Show Job Controls
Bid Cobra

TARRANT SH 199 (0171-04-087)

Items: 20

County: TARRANT
Length: 0.2900 MILES (0.0296 MILES)
Highway: SH 199
District: FORT WORTH
Control Number: 0171-04-087
DBE Goal: 0.0%
Project: F 2026(731)
Guaranty: $7,000.00
Time: 32 WORKING DAYS
Engineer's Estimate: $347,739.50
Date: 07/01/2026 1:00 PM CDT (17 days ago)
Contract Number: 7263031
Type: LANDSCAPE DEVELOPMENT
Project ID: A00217580
Contract Type: FEDERAL
Project Description: FY 2026 GREEN RIBBON PROJECT: LANDSCAPE ENHANCEMENT- SH 199 & FM 730 CITY OF AZLE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DANIEL POOLE
SURAFEL SINTAYEHU
JASON PASCOE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$347,739.50
Over/Under Est: -17.79% -$61,869.50
Over/Under Est: -7.14% -$24,821.70
Amt Left: 12.96% $37,047.80
Over/Under Est: -6.3% -$21,921.05
Amt Left: 13.97% $39,948.45
Delta: -0.90% -$2,900.65
Over/Under Est: -4.07% -$14,155.10
Amt Left: 16.69% $47,714.40
Delta: -2.38% -$7,765.95
Over/Under Est: 0.97% $3,368.50
Amt Left: 22.82% $65,238.00
Delta: -5.25% -$17,523.60
Over/Under Est: 6.05% $21,037.50
Amt Left: 29% $82,907.00
Delta: -5.03% -$17,669.00

Bid Items & Bid Tabulations

20 Total 0 of 20
TARRANT  |  SH 199  |  FORT WORTH  |  0171-04-087  |  07/01/2026 1:00 PM CDT  |  $347,739.50  |  F 2026(731)  |  LANDSCAPE DEVELOPMENT  |  32 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GREEN SAGE SERVICES LLC
CENTRAL NORTH CONSTRUCTION, LLC
APEX LANDSCAPE & IRRIGATION, LLC
ABESCAPE LANDSCAPING, LLC
C. GREEN SCAPING, L.P.
PACE CONSTRUCTION SERVICES LLC
PREPARING ROW
AC 0.750 $25,000.000 $7,500.000 $50,000.000 $14,000.000 $10,000.000 $13,680.000 $15,000.000
COMPOST MANUF TOPSOIL (4")
SY 1,360.000 $5.000 $4.000 $3.000 $4.600 $2.250 $13.800 $15.000
IRRIGATION SYSTEM
LS 1.000 $75,000.000 $34,000.000 $92,187.600 $26,000.000 $94,396.400 $89,560.000 $15,000.000
LANDSCAPE EDGE (CONC)
LF 1,246.000 $22.000 $27.000 $50.000 $32.000 $21.000 $28.000 $40.000
LOOSE AGGR GRND COVER (TY I)
CY 125.000 $200.000 $230.000 $100.000 $220.000 $135.000 $357.000 $350.000
LOOSE AGGR GRND COVER (TY II)
CY 147.000 $210.000 $260.000 $100.000 $220.000 $135.000 $357.000 $350.000
PLANT MATERIAL (3 GAL)
EA 1,138.000 $25.000 $18.500 $14.000 $30.000 $20.000 $10.000 $50.000
PLANT MATERIAL (5 GAL)
EA 474.000 $50.000 $21.000 $20.000 $35.000 $45.000 $10.000 $75.000
PLANT MATERIAL (15 GAL)
EA 30.000 $300.000 $210.000 $200.000 $285.000 $150.000 $120.000 $150.000
PLANT MATERIAL (45 GAL) (TREE)
EA 12.000 $600.000 $520.000 $400.000 $570.000 $450.000 $280.000 $1,000.000
LANDSCAPE ESTABLISH
MO 12.000 $1,250.000 $2,000.000 $1,900.000 $2,000.000 $2,000.000 $1,500.000 $1,000.000
IRRIG SYS OPER AND MAINT (SCH A)
MO 12.000 $1,000.000 $1,000.000 $900.000 $1,300.000 $1,500.000 $1,000.000 $1,000.000
RDSIDE AMENITY (BOULDER)
EA 25.000 $750.000 $250.000 $200.000 $750.000 $500.000 $390.000 $50.000
MOBILIZATION
LS 1.000 $28,000.000 $27,000.000 $15,000.000 $32,500.000 $25,000.000 $10,500.000 $10,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $3,000.000 $4,500.000 $2,500.000 $5,150.000 $5,000.000 $4,500.000 $5,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 32.000 $100.000 $150.000 $25.000 $185.000 $100.000 $80.000 $250.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 841.000 $4.500 $5.000 $0.100 $1.950 $1.500 $6.000 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 841.000 $3.000 $1.000 $0.100 $0.500 $0.500 $2.000 $2.000
CONDT (HDPE) (1")
LF 90.000 $30.000 $35.000 $8.000 $20.000 $145.000 $7.000 $25.000
CONDT (PVC) (SCH 80) (4") (BORE)
LF 90.000 $40.000 $60.000 $35.000 $70.000 $48.000 $92.000 $75.000
Totals: $347,739.500 $285,870.000 $322,917.800 $325,818.450 $333,584.400 $351,108.000 $368,777.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
CONTRACTOR FORCE ACCOUNT WORK (PART) $20,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $20,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $360,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $25,000.00
Total: $425,000.00