Show Job Controls
Bid Cobra

TARRANT US 377 (0081-02-076)

Items: 24

County: TARRANT
Length: N/A
Highway: US 377
District: FORT WORTH
Control Number: 0081-02-076
DBE Goal: N/A
Project: F 2022(846)
Guaranty: N/A
Time: 64 WORKING DAYS
Engineer's Estimate: $416,011.50
Date: 08/03/2022 (3 years ago)
Contract Number: N/A
Type: LANDSCAPE DEVELOPMENT
Mail/Deliver Bids To: N/A
DAVID NEELEY
RUSSELL POER
RIDWAN NAIFE
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$416,011.50
Over/Under Est: 13.19% $54,860.50
Over/Under Est: 21.43% $89,164.25
Amt Left: 7.29% $34,303.75
Over/Under Est: 29.33% $122,034.50
Amt Left: 14.27% $67,174.00
Delta: -6.51% -$32,870.25
Subcontractor Percentage Amount
BARRICADES UNLIMITED 1.04% $4,909.76
Total: 1.04% $4,909.76

Bid Items & Bid Tabulations

24 Total 0 of 24
TARRANT  |  US 377  |  FORT WORTH  |  0081-02-076  |  08/03/2022  |  $416,011.50  |  F 2022(846)  |  LANDSCAPE DEVELOPMENT  |  64 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
APEX LANDSCAPE & IRRIGATION, LLC
CENTRAL NORTH CONSTRUCTION, LLC
ENCINO LANDSCAPE, INC.
PREPARING ROW
AC 1.000 $7,500.000 $20,000.000 $50,000.000 $5,000.000
COMPOST MANUF TOPSOIL (4")
SY 568.000 $4.000 $5.000 $10.000 $5.000
IRRIGATION SYSTEM
LS 1.000 $32,000.000 $45,000.000 $43,010.750 $80,000.000
PLANT MATERIAL (1-GAL)
EA 105.000 $15.000 $10.000 $11.000 $15.000
PLANT MATERIAL (3-GAL)
EA 570.000 $24.000 $30.000 $25.000 $35.000
PLANT MATERIAL (45 GAL) (TREE)
EA 37.000 $400.000 $295.000 $425.000 $500.000
LANDSCAPE EDGE (TYPE I)
LF 1,563.000 $25.000 $25.000 $9.000 $5.000
LANDSCAPE EDGE (TYPE II)
LF 2,076.000 $24.000 $30.000 $32.000 $35.000
CONC LNDSCP EDG (12 IN WIDTH)
LF 2,898.000 $25.000 $30.000 $28.000 $30.000
PLANT MAINTENANCE
MO 12.000 $1,500.000 $1,250.000 $1,500.000 $2,000.000
IRRIGATION SYSTEM OPER AND MAINT
MO 12.000 $750.000 $750.000 $650.000 $1,000.000
MOBILIZATION
LS 1.000 $42,300.000 $40,000.000 $24,000.000 $40,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $3,500.000 $4,000.000 $1,800.000 $4,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 27.000 $50.000 $30.000 $1.000 $50.000
CONSTRUCTION EXITS (REMOVE)
SY 27.000 $25.000 $5.000 $1.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 299.000 $7.000 $2.000 $1.000 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 299.000 $2.500 $1.000 $1.000 $1.000
COLORED TEXTURED CONC (6")
SY 54.000 $100.000 $145.000 $150.000 $300.000
LANDSCAPE AMENITY (TY 11)
EA 1.000 $17,000.000 $5,000.000 $10,000.000 $10,000.000
LANDSCAPE AMENITY (BOULDER)
EA 25.000 $700.000 $650.000 $400.000 $1,000.000
LOOSE AGGR FOR GROUNDCOVER (TYPE I)
CY 76.000 $110.000 $250.000 $220.000 $200.000
LOOSE AGGR FOR GROUNDCOVER (TYPE II)
CY 86.000 $110.000 $250.000 $90.000 $100.000
LOOSE AGGR FOR GROUNDCOVER (TYPE III)
CY 298.000 $135.000 $125.000 $350.000 $250.000
LOOSE AGGR FOR GROUNDCOVER (TYPE IV)
CY 2.000 $110.000 $500.000 $500.000 $300.000
Totals: $416,011.500 $470,872.000 $505,175.750 $538,046.000