920 $1.000 $30.000 $10.000 $20.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 10.000 $2.090 $1.000 $30.000 $1.000 $5.000
PTB(FRN&INSTL)(SSCB OR CSB)(TY1)OR(STL)
LF 600.000 $45.000 $60.000 $50.000 $50.000 $20.000
PTB(MOVE)(SSCB OR CSB)(TY1)OR(STL)
LF 860.000 $12.000 $12.000 $20.000 $10.000 $47.000
PTB(REMOVE)(SSCB OR CSB)(TY1)OR(STL)
LF 600.000 $5.000 $12.750 $30.000 $10.000 $20.000
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 54.000 $180.000 $107.000 $250.000 $80.000 $495.000
CONC CURB & GUTTER (TY II)
LF 101.000 $40.000 $60.000 $35.000 $40.000 $150.000
CONC SIDEWALKS (4")
SY 148.000 $69.000 $100.000 $75.000 $80.000 $100.000
CURB RAMPS (TY 2)
EA 14.000 $2,000.000 $3,000.000 $1,800.000 $2,100.000 $500.000
MTL W-BEAM GD FEN (STEEL POST)
LF 7,680.340 $30.000 $29.000 $36.850 $35.000 $37.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 23.000 $2,122.000 $2,096.000 $1,980.000 $2,400.000 $2,015.000
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $980.000 $1,200.000 $1,045.000 $1,500.000 $1,065.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 10.000 $1,177.000 $1,430.000 $1,485.000 $1,800.000 $1,510.000
MTL BM GD FEN TRANS (NON - SYM)
EA 3.000 $896.000 $890.000 $770.000 $2,500.000 $785.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 274.660 $62.500 $72.000 $99.000 $100.000 $100.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 9.000 $1,233.000 $1,400.000 $1,485.000 $1,500.000 $1,510.000
MTL BM GD FEN TRANS (ANCHOR PLATE)
EA 8.000 $1,026.000 $775.000 $880.000 $1,000.000 $900.000
CONNECTOR PLATE FOR THRIE BEAM
EA 8.000 $270.000 $1,200.000 $880.000 $400.000 $900.000
REMOVE METAL BEAM GUARD FENCE
LF 5,767.000 $4.000 $3.000 $2.200 $3.000 $3.000
GUARDRAIL END TREATMENT (INSTALL)
EA 48.000 $2,870.000 $3,000.000 $3,355.000 $3,200.000 $3,410.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 4.000 $700.000 $715.000 $1,430.000 $800.000 $1,455.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 4.000 $1,350.000 $1,471.000 $1,500.000 $1,500.000 $3,000.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,050.000 $1,162.000 $1,500.000 $900.000 $300.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $7,000.000 $9,004.000 $10,000.000 $14,000.000 $2,000.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 18.000 $673.000 $536.000 $550.000 $1,000.000 $560.000
RELOCATE SM RD SN SUP&AM TY S80
EA 6.000 $611.000 $604.000 $715.000 $500.000 $730.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 34.000 $25.000 $24.000 $22.000 $30.000 $25.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 14.000 $20.000 $24.000 $3.300 $30.000 $10.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 151.000 $34.000 $32.000 $26.400 $30.000 $30.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 3,160.000 $1.500 $1.060 $7.590 $1.000 $2.500
ELIM EXT PAV MRK & MRKS (4")
LF 800.000 $1.500 $0.970 $9.790 $1.000 $1.950
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 119.000 $125.000 $107.000 $300.000 $500.000 $100.000
TMA (STATIONARY)
DAY 228.000 $232.000 $100.000 $300.000 $830.000 $360.000
Totals: $1,702,267.130 $1,746,965.980 $1,874,036.319 $1,898,927.900 $2,360,203.250