Show Job Controls
Bid Cobra

TARRANT VARIOUS (0902-90-176)

Items: 105

County: TARRANT
Length: 0.0000 MILES
Highway: VARIOUS
District: FORT WORTH
Control Number: 0902-90-176
DBE Goal: 0.0%
Project: CM 2026(885)
Guaranty: $100,000.00
Time: 219 WORKING DAYS
Engineer's Estimate: $6,914,803.00
Date: 07/01/2026 1:00 PM CDT (17 days ago)
Contract Number: 7263038
Type: CONSTRUCT NEW ROADWAY LANES
Project ID: A00131976
Contract Type: FEDERAL
Project Description: RECONSTRUCT AND WIDEN FROM 2 LANES TO 4 LANES WITH SIDEWALKS, INTERSECTION IMPROVEMENTS, STORMWATER AND CULVERT IMPROVEMENTS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DANIEL POOLE
SURAFEL SINTAYEHU
JASON PASCOE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$6,914,803.00
Over/Under Est: -25.37% -$1,754,521.21
Over/Under Est: -20.83% -$1,440,022.47
Amt Left: 6.09% $314,498.74
Over/Under Est: -11.62% -$803,431.50
Amt Left: 18.43% $951,089.71
Delta: -11.63% -$636,590.97
$6,166,871.05
Over/Under Est: -10.82% -$747,931.95
Amt Left: 19.51% $1,006,589.26
Delta: -0.91% -$55,499.55

