TARRANT VARIOUS (0902-90-112)

Items: 61

County: TARRANT
Length: 0.1000 MILES
Highway: VARIOUS
District: FORT WORTH
Control Number: 0902-90-112
DBE Goal: 0.0%
Project: CM 2026(684)
Guaranty: $82,000.00
Time: 192 WORKING DAYS
Engineer's Estimate: $4,188,498.30
Date: 07/02/2026 1:00 PM CDT (16 days ago)
Contract Number: 7263212
Type: INSTALL/REHABILITATE ITS
Project ID: A00064320
Contract Type: FEDERAL
Project Description: INSTALLATION OF ITS EQUIPMENT AND COMMUNICATIONS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
THERESA POER
CARLOS MOLINA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$4,188,498.30
$3,181,300.83
Over/Under Est: -24.05% -$1,007,197.47
Over/Under Est: -17.92% -$750,498.30
Amt Left: 8.07% $256,699.17
$3,484,187.59
Over/Under Est: -16.82% -$704,310.71
Amt Left: 9.52% $302,886.76
Delta: -1.34% -$46,187.59
Over/Under Est: -14.46% -$605,550.32
Amt Left: 12.63% $401,647.15
Delta: -2.83% -$98,760.39
Over/Under Est: -3.85% -$161,101.30
Amt Left: 26.6% $846,096.17
Delta: -12.40% -$444,449.02
Over/Under Est: 25.66% $1,074,963.56
Amt Left: 65.45% $2,082,161.03
Delta: -30.69% -$1,236,064.86

Bid Items & Bid Tabulations

61 Total 0 of 61
TARRANT  |  VARIOUS  |  FORT WORTH  |  0902-90-112  |  07/02/2026 1:00 PM CDT  |  $4,188,498.30  |  CM 2026(684)  |  INSTL/REHAB ITS  |  192 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SICE, INC.
FLORIDA TRAFFIC CONTROL DEVICES, INC.
MICA CORPORATION
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC
ELECNOR BELCO ELECTRIC, INC.
LUMIN8 TRANSPORTATION TECHNOLOGIES, LLC
BLOCK SODDING
SY 3,640.000 $15.000 $5.746 $5.300 $4.950 $11.170 $15.300 $6.400
VEGETATIVE WATERING
TGL 128.000 $75.000 $100.622 $91.500 $117.100 $120.000 $398.000 $109.000
DRILL SHAFT (48 IN)
LF 448.000 $675.000 $522.251 $788.000 $393.100 $599.990 $703.000 $902.000
DRILL SHAFT (54 IN)
LF 179.000 $1,000.000 $529.698 $1,063.000 $473.000 $670.520 $752.000 $1,185.000
RIPRAP (CONC)(CL A)
CY 25.000 $1,000.000 $879.377 $815.000 $755.000 $780.000 $703.000 $1,133.000
RIPRAP (MOW STRIP)(4 IN)
CY 41.200 $740.000 $809.273 $750.000 $695.000 $900.000 $730.000 $785.000
MOBILIZATION
LS 1.000 $376,140.000 $314,917.041 $200,000.000 $297,116.000 $352,962.840 $528,000.000 $487,930.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $12,000.000 $9,395.871 $2,290.000 $26,356.000 $7,544.180 $8,138.000 $26,253.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 151.000 $100.000 $153.061 $169.000 $101.200 $51.710 $89.000 $220.000
TMA (STATIONARY)
DAY 141.000 $167.000 $307.680 $169.000 $317.250 $218.620 $97.000 $287.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 360.000 $10.000 $9.551 $7.150 $6.650 $9.600 $16.000 $8.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 360.000 $5.000 $1.483 $1.400 $1.270 $2.400 $5.000 $1.600
