TARRANT BU 287P (0013-10-098)

Items: 76

County: TARRANT
Length: 3.5000 MILES
Highway: BU 287P
District: FORT WORTH
Control Number: 0013-10-098
DBE Goal: 0.0%
Project: F 2026(884)
Guaranty: $100,000.00
Time: 157 WORKING DAYS
Engineer's Estimate: $8,675,951.77
Date: 07/01/2026 1:00 PM CDT (17 days ago)
Contract Number: 7263039
Type: RESURFACE ROADWAY
Project ID: A00217855
Contract Type: FEDERAL
Project Description: MILLING & OVERLAY, PAVEMENT BASE REPAIR, PAVEMENT MARKINGS, MBGF, RUMBLE STRIPS, CONCRETE TRAFFIC BARRIER
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DANIEL POOLE
SURAFEL SINTAYEHU
JASON PASCOE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$8,675,951.77
$8,547,147.17
Over/Under Est: -1.48% -$128,804.60
Over/Under Est: 5.81% $503,783.16
Amt Left: 7.4% $632,587.76
Over/Under Est: 11.31% $981,530.21
Amt Left: 12.99% $1,110,334.81
Delta: -5.20% -$477,747.05
Over/Under Est: 12.7% $1,102,244.40
Amt Left: 14.4% $1,231,049.00
Delta: -1.25% -$120,714.19
Over/Under Est: 19.68% $1,707,574.89
Amt Left: 21.49% $1,836,379.49
Delta: -6.19% -$605,330.49
Over/Under Est: 20.23% $1,754,961.18
Amt Left: 22.04% $1,883,765.78
Delta: -0.46% -$47,386.29
$11,700,978.70
Over/Under Est: 34.87% $3,025,026.93
Amt Left: 36.9% $3,153,831.53
Delta: -12.18% -$1,270,065.75

Bid Items & Bid Tabulations

76 Total 0 of 76
TARRANT  |  BU 287P  |  FORT WORTH  |  0013-10-098  |  07/01/2026 1:00 PM CDT  |  $8,675,951.77  |  F 2026(884)  |  RESURF ROADWAY  |  157 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JAGOE-PUBLIC COMPANY
AUSTIN BRIDGE & ROAD SERVICES, LP
TEXAS MATERIALS GROUP, INC.
FOUTSCO PAVING COMPANY, LLC
PEACHTREE CONSTRUCTION, LTD.
EUROVIA ATLANTIC COAST LLC
OVERLAND CORPORATION
RMV (4"-8") TRT/UNTRT BASE & ASPH PAV
SY 4,904.000 $6.000 $12.000 $8.280 $11.000 $15.000 $11.500 $16.000 $16.300
BACKFILL (TY A OR B)
STA 266.000 $150.000 $280.000 $170.000 $335.000 $150.000 $500.000 $375.000 $350.000
ASPH (AC-20-5TR)
GAL 50,566.000 $5.000 $5.300 $5.250 $4.000 $3.000 $5.200 $5.300 $5.500
AGGR (TY-B, GR-4)(SAC-B)
CY 1,165.000 $180.000 $255.000 $225.000 $190.000 $250.000 $250.000 $255.000 $260.000
D-GR HMA TY-D PG64-22 (LEVEL-UP)
TON 2,831.000 $115.000 $130.000 $94.750 $137.000 $136.000 $160.000 $140.000 $153.000
SP MIXES SP-C SAC-A PG70-28
TON 14,703.670 $120.000 $125.000 $159.500 $155.000 $177.000 $155.500 $156.000 $170.000
TACK COAT
GAL 25,575.000 $0.500 $2.500 $4.200 $0.010 $0.100 $2.000 $3.000 $4.350
TOM-F PG76-22 SAC-B
TON 3,131.000 $235.000 $145.000 $170.000 $175.000 $190.000 $170.000 $165.000 $181.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 15,727.000 $75.000 $39.000 $69.520 $65.000 $45.000 $55.000 $64.000 $70.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 2,193.000 $110.000 $80.000 $77.070 $95.000 $95.000 $95.000 $88.000 $120.000
PLANE ASPH CONC PAV(0" TO 6")
SY 127,858.000 $2.300 $3.250 $2.500 $2.980 $1.000 $3.250 $4.150 $6.000
FULL - DEPTH REPAIR CRCP (10")
SY 1,023.000 $195.000 $180.000 $355.940 $330.000 $305.000 $340.000 $326.000 $356.000
RIPRAP (CONC)(6 IN)
