Show Job Controls
Bid Cobra

TERRELL US 90 (0021-07-063)

Items: 21

County: TERRELL
Length: 0.0000 MILES
Highway: US 90
District: ODESSA
Control Number: 0021-07-063
DBE Goal: 0.0%
Project: C 21-7-63
Guaranty: $100,000.00
Time: 84 WORKING DAYS
Engineer's Estimate: $13,466,921.01
Date: 09/06/2024 (1 year ago)
Contract Number: 9243209
Type: SEAL COAT
Project ID: A00189375
Project Description: FY 2025 SEAL COAT
Mail/Deliver Bids To: N/A
PRELETTINGQUESTIONS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$13,466,921.01
$13,343,819.72
Over/Under Est: -0.91% -$123,101.29
$14,113,349.48
Over/Under Est: 4.8% $646,428.47
Amt Left: 5.77% $769,529.76
Over/Under Est: 12.07% $1,625,451.27
Amt Left: 13.1% $1,748,552.56
Delta: -6.94% -$979,022.80
Subcontractor Percentage Amount
VIZCAINO, L.P. 5.40% $720,566.26
BARRICADES PLUS, LLC 1.38% $184,144.71
Total: 6.78% $904,710.97

Bid Items & Bid Tabulations

21 Total 0 of 21
TERRELL  |  US 90  |  ODESSA  |  0021-07-063  |  09/06/2024  |  $13,466,921.01  |  C 21-7-63  |  SEAL COAT  |  84 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RONALD R. WAGNER & CO., LP
CK NEWBERRY, LLC
CLARK CONSTRUCTION OF TEXAS, INC.
MOBILIZATION
LS 1.000 $1,180,502.810 $1,256,216.000 $1,375,000.000 $1,817,755.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $15,000.000 $0.010 $100,000.000 $35,000.000
TMA (MOBILE OPERATION)
DAY 80.000 $254.180 $0.010 $400.000 $10.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 5,940.000 $0.260 $0.010 $0.010 $0.450
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 94,390.000 $0.260 $0.010 $0.010 $0.450
RE PM TY II (W) 6" (BRK)
LF 19,720.000 $0.200 $0.170 $0.250 $0.180
RE PM TY II (W) 6" (SLD)
LF 2,342,256.000 $0.170 $0.170 $0.180 $0.170
RE PM TY II (W) 8" (SLD)
LF 9,455.000 $0.340 $0.250 $0.500 $0.350
RE PM TY II (W) 12" (SLD)
LF 43.000 $3.750 $3.000 $3.000 $5.000
RE PM TY II (W) 24" (SLD)
LF 923.000 $5.670 $5.000 $5.000 $5.000
RE PM TY II (W) (ARROW)
EA 22.000 $106.670 $120.000 $125.000 $75.000
RE PM TY II (W) (WORD)
EA 12.000 $106.670 $200.000 $150.000 $75.000
RE PM TY II (W) (RR XING)
EA 3.000 $500.000 $500.000 $555.000 $250.000
RE PM TY II (W) (SYMBOL)
EA 3.000 $150.000 $500.000 $225.000 $250.000
RE PM TY II (Y) 6" (BRK)
LF 244,400.000 $0.190 $0.170 $0.250 $0.180
RE PM TY II (Y) 6" (SLD)
LF 696,603.000 $0.180 $0.170 $0.200 $0.170
PREFAB PM TY C (W)(36")(YLD TRI)
EA 27.000 $35.000 $35.000 $100.000 $30.000
REFL PAV MRKR TY I-C
EA 1,010.000 $4.250 $3.000 $5.000 $5.000
REFL PAV MRKR TY II-A-A
EA 45,840.000 $4.250 $3.000 $5.000 $4.000
ASPH (AC-20-5TR)
TON 7,710.000 $885.730 $862.640 $875.000 $917.250
AGGR (TY-PB, GR-4)(SAC-A)
CY 38,668.000 $118.000 $122.000 $121.000 $135.800
Totals: $13,466,921.010 $13,343,819.720 $14,113,349.480 $15,092,372.280