Job Info for 0908-00-126

County: TAYLOR Highway: VA Date: 09/05/2024 (2 months ago) Engineer's Estimate: $2,806,642 Control Number: 0908-00-126
Project: C 908-00-126 District: ABILENE Time: 173 WORKING DAYS Type: BRIDGE MAINTENANCE
Bidder's List

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,806,641.90
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC   $2,658,110.75 1
-5.29% | -$148,531.15
GIBSON & ASSOCIATES, INC.   $2,688,962.66 2
-4.19% | -$117,679.24
1.16% | $30,851.91
BLACKSMITH VENTURES LLC   $2,746,263.00 3
-2.15% | -$60,378.90
3.32% | $88,152.25
2.13% | $57,300.34

Bid Items

Items: 44, 0 filtered
TAYLOR VA  |  ABILENE  |  0908-00-126  |  09/05/2024  |  $2,806,642  |  C 908-00-126  |  BRIDGE MAINT  |  173 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC GIBSON & ASSOCIATES, INC. BLACKSMITH VENTURES LLC
104 7006 REMOV CONC (RIPRAP) SY 13.000 $60.000 $25.000 $550.000 $150.000
401 7001 FLOWABLE BACKFILL CY 23.000 $550.000 $500.000 $755.000 $500.000
429 7003 CONC STR REPAIR(DECK REP(PART DEPTH)) SF 1,498.000 $135.000 $325.000 $86.000 $175.000
429 7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) SF 44.000 $225.000 $350.000 $500.000 $500.000
429 7007 CONC STR REPAIR (VERTICAL & OVERHEAD) SF 1,238.000 $200.000 $275.000 $272.420 $150.000
432 7001 RIPRAP (CONC)(4 IN) CY 3.000 $800.000 $1,000.000 $3,200.000 $2,000.000
432 7041 RIPRAP (STONE PROTECTION)(12 IN) CY 25.000 $800.000 $250.000 $850.000 $750.000
438 7007 CLEANING AND SEALING EXIST JOINTS (CL7) LF 350.000 $50.000 $60.000 $74.000 $50.000
438 7012 CLEAN AND SEAL JNTS (PAN GIRDERS) (CL7) LF 556.000 $50.000 $65.000 $122.000 $50.000
439 7007 LATEX - MODIFIED CONC OVERLAY (2 IN) SY 1,632.000 $155.000 $150.000 $195.000 $250.000
439 7014 MULTI-LAYER POLYMER OVERLAY SY 4,338.000 $75.000 $55.000 $47.000 $55.000
442 7010 STR STEEL (PEDESTAL) LB 1,840.000 $35.000 $50.000 $10.000 $40.000
446 7002 CLEAN & PAINT EXIST STR (SYSTEM II) LS 1.000 $180,000.000 $160,000.000 $146,625.000 $127,500.000
446 7019 SPOT CLEAN & PNT EXT STR(SPL PROT SYS) LS 1.000 $70,000.000 $18,000.000 $18,500.000 $19,900.000
483 7010 HYDRO-DEMOLITION (2 IN) SY 1,632.000 $145.000 $150.000 $284.000 $90.000
483 7016 SHOT BLASTING SY 4,338.000 $8.000 $10.000 $3.750 $8.000
500 7001 MOBILIZATION LS 1.000 $270,000.000 $200,000.000 $300,000.000 $110,000.000
502 7001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 10.000 $20,000.000 $4,000.000 $4,350.000 $25,000.000
505 7001 TMA (STATIONARY) DAY 90.000 $300.000 $300.000 $300.000 $350.000
505 7003 TMA (MOBILE OPERATION) DAY 8.000 $500.000 $300.000 $300.000 $500.000
510 7003 ONE-WAY TRAF CONT (PORT TRAF SIG) MO 2.000 $8,000.000 $15,000.000 $8,200.000 $10,000.000
512 7017 PORT CTB (DES SOURCE)(F-SHAPE)(TY 1) LF 300.000 $45.000 $35.000 $33.000 $150.000
512 7029 PORT CTB (MOVE)(F-SHAPE)(TY 1) LF 300.000 $20.000 $35.000 $33.000 $25.000
512 7041 PORT CTB (STKPL)(F-SHAPE)(TY 1) LF 300.000 $30.000 $35.000 $33.000 $1.000
545 7004 CRASH CUSH ATTEN (REMOVE) EA 1.000 $3,000.000 $2,500.000 $2,200.000 $1,000.000
545 7014 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 1.000 $14,000.000 $12,000.000 $9,900.000 $25,000.000
662 7051 WK ZN PAV MRK REMOV (REFL) TY II-A-A EA 200.000 $4.000 $10.000 $7.700 $5.000
662 7068 WK ZN PAV MRK REMOV (W)6"(SLD) LF 1,620.000 $0.600 $3.600 $3.300 $2.000
662 7077 WK ZN PAV MRK REMOV (W)24"(SLD) LF 48.000 $20.000 $25.000 $22.000 $25.000
662 7100 WK ZN PAV MRK REMOV (Y)6"(SLD) LF 7,680.000 $0.800 $3.600 $3.300 $2.000
666 7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) LF 11,560.000 $1.100 $3.500 $3.030 $2.000
666 7420 REFL PAV MRK TY I (Y)6"(BRK)(100MIL) LF 1,315.000 $1.100 $3.600 $3.300 $2.000
666 7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) LF 3,760.000 $1.100 $3.600 $3.300 $2.000
672 7002 REFL PAV MRKR TY I-C EA 14.000 $6.000 $12.000 $11.000 $7.000
672 7004 REFL PAV MRKR TY II-A-A EA 134.000 $6.000 $12.000 $8.800 $20.000
677 7001 ELIM EXT PM & MRKS (4") LF 10,688.000 $0.800 $2.000 $1.650 $2.000
678 7002 PAV SURF PREP FOR MRK (6") LF 14,515.000 $1.000 $1.250 $1.100 $1.000
778 7004 CONCRETE RAIL REPLACEMENT (IN-KIND) LF 30.000 $400.000 $250.000 $1,500.000 $500.000
780 7002 CNC CRACK REPAIR (DISCRETE)(INJECT) LF 100.000 $180.000 $125.000 $95.000 $75.000
784 7002 REP STL BRIDGE MEMBER (BEAM) EA 7.000 $40,000.000 $15,000.000 $8,500.000 $45,000.000
784 7003 REP STL BRIDGE MEMBER (DIAPHRAGM) EA 2.000 $5,000.000 $5,000.000 $4,500.000 $5,000.000
786 7001 CARBON FIBER REINF POLYMER PROTECTION SF 132.000 $175.000 $110.000 $150.000 $100.000
787 7001 REPLACING ELASTOMERIC BEARING PADS EA 22.000 $5,500.000 $2,500.000 $7,300.000 $8,500.000
7001 7002 BENT CAP/ABUTMENT CAP CLEANING EA 6.000 $4,000.000 $1,500.000 $1,980.000 $1,500.000
Totals: $2,806,641.90 $2,658,110.75 $2,688,962.66 $2,746,263.00