TARRANT SH 199 (0171-04-087)
Items: 20
County: TARRANT
Length: 0.2900 MILES (0.0296 MILES)
Highway: SH 199
District: FORT WORTH
Control Number: 0171-04-087
DBE Goal: 0.0%
Project: F 2026(731)
Guaranty: $7,000.00
Time: 32 WORKING DAYS
Engineer's Estimate: $347,739.50
Date: 07/01/2026 1:00 PM CDT (17 days ago)
Contract Number: 7263031
Type: LANDSCAPE DEVELOPMENT
Project ID: A00217580
Contract Type: FEDERAL
Project Description: FY 2026 GREEN RIBBON PROJECT: LANDSCAPE ENHANCEMENT- SH 199 & FM 730 CITY OF AZLE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
TARRANT SH 199 (0171-04-087)
Project Name: N/A
Project: F 2026(731)
Engineer's Estimate: $347,739.50
Length: 0.2900 MILES (0.0296 MILES)
Project Class: LANDSCAPE & SCENIC ENHANCEMENT
Limits From: EAST SH199 AT BOYD RD (FM 730)
Limits To: WEST SH199 AT BOYD RD (FM 730)
Project Description: FY 2026 GREEN RIBBON PROJECT: LANDSCAPE ENHANCEMENT- SH 199 & FM 730 CITY OF AZLE
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$347,739.50 | |||
| $285,870.00 |
-17.79%
-$61,869.50
|
|||
| $322,917.80 |
-7.14%
-$24,821.70
|
12.96%
$37,047.80
|
||
| $325,818.45 |
-6.3%
-$21,921.05
|
13.97%
$39,948.45
|
-0.90%
-$2,900.65
|
|
| $333,584.40 |
-4.07%
-$14,155.10
|
16.69%
$47,714.40
|
-2.38%
-$7,765.95
|
|
| $351,108.00 |
0.97%
$3,368.50
|
22.82%
$65,238.00
|
-5.25%
-$17,523.60
|
|
| $368,777.00 |
6.05%
$21,037.50
|
29%
$82,907.00
|
-5.03%
-$17,669.00
|
E
Engineer's Estimate
$347,739.50
$285,870.00
Over/Under Est:
-17.79%
-$61,869.50
$322,917.80
Over/Under Est:
-7.14%
-$24,821.70
Amt Left:
12.96%
$37,047.80
$325,818.45
Over/Under Est:
-6.3%
-$21,921.05
Amt Left:
13.97%
$39,948.45
Delta:
-0.90%
-$2,900.65
$333,584.40
Over/Under Est:
-4.07%
-$14,155.10
Amt Left:
16.69%
$47,714.40
Delta:
-2.38%
-$7,765.95
$351,108.00
Over/Under Est:
0.97%
$3,368.50
Amt Left:
22.82%
$65,238.00
Delta:
-5.25%
-$17,523.60
$368,777.00
Over/Under Est:
6.05%
$21,037.50
Amt Left:
29%
$82,907.00
Delta:
-5.03%
-$17,669.00
Bid Items & Bid Tabulations
20
Total
0 of 20
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| CONTRACTOR FORCE ACCOUNT WORK (PART) | $20,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $20,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $360,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $25,000.00 |
| Total: | $425,000.00 |