MTL W-BEAM GD FEN (TIM POST)
LF 500.000 $50.000 $30.889 $28.600 $33.200 $37.200 $31.000 $38.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 5.000 $1,400.000 $1,482.637 $1,375.000 $1,516.000 $1,740.000 $1,468.000 $1,590.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 1.000 $500.000 $247.107 $230.060 $424.000 $240.000 $245.000 $314.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,500.000 $3,644.815 $3,375.000 $3,467.000 $3,930.000 $3,607.000 $4,640.000
CONDT (PVC) (SCH 40) (2")
LF 205.000 $29.000 $12.959 $14.400 $11.700 $14.760 $19.000 $41.000
CONDT (PVC) (SCH 40) (3")
LF 10,234.000 $27.000 $15.309 $17.650 $10.900 $30.600 $17.500 $43.000
CONDT (PVC) (SCH 80) (3") (BORE)
LF 3,825.000 $33.000 $16.067 $32.700 $21.550 $29.410 $27.000 $29.000
CONDT (RM) (3")
LF 72.000 $80.000 $38.399 $127.800 $41.700 $103.390 $85.000 $62.000
CONDUIT (PREPARE)
LF 5,515.000 $4.300 $0.618 $4.500 $1.620 $3.360 $7.400 $1.500
ELEC CONDR (NO.8) BARE
LF 2,822.000 $2.000 $1.425 $1.800 $2.210 $2.090 $2.000 $2.500
ELEC CONDR (NO.8) INSULATED
LF 1,816.000 $2.500 $1.656 $2.150 $2.210 $2.300 $2.000 $2.500
ELEC CONDR (NO.6) BARE
LF 292.000 $3.000 $1.949 $2.050 $2.770 $2.540 $2.500 $3.100
ELEC CONDR (NO.6) INSULATED
LF 584.000 $3.500 $2.273 $2.550 $2.770 $2.990 $2.500 $3.100
ELEC CONDR (NO.4) BARE
LF 1,825.000 $2.800 $2.660 $3.100 $3.530 $3.490 $3.600 $4.600
ELEC CONDR (NO.4) INSULATED
LF 3,984.000 $3.100 $3.176 $3.600 $3.530 $3.910 $3.500 $4.600
ELEC CONDR (NO.2) BARE
LF 1,934.000 $4.200 $3.959 $4.250 $5.400 $4.780 $5.000 $5.500
ELEC CONDR (NO.2) INSULATED
LF 7,828.000 $4.700 $4.650 $5.000 $5.400 $5.340 $5.000 $5.500
ELEC CONDR (NO.1) BARE
LF 2,400.000 $4.500 $6.300 $4.800 $5.900 $5.460 $6.000 $7.200
ELEC CONDR (NO.1) INSULATED
LF 4,800.000 $4.800 $7.020 $6.300 $5.900 $5.930 $6.000 $7.200
ELEC CONDR (1/0) BARE
LF 2,090.000 $8.000 $6.891 $5.650 $6.850 $6.460 $7.000 $8.400
ELEC CONDR (1/0) INSULATED
LF 6,270.000 $8.500 $4.594 $6.700 $6.850 $7.040 $7.000 $8.400
ITS GND BOX(PCAST) TY 1 (243636)W/APRN
EA 14.000 $5,200.000 $3,628.305 $5,355.000 $3,970.000 $6,350.540 $4,402.000 $6,437.000
ITS GND BOX(PCAST) TY 2 (366036)W/APRN
EA 12.000 $7,500.000 $5,560.028 $8,390.000 $5,729.000 $9,341.780 $8,574.000 $8,837.000
GROUND BOX TY D (162922)W/APRON
EA 31.000 $2,640.000 $1,250.798 $1,553.000 $1,670.000 $2,302.270 $1,651.000 $1,817.000
ELC SRV TY D 120/240 060(NS)SS(N)PS(U)
EA 6.000 $10,000.000 $6,202.055 $8,400.000 $9,110.000 $8,149.390 $7,459.000 $12,803.000
ELC SRV TY D 120/240 060(NS)SS(N)SP(O)
EA 13.000 $8,500.000 $7,378.837 $12,200.000 $7,421.000 $8,283.790 $7,325.000 $12,561.000
ELC SRV TY D 120/240 150(NS)SS(N)PS(U)
EA 1.000 $10,000.000 $6,616.532 $11,100.000 $9,721.000 $8,703.790 $7,927.000 $12,803.000
INS OH SN SUP(35 FT BAL TEE)
