TAYLOR US 83 (0034-02-050)

Items: 26

County: TAYLOR
Length: N/A
Highway: US 83
District: ABILENE
Control Number: 0034-02-050
DBE Goal: N/A
Project: C 34-2-50
Guaranty: N/A
Time: 56 WORKING DAYS
Engineer's Estimate: $2,491,512.27
Date: 03/07/2023 (3 years ago)
Contract Number: N/A
Type: PREVENTIVE MAINTENANCE
Mail/Deliver Bids To: N/A
BRYCE TURENTINE
CHAD W CARTER
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$2,491,512.27
$1,760,153.98
Over/Under Est: -29.35% -$731,358.29
Over/Under Est: -28.66% -$714,136.05
Amt Left: 0.98% $17,222.24
$1,884,741.81
Over/Under Est: -24.35% -$606,770.46
Amt Left: 7.08% $124,587.83
Delta: -6.04% -$107,365.59
$2,315,181.98
Over/Under Est: -7.08% -$176,330.29
Amt Left: 31.53% $555,028.00
Delta: -22.84% -$430,440.17

Bid Items & Bid Tabulations

26 Total 0 of 26
TAYLOR  |  US 83  |  ABILENE  |  0034-02-050  |  03/07/2023  |  $2,491,512.27  |  C 34-2-50  |  PREVENT MAINT  |  56 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. H. STRAIN & SONS, INC.
FOUTSCO PAVING COMPANY, LLC
DUININCK, INC.
GILVIN-TERRILL, LTD.
BACKFILL (TY B)
STA 208.540 $270.000 $185.000 $50.000 $100.000 $500.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 3,434.000 $48.000 $30.000 $40.000 $35.500 $40.000
PLANE ASPH CONC PAV (2")
SY 36,269.000 $1.800 $1.500 $1.000 $2.550 $5.000
MOBILIZATION
LS 1.000 $226,501.120 $122,000.000 $180,000.000 $150,000.000 $200,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $10,000.000 $3,000.000 $9,000.000 $20,000.000 $42,500.000
RUMBLE STRIPS (SHOULDER)
LF 27,202.000 $0.250 $0.310 $0.200 $0.070 $0.300
RUMBLE STRIPS (CENTERLINE)
LF 13,601.000 $0.250 $0.370 $0.200 $0.080 $0.400
MTL W-BEAM GD FEN (TIM POST)
LF 825.000 $35.000 $27.000 $24.500 $28.000 $27.500
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 4.000 $1,400.000 $1,575.000 $1,300.000 $1,300.000 $2,000.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 125.000 $85.000 $64.250 $78.000 $78.000 $60.000
REMOVE METAL BEAM GUARD FENCE
LF 950.000 $2.500 $2.150 $2.000 $2.000 $2.000
REMOVE TERMINAL ANCHOR SECTION
EA 6.000 $325.000 $215.000 $250.000 $250.000 $200.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,500.000 $3,475.000 $1,950.000 $2,000.000 $3,250.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $300.000 $270.000 $250.000 $255.000 $250.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 9.000 $75.000 $76.500 $50.000 $85.000 $75.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $38.000 $37.500 $50.000 $25.000 $35.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,032.000 $1.000 $1.500 $0.010 $1.350 $1.500
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 27,202.000 $0.600 $0.540 $0.550 $0.500 $0.490
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 2,842.000 $0.500 $0.540 $0.500 $0.560 $0.550
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 11,532.000 $0.600 $0.540 $0.500 $0.510 $0.500
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 156.000 $15.000 $19.800 $12.000 $11.500 $11.500
REFL PAV MRKR TY II-A-A
EA 286.000 $4.500 $9.100 $5.000 $3.950 $3.900
SP MIXES SP-C SAC-B PG70-22
TON 11,258.000 $155.000 $116.050 $115.000 $113.850 $117.000
TACK COAT
GAL 10,387.000 $6.000 $1.000 $0.100 $2.800 $6.000
TMA (STATIONARY)
DAY 40.000 $300.000 $200.000 $1.000 $255.000 $700.000
TMA (MOBILE OPERATION)
DAY 18.000 $700.000 $200.000 $1.000 $910.000 $950.000
Totals: $2,491,512.270 $1,760,153.980 $1,777,376.220 $1,884,741.810 $2,315,181.980