Bid Items & Bid Tabulations

105 Total 0 of 105
TARRANT  |  VARIOUS  |  FORT WORTH  |  0902-90-176  |  07/01/2026 1:00 PM CDT  |  $6,914,803.00  |  CM 2026(885)  |  CONSTRUCT NEW ROADWAY LANES  |  219 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FOUTSCO PAVING COMPANY, LLC
RAGLE CONSTRUCTION, INC.
ED BELL CONSTRUCTION COMPANY
JAGOE-PUBLIC COMPANY
PREPARING ROW
STA 16.000 $4,000.000 $1,000.000 $33,750.000 $18,900.000 $4,550.000
REMOV CONC (DRIVEWAYS)
SY 831.000 $35.000 $40.000 $16.000 $23.000 $20.000
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 63.000 $50.000 $30.000 $14.000 $76.000 $26.000
REMOV CONC (CURB & GUTTER)
LF 1,302.000 $15.000 $10.000 $8.500 $16.000 $21.000
EXCAV (ROADWAY & CHANNEL)
CY 9,029.000 $45.000 $22.000 $40.000 $42.000 $42.000
EMBANK (FNL)(DC)(TY C2)
CY 1,493.000 $50.000 $18.000 $15.000 $63.000 $70.000
COMPOST MANUF TOPSOIL (4")
SY 8,690.000 $15.000 $9.000 $6.850 $7.300 $10.000
BLOCK SODDING
SY 6,032.000 $25.000 $4.550 $7.250 $5.640 $5.000
ROLL SODDING
SY 2,658.000 $10.000 $4.550 $7.500 $5.860 $5.000
BROADCAST SEED (TEMP_WARM)
SY 4,345.000 $1.000 $0.250 $0.500 $0.530 $0.300
BROADCAST SEED (TEMP_COOL)
SY 4,345.000 $1.000 $0.260 $0.500 $0.530 $0.300
VEGETATIVE WATERING
TGL 305.000 $180.000 $65.000 $40.000 $53.250 $38.000
RDSIDE AMENITY (GATE)
EA 1.000 $5,000.000 $11,500.000 $3,500.000 $5,325.000 $2,700.000
PROOF ROLLING
HR 16.000 $150.000 $400.000 $125.000 $315.000 $60.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 2,815.000 $100.000 $80.000 $110.000 $88.000 $80.000
LIME (COM OR QK)(SLURRY)
TON 222.000 $400.000 $325.000 $315.000 $315.000 $330.000
LIME TRT (EXIST MATL)(8")
SY 13,246.000 $10.000 $6.000 $3.900 $3.150 $6.000
CEMENT TRT (NEW BASE)(8")
SY 5,000.000 $10.000 $6.000 $2.900 $5.250 $3.000
SALV, HAUL & STKPL RCL APH PV (2"-6")
SY 1,920.000 $15.000 $5.240 $5.500 $7.190 $7.000
SALV, HAUL & STKPL RCL APH PV (5 TO 9")
SY 5,940.000 $15.000 $8.000 $5.500 $8.790 $9.000
PRIME COAT(MC-30 OR AE-P)
GAL 4,834.000 $12.000 $0.100 $5.500 $8.380 $4.250
D-GR HMA TY-B PG64-22
TON 2,020.000 $150.000 $125.000 $150.000 $127.320 $110.000
TACK COAT
GAL 2,303.000 $10.000 $0.100 $5.500 $5.330 $3.000
SP MIXES SP-C SAC-B PG70-28
TON 1,257.000 $225.000 $155.000 $175.000 $172.640 $130.000
CONC PVMT (CRCP) (9")
SY 492.000 $150.000 $132.360 $95.000 $161.000 $160.000
TRENCH EXCAVATION PROTECTION
LF 1,878.000 $30.000 $40.000 $2.000 $25.000 $12.000
TEMPORARY SPL SHORING
SF 8,474.000 $50.000 $35.000 $0.100 $50.000 $36.000
RETAINING WALL (SPREAD FOOTING)
SF 6,209.000 $125.000 $77.100 $90.000 $90.000 $135.000
RIPRAP (CONC)(5 IN)
CY 12.000 $2,000.000 $522.420 $650.000 $1,155.000 $500.000
RIPRAP (STONE COMMON)(GROUT)(24 IN)
CY 447.000 $200.000 $232.950 $175.000 $630.000 $400.000
RAIL (TY C223)
LF 422.000 $200.000 $89.600 $125.000 $205.000 $220.000
CONC BOX CULV (7 FT X 6 FT)
LF 400.000 $1,300.000 $515.700 $1,200.000 $915.000 $1,100.000
RC PIPE (CL III)(24 IN)
LF 1,577.000 $175.000 $165.000 $92.000 $150.000 $180.000
RC PIPE (CL III)(30 IN)
LF 418.000 $200.000 $210.000 $125.000 $175.000 $290.000
INLET (COMPL)(CO)(10 FT)(FTW)
EA 5.000 $12,000.000 $4,909.400 $11,350.000 $11,000.000 $12,000.000
INLET (COMPL)(CO)(15 FT)(FTW)
EA 4.000 $15,000.000 $6,272.100 $14,750.000 $13,000.000 $16,000.000
INLET (COMPL)( CO)(20 FT)(FTW)
EA 4.000 $18,000.000 $7,637.600 $18,075.000 $15,000.000 $16,000.000
INLET (COMPL)(COB)(20 FT)(FTW)
EA 1.000 $30,000.000 $10,293.900 $21,050.000 $20,000.000 $29,000.000
ADJUSTING MANHOLES
EA 4.000 $1,450.000 $800.000 $1,280.000 $4,500.000 $3,600.000
REMOV STR (INLET)
EA 1.000 $1,200.000 $1,500.000 $600.000 $2,000.000 $4,800.000
REMOV STR (HEADWALL)
EA 2.000 $1,400.000 $1,800.000 $1,400.000 $5,000.000 $7,000.000
REMOV STR (BOX CULVERT)
LF 63.000 $100.000 $87.000 $70.000 $300.000 $600.000
MOBILIZATION
LS 1.000 $700,000.000 $305,000.000 $540,000.000 $595,000.000 $684,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $15,000.000 $100,000.000 $35,825.000 $21,000.000 $36,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $8,500.000 $5,000.000 $12,000.000 $20,000.000 $15,750.000
TMA (STATIONARY)
DAY 94.000 $225.000 $1.000 $400.000 $210.000 $260.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 122.000 $60.000 $40.000 $44.000 $61.130 $46.000
ROCK FILTER DAMS (REMOVE)
LF 122.000 $25.000 $14.000 $18.000 $26.630 $19.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 342.000 $40.000 $33.500 $44.000 $54.210 $4.250
CONSTRUCTION EXITS (REMOVE)
SY 342.000 $15.000 $9.000 $13.000 $23.430 $14.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,762.000 $5.000 $0.100 $5.000 $3.040 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,762.000 $2.000 $0.100 $1.000 $1.380 $1.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 285.000 $10.000 $4.500 $6.000 $4.260 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 285.000 $3.000 $1.100 $1.000 $2.080 $1.000