EA 6.000 $45,000.000 $47,371.971 $50,565.000 $63,311.000 $46,682.180 $55,000.000 $71,670.000
SIGN WALKWAY (48 IN) WITH HNDRL
LF 49.980 $650.000 $640.136 $648.000 $534.000 $748.000 $1,000.000 $707.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GF2
EA 9.000 $50.000 $30.889 $40.000 $38.000 $30.000 $31.000 $126.000
INSTL DEL ASSM (D-SY)SZ 1(YFLX)GF2
EA 3.000 $50.000 $30.889 $35.000 $38.250 $30.000 $31.000 $126.000
REPLACE BREAKER PANEL
EA 1.000 $5,000.000 $3,703.352 $1,600.000 $3,823.000 $1,098.020 $1,338.000 $611.000
INSTALL DMS (POLE MTD CABINET)
EA 6.000 $23,300.000 $10,436.767 $12,725.000 $16,475.000 $12,744.560 $15,138.000 $10,576.000
ITS COM CBL (ETHERNET)
LF 335.000 $5.000 $1.397 $3.050 $8.150 $8.830 $2.000 $1.900
ITS RVSD (DATA COLLECT & WWA) SYS
EA 19.000 $21,000.000 $13,559.991 $11,900.000 $14,602.000 $9,492.110 $15,434.000 $13,634.000
ITS POLE (60 FT)(90 MPH)
EA 20.000 $23,600.000 $28,016.899 $26,140.000 $21,405.000 $23,122.940 $27,175.000 $47,331.000
ITS POLE MNT CAB (TY 3)(CONF 2)
EA 18.000 $14,000.000 $6,039.370 $5,320.000 $7,110.000 $6,062.510 $7,793.000 $8,166.000
GROUND BOX (PREPARE)
EA 21.000 $350.000 $494.213 $330.000 $373.000 $830.830 $245.000 $957.000
CCTV FIELD EQUIPMENT (DIGITAL)
EA 20.000 $9,500.000 $7,342.480 $8,930.000 $10,805.000 $7,757.680 $11,049.000 $9,028.000
CCTV MOUNT (PEDESTAL)
EA 20.000 $650.000 $846.032 $465.000 $976.000 $848.830 $2,224.000 $412.000
FIBER OPTIC CBL (SINGLE-MODE)(36 FIBER)
LF 7,895.000 $5.000 $2.306 $4.300 $5.910 $2.650 $3.000 $2.000
FIBER OPTIC FUSION SPLICE
EA 192.000 $100.000 $71.661 $54.000 $66.100 $72.000 $65.000 $49.000
FO SPLICE ENCLOSURE (TYPE 1)
EA 11.000 $2,675.000 $1,015.607 $1,145.000 $1,950.000 $2,547.050 $1,247.000 $592.000
FO CBL (12 SMF)(PIGTAIL)
LF 740.000 $5.000 $2.048 $2.400 $10.450 $8.740 $16.000 $62.000
PRETERM FIBER PATCH PANEL (12 POSITION)
EA 8.000 $2,000.000 $684.484 $972.000 $1,940.000 $2,173.520 $1,614.000 $8,188.000
PRETERM FIBER PATCH PANEL (24 POSITION)
EA 4.000 $2,800.000 $983.483 $1,315.000 $2,290.000 $2,898.020 $3,227.000 $8,251.000
FO CBL (24 SMF)(PIGTAIL)
LF 1,275.000 $5.000 $2.157 $1.750 $6.450 $8.500 $23.000 $62.000
INSTALLATION OF ETHERNET SWITCH
EA 10.000 $2,000.000 $792.697 $860.000 $1,767.000 $1,636.090 $1,000.000 $566.000
INSTALLATION OF CELLULAR ROUTER
EA 15.000 $2,000.000 $792.638 $290.000 $1,432.000 $1,636.090 $1,000.000 $1,832.000
Totals: $4,188,498.300 $3,181,300.780 $3,438,000.000 $3,484,187.590 $3,582,947.980 $4,027,397.000 $5,263,461.860
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
PUBLIC UTILITY FORCE ACCT WORK (PART) $88,600.00
MATERIAL FURNISHED BY THE STATE (PART) $646,195.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $20,600.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $15,000.00
Total: $775,395.00