CY 1,020.000 $725.000 $300.000 $455.210 $590.000 $356.000 $610.000 $784.000 $455.250
RIPRAP (MOW STRIP)(4 IN)
CY 151.000 $615.000 $950.000 $516.160 $625.000 $475.000 $650.000 $680.000 $660.000
MOBILIZATION
LS 1.000 $780,106.070 $948,000.000 $1,009,770.840 $780,000.000 $625,000.000 $700,000.000 $825,000.000 $1,169,780.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $9,500.000 $26,000.000 $20,739.500 $21,500.000 $100,000.000 $35,000.000 $38,000.000 $29,050.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $13,000.000 $8,147.270 $10,000.000 $20,000.000 $14,000.000 $18,000.000 $2,250.000
TMA (STATIONARY)
DAY 300.000 $200.000 $200.000 $1.000 $1.000 $1.000 $175.000 $325.000 $25.000
TMA (MOBILE OPERATION)
DAY 40.000 $240.000 $200.000 $1.000 $1.000 $1.000 $450.000 $715.000 $50.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,365.000 $4.500 $3.750 $3.600 $4.500 $1.000 $3.750 $5.500 $3.600
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,365.000 $1.500 $1.000 $1.100 $0.650 $0.500 $1.150 $2.000 $1.100
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 10,980.000 $52.000 $95.000 $54.630 $87.000 $97.000 $100.000 $92.500 $100.000
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 10,980.000 $17.750 $15.000 $7.200 $18.000 $25.000 $26.500 $12.500 $35.000
PORT CTB (PINNING)
EA 2,932.000 $58.000 $100.000 $95.310 $150.000 $100.000 $130.000 $53.000 $150.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 29,198.000 $0.300 $0.210 $0.210 $0.360 $0.210 $0.230 $0.490 $0.350
MTL W-BEAM GD FEN (TIM POST)
LF 2,025.000 $28.000 $24.000 $22.250 $24.000 $22.500 $25.500 $22.250 $24.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 9.000 $1,200.000 $1,200.000 $1,645.000 $1,200.000 $1,300.000 $1,800.000 $1,645.000 $1,800.000
REMOVE METAL BEAM GUARD FENCE
LF 2,025.000 $3.000 $2.500 $2.750 $2.500 $2.000 $3.150 $2.750 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 9.000 $200.000 $150.000 $275.000 $150.000 $200.000 $265.000 $275.000 $300.000
GUARDRAIL END TREATMENT (INSTALL)
EA 9.000 $3,000.000 $3,000.000 $3,216.000 $2,950.000 $3,125.000 $3,650.000 $3,216.000 $3,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 9.000 $245.000 $250.000 $275.000 $250.000 $200.000 $265.000 $275.000 $350.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 7.000 $1,400.000 $800.000 $1,289.960 $2,000.000 $4,000.000 $4,700.000 $3,535.000 $4,500.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $755.000 $800.000 $1,914.970 $900.000 $2,800.000 $1,600.000 $1,969.250 $1,500.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 1.000 $24,700.000 $29,000.000 $25,854.910 $13,000.000 $27,500.000 $34,000.000 $32,325.550 $32,000.000
IN SM RD SN SUP&AM (INST SIGN ONLY)
EA 43.000 $355.000 $210.000 $205.550 $270.000 $210.000 $315.000 $205.550 $225.000
REMOVE SM RD SN SUP&AM (SIGN ONLY)
EA 43.000 $41.000 $70.000 $69.000 $70.000 $69.000 $80.000 $69.000 $80.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 40.000 $11.000 $25.000 $25.000 $25.000 $31.000 $30.000 $25.000 $26.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB (BI)