CONSTRUCTING DETOURS
SY 642.000 $100.000 $85.000 $120.000 $111.000 $100.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 180.000 $50.000 $70.000 $150.000 $40.000 $70.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 40.000 $50.000 $70.000 $150.000 $120.000 $70.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 180.000 $10.000 $50.000 $12.000 $30.000 $50.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 40.000 $10.000 $50.000 $20.000 $90.000 $60.000
CONC CURB (MONO) (TY II)
LF 286.000 $15.000 $15.930 $13.000 $10.500 $2.000
CONC CURB & GUTTER (TY II)
LF 3,829.000 $70.000 $26.250 $27.000 $42.000 $26.000
DRIVEWAYS (CONC)
SY 929.000 $135.000 $93.240 $96.000 $147.000 $120.000
CONC SIDEWALKS (4")
SY 3,001.000 $100.000 $50.840 $55.000 $77.000 $70.000
CURB RAMPS (TY 1)
EA 2.000 $4,600.000 $2,500.000 $1,750.000 $2,500.000 $3,700.000
CURB RAMPS (TY 3)
EA 3.000 $4,000.000 $2,500.000 $1,350.000 $2,500.000 $3,700.000
CURB RAMPS (TY 22)
EA 1.000 $7,000.000 $3,500.000 $3,710.000 $4,000.000 $5,000.000
CONC SIDEWALKS (SPECIAL) (TYPE A)
SY 57.000 $300.000 $129.630 $135.000 $275.000 $320.000
REMOVE METAL BEAM GUARD FENCE
LF 238.000 $5.000 $5.000 $5.000 $29.350 $6.000
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $200.000 $300.000 $300.000 $1,467.310 $360.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 21.000 $1,000.000 $645.000 $650.000 $692.250 $700.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $1,000.000 $735.000 $725.000 $772.130 $700.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $1,200.000 $1,225.000 $1,130.000 $1,203.450 $1,200.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $1,300.000 $1,299.000 $1,130.000 $1,203.450 $1,300.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 4.000 $100.000 $75.000 $60.000 $63.900 $80.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 3,087.000 $2.000 $0.500 $0.450 $0.800 $0.400
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 3,358.000 $2.000 $0.500 $0.450 $0.800 $0.400
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 7,105.000 $6.000 $3.750 $3.550 $5.060 $6.000
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 4,076.000 $2.000 $0.880 $1.350 $1.540 $0.900
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 37.000 $15.000 $5.760 $7.000 $5.330 $6.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 3,765.000 $2.000 $0.880 $1.350 $1.540 $0.900
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 57.000 $3.000 $2.000 $2.450 $1.070 $1.750
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,098.000 $2.000 $1.000 $1.450 $1.070 $0.900
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 403.000 $10.000 $6.890 $6.950 $7.190 $7.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 16.000 $160.000 $155.000 $181.000 $149.100 $140.000
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
EA 2.000 $250.000 $199.000 $362.000 $239.630 $190.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 7.000 $250.000 $170.000 $210.000 $159.750 $160.000
REF PAV MRK TY I(W)18"(YLD TRI)(100MIL)
EA 29.000 $85.000 $38.000 $25.500 $58.580 $60.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 383.000 $2.000 $1.000 $0.850 $0.850 $0.700
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 4,183.000 $2.000 $0.870 $0.680 $0.800 $0.700
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 277.000 $2.000 $1.000 $0.850 $0.850 $0.700
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 5,183.000 $2.000 $0.870 $0.680 $0.800 $0.700
REFL PAV MRKR TY I-C
EA 66.000 $5.000 $5.000 $3.550 $15.980 $5.000
REFL PAV MRKR TY II-A-A
EA 7.000 $5.000 $5.000 $5.000 $26.630 $5.000
ELIM EXT PM & MRKS (6")
LF 836.000 $2.000 $0.750 $0.650 $2.130 $0.500
ELIM EXT PM & MRKS (24")
LF 98.000 $2.000 $3.900 $3.550 $3.200 $2.750
ELIM EXT PM & MRKS (ARROW)
EA 2.000 $2.000 $55.000 $65.000 $53.250 $39.000
ELIM EXT PM & MRKS (DBL ARROW)
EA 1.000 $2.000 $75.000 $125.000 $63.900 $50.000
ELIM EXT PM & MRKS (WORD)
EA 1.000 $2.000 $55.000 $65.000 $58.580 $47.000
PAV SURF PREP FOR MRK (6")
LF 1,360.000 $2.000 $0.250 $0.060 $0.320 $0.020
PAV SURF PREP FOR MRK (8")
LF 355.000 $2.000 $0.330 $0.080 $0.640 $0.060
PAV SURF PREP FOR MRK (24")
LF 70.000 $5.000 $55.000 $0.240 $1.070 $0.500
PAV SURF PREP FOR MRK (ARROW)
EA 2.000 $2.000 $15.000 $15.000 $21.300 $12.000
PAV SURF PREP FOR MRK (DBL ARROW)
EA 1.000 $50.000 $20.000 $30.000 $31.950 $17.000
PAV SURF PREP FOR MRK (WORD)
EA 1.000 $50.000 $15.000 $15.000 $26.630 $13.000
REMOV RDSD FLSH BCN AM (SOLAR PWRD)
EA 2.000 $1,200.000 $225.000 $1,750.000 $1,597.500 $230.000
Totals: $6,914,803.000 $5,160,281.790 $5,474,780.530 $6,111,371.500 $6,166,871.050
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $100,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $100,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $100,000.00
Total: $300,000.00