TAYLOR SH 36 (0181-01-061)

Items: 66

County: TAYLOR
Length: N/A
Highway: SH 36
District: ABILENE
Control Number: 0181-01-061
DBE Goal: N/A
Project: STP 2019(789)
Guaranty: N/A
Time: 232 WORKING DAYS
Engineer's Estimate: $4,089,157.80
Date: 10/01/2020 (5 years ago)
Contract Number: N/A
Type: OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$4,089,157.80
$2,378,249.95
Over/Under Est: -41.84% -$1,710,907.85
Over/Under Est: -40.43% -$1,653,238.01
Amt Left: 2.42% $57,669.84
$2,882,602.05
Over/Under Est: -29.51% -$1,206,555.75
Amt Left: 21.21% $504,352.10
Delta: -18.34% -$446,682.26
Over/Under Est: -25.46% -$1,041,094.55
Amt Left: 28.16% $669,813.30
Delta: -5.74% -$165,461.20
$3,083,981.10
Over/Under Est: -24.58% -$1,005,176.70
Amt Left: 29.67% $705,731.15
Delta: -1.18% -$35,917.85
Over/Under Est: -14.92% -$610,297.80
Amt Left: 46.28% $1,100,610.05
Delta: -12.80% -$394,878.90
$3,490,867.33
Over/Under Est: -14.63% -$598,290.47
Amt Left: 46.78% $1,112,617.38
Delta: -0.35% -$12,007.33

Bid Items & Bid Tabulations

66 Total 0 of 66
TAYLOR  |  SH 36  |  ABILENE  |  0181-01-061  |  10/01/2020  |  $4,089,157.80  |  STP 2019(789)  |  OVERLAY  |  232 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FOUTSCO PAVING COMPANY, LLC
J. H. STRAIN & SONS, INC.
VULCAN CONSTRUCTION
BONTKE BROTHERS CONSTRUCTION COMPANY
CONTRACT PAVING CO.
TIERRA LEASE SERVICE, LLC
GILVIN-TERRILL, LTD.
REMOVING CONC (CURB AND GUTTER)
LF 433.000 $20.000 $10.000 $8.000 $16.500 $15.000 $9.000 $12.000 $35.000
PRIME COAT (AE-P)
GAL 242.000 $8.000 $4.000 $6.000 $6.350 $15.000 $10.000 $25.000 $7.000
ASPH (MULTI OPTION)
GAL 49,124.000 $6.000 $3.500 $3.750 $4.650 $6.350 $5.000 $4.000 $3.500
AGGR(TY-PB GR-4 SAC-B)
CY 877.000 $130.000 $150.000 $105.000 $185.000 $225.000 $125.000 $170.000 $200.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 2,056.000 $60.000 $44.000 $45.450 $59.600 $58.000 $68.000 $63.000 $70.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 2,784.000 $40.000 $29.000 $25.800 $42.200 $38.000 $46.000 $36.000 $45.000
FLEX PAVEMENT STRUCTURE REPAIR (2.5")
SY 3,630.000 $30.000 $20.000 $17.300 $35.500 $18.000 $38.000 $27.000 $35.000
PLANE ASPH CONC PAV (1")
SY 79,961.000 $3.000 $0.550 $0.850 $2.000 $1.500 $1.500 $1.250 $1.500
PLANE ASPH CONC PAV (2")
SY 6,934.000 $6.000 $1.650 $1.600 $3.000 $2.250 $2.500 $2.500 $2.000
PLANE ASPH CONC PAV(1" TO 2")
SY 34,083.000 $3.000 $0.650 $0.980 $1.950 $2.000 $1.550 $2.500 $1.600
CLEANING EXISTING JOINTS
LF 910.000 $17.000 $8.000 $11.000 $15.400 $11.000 $10.000 $12.000 $20.000
HEADER TYPE EXPANSION JOINT
CF 188.000 $550.000 $1,000.000 $388.000 $307.000 $475.000 $500.000 $385.000 $300.000
JOINT SEALANT
LF 910.000 $15.000 $13.000 $14.300 $18.600 $12.000 $15.000 $15.250 $30.000
MOBILIZATION
LS 1.000 $350,000.000 $12,750.000 $188,000.000 $230,000.000 $155,000.000 $260,000.000 $450,000.000 $350,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $15,000.000 $4,000.000 $2,500.000 $8,268.000 $2,500.000 $2,500.000 $1,950.000 $15,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 60.000 $50.000 $15.000 $35.000 $32.900 $30.000 $50.000 $33.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 60.000 $15.000 $5.000 $10.000 $11.000 $10.000 $15.000 $20.000 $15.000
SANDBAGS FOR EROSION CONTROL
EA 140.000 $14.000 $4.000 $8.000 $16.500 $12.000 $19.000 $15.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 24.000 $20.000 $5.000 $7.000 $3.300 $14.000 $10.000 $20.000 $15.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 24.000 $10.000 $1.000 $2.000 $1.100 $14.000 $10.000 $15.000 $10.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 730.000 $10.000 $5.000 $7.000 $5.500 $7.000 $6.000 $6.000 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 730.000 $5.000 $2.000 $2.000 $1.100 $7.000 $3.000 $2.000 $2.000
CONC CURB & GUTTER (TY II)
LF 375.000 $45.000 $50.000 $15.000 $73.000 $20.000 $33.000 $60.000 $70.000
REMOVE METAL BEAM GUARD FENCE
LF 64.000 $10.000 $10.000 $3.000 $31.900 $30.000 $15.000 $11.000 $10.000
REPLACE EXISTING ALUMINUM SIGNS(TY A)
SF 32.000 $35.000 $40.000 $30.250 $30.200 $1,100.000 $36.000 $37.000 $27.500
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 27.000 $910.000 $350.000 $770.000 $767.500 $400.000 $800.000 $800.000 $700.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 33.000 $1,015.000 $450.000 $852.000 $850.000 $525.000 $950.000 $925.000 $810.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 5.000 $1,100.000 $500.000 $1,018.000 $1,014.000 $650.000 $1,500.000 $1,100.000 $925.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $1,200.000 $650.000 $1,075.000 $1,069.000 $710.000 $2,000.000 $1,200.000 $975.000
REMOVE SM RD SN SUP&AM
EA 74.000 $115.000 $120.000 $110.000 $109.500 $100.000 $200.000 $100.000 $100.000
REMOVE SM RD SN SUP&AM (SIGN ONLY)
EA 2.000 $115.000 $100.000 $55.000 $54.800 $250.000 $300.000 $130.000 $50.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 17,840.000 $0.300 $0.300 $0.200 $0.550 $0.600 $0.250 $0.550 $0.350
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 5,500.000 $0.600 $0.700 $0.300 $0.550 $0.600 $0.350 $0.550 $0.550
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 2,360.000 $3.500 $2.900 $1.500 $3.300 $3.300 $1.600 $3.250 $4.250
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 160.000 $50.000 $58.000 $25.000 $71.300 $72.000 $26.250 $70.000 $125.000
WK ZN PAV MRK NON-REMOV (W)(RR XING)
EA 12.000 $285.000 $300.000 $150.000 $219.500 $220.000 $157.500 $215.000 $400.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 36.000 $70.000 $6.000 $30.000 $71.300 $72.000 $31.500 $70.000 $155.000
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 12,220.000 $0.300 $0.360 $0.200 $0.550 $0.600 $0.250 $0.550 $0.350
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 73,926.000 $0.300 $0.300 $0.200 $0.550 $0.550 $0.250 $0.550 $0.270
WK ZN PAV MRK NON-REMOV (Y)24"(SLD)
LF 1,316.000 $3.000 $3.000 $1.500 $3.300 $3.300 $1.600 $3.250 $4.250
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 2,844.000 $4.000 $4.000 $3.000 $3.850 $3.700 $3.250 $3.750 $3.650
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 3,682.000 $4.000 $4.000 $3.000 $3.850 $3.700 $3.250 $3.750 $3.650
WK ZN PAV MRK REMOV (TRAF BTN) TY W
EA 826.000 $3.250 $4.000 $3.000 $3.000 $3.000 $3.250 $3.000 $3.450
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
EA 5,545.000 $4.000 $3.000 $3.000 $3.000 $3.000 $3.250 $3.000 $3.450
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 2,844.000 $2.000 $1.000 $2.250 $1.300 $1.000 $2.000 $1.250 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,682.000 $2.000 $1.000 $2.250 $1.150 $1.000 $2.000 $1.250 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,750.000 $1.100 $2.500 $0.900 $1.100 $1.150 $1.000 $1.100 $1.000
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 658.000 $7.000 $6.000 $3.500 $6.050 $6.050 $3.700 $6.000 $6.000
PAVEMENT SEALER 4"
LF 1,446.000 $1.250 $0.300 $0.550 $0.200 $0.300 $0.600 $0.200 $0.300
PAVEMENT SEALER 8"
LF 667.000 $1.250 $0.350 $0.550 $0.350 $0.400 $0.600 $0.300 $0.600
PAVEMENT SEALER 24"
LF 167.000 $4.000 $1.000 $1.000 $2.200 $2.200 $1.100 $2.000 $3.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 8,920.000 $1.000 $0.700 $0.320 $0.550 $0.550 $0.500 $0.550 $0.470
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 6,110.000 $1.000 $0.700 $0.320 $0.550 $0.550 $0.500 $0.550 $0.470
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 36,963.000 $0.750 $0.600 $0.320 $0.550 $0.550 $0.500 $0.550 $0.420
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 1,180.000 $16.000 $11.000 $15.000 $13.200 $13.200 $15.750 $13.000 $15.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 80.000 $250.000 $200.000 $250.000 $197.500 $200.000 $262.500 $200.000 $245.000
PREFAB PAV MRK TY C (W) (WORD)
EA 18.000 $285.000 $250.000 $220.000 $274.000 $275.000 $231.000 $275.000 $285.000
PREFAB PAV MRK TY C (W) (RR XING)
EA 6.000 $750.000 $600.000 $550.000 $658.000 $660.000 $577.500 $650.000 $715.000
REFL PAV MRKR TY I-C
EA 576.000 $5.000 $4.000 $3.000 $3.850 $4.000 $3.250 $3.750 $4.200
REFL PAV MRKR TY II-A-A
EA 1,072.000 $5.000 $4.000 $3.000 $3.850 $4.000 $3.250 $3.750 $4.200
CLEANING / SWEEPING (HANDWORK)
SY 381.000 $25.000 $10.000 $20.000 $15.700 $30.000 $55.000 $15.000 $10.000
SP MIXES SP-D SAC-B PG70-22
TON 13,307.000 $130.000 $88.000 $87.170 $80.300 $93.000 $97.000 $116.000 $107.000
TACK COAT
GAL 3,630.000 $4.000 $0.010 $2.000 $4.050 $8.000 $6.000 $5.500 $5.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $20,000.000 $10,000.000 $10,000.000 $4,387.000 $2,000.000 $15,000.000 $12,000.000 $15,000.000
TMA (STATIONARY)
DAY 220.000 $400.000 $1.000 $175.000 $60.000 $475.000 $125.000 $325.000 $310.000
TMA (MOBILE OPERATION)
DAY 24.000 $500.000 $1.000 $175.000 $27.400 $1,000.000 $400.000 $225.000 $950.000
Totals: $4,089,157.800 $2,378,249.950 $2,435,919.790 $2,882,602.050 $3,048,063.250 $3,083,981.100 $3,478,860.000 $3,490,867.330