EA 752.000 $10.000 $15.000 $15.000 $20.000 $29.000 $16.000 $15.000 $2.500
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 16,809.000 $0.300 $0.300 $0.300 $0.210 $0.210 $0.330 $0.300 $0.300
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 72,344.000 $0.300 $0.240 $0.240 $0.200 $0.200 $0.270 $0.240 $0.250
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 13,184.000 $0.500 $0.500 $0.450 $0.500 $0.500 $0.500 $0.450 $0.450
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 842.000 $2.800 $2.750 $2.750 $4.000 $4.000 $3.000 $2.750 $2.750
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 78.000 $30.000 $40.000 $40.000 $45.000 $45.000 $44.000 $40.000 $40.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 78.000 $30.000 $50.000 $50.000 $45.000 $45.000 $55.000 $50.000 $50.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 81,120.000 $0.300 $0.240 $0.240 $0.200 $0.200 $0.270 $0.240 $0.500
WK ZN PAV MRK NON-REMOV (Y)24"(SLD)
LF 1,906.000 $2.000 $2.750 $2.750 $3.000 $3.000 $3.000 $2.750 $2.750
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 2,555.000 $1.500 $2.000 $0.500 $0.840 $5.000 $2.500 $2.190 $1.650
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 152.000 $1.100 $1.000 $1.000 $1.000 $1.000 $1.100 $1.000 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 6,592.000 $1.000 $0.900 $0.900 $0.850 $1.000 $1.000 $0.900 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 421.000 $8.000 $7.000 $6.750 $6.490 $1.000 $7.500 $6.750 $7.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 39.000 $145.000 $140.000 $140.000 $149.000 $149.000 $155.000 $140.000 $140.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 39.000 $150.000 $160.000 $155.000 $155.000 $155.000 $170.000 $155.000 $155.000
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 953.000 $9.000 $7.000 $6.750 $6.400 $6.400 $7.500 $6.750 $6.750
TY I HIGH PERF PM (W)6"(BRK)(100MIL)
LF 8,426.000 $0.700 $0.600 $0.550 $0.550 $0.540 $0.600 $0.550 $0.550
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 36,172.000 $0.700 $0.500 $0.510 $0.540 $0.530 $0.550 $0.510 $0.550
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 40,560.000 $0.700 $0.500 $0.510 $0.540 $0.530 $0.550 $0.510 $0.550
PAVEMENT SLER 6"
LF 85,289.000 $0.150 $0.130 $0.130 $0.130 $0.130 $0.140 $0.130 $0.150
PAVEMENT SLER 8"
LF 6,592.000 $0.250 $0.180 $0.180 $0.200 $0.200 $0.200 $0.180 $0.200
PAVEMENT SLER 24"
LF 1,374.000 $1.150 $1.000 $1.000 $0.700 $0.700 $1.100 $1.000 $1.000
PAVEMENT SLER (ARROW)
EA 39.000 $9.000 $15.000 $15.000 $12.000 $12.000 $16.500 $15.000 $15.000
PAVEMENT SLER (WORD)
EA 39.000 $9.000 $15.000 $15.000 $12.000 $12.000 $16.500 $15.000 $15.000
REFL PAV MRKR TY I-C
EA 351.000 $5.000 $4.000 $3.850 $4.000 $3.980 $4.250 $3.850 $3.850
REFL PAV MRKR TY II-A-A
EA 452.000 $4.500 $4.000 $3.850 $4.000 $3.980 $4.250 $3.850 $3.850
REFL PAV MRKR TY II-C-R
EA 461.000 $7.000 $4.000 $3.850 $4.000 $3.980 $4.250 $3.850 $3.850
PAV SURF PREP FOR MRK (6")
LF 16,418.000 $0.110 $0.100 $0.100 $0.210 $0.240 $0.110 $0.100 $0.200
PAV SURF PREP FOR MRK (8")
LF 3,082.000 $0.110 $0.200 $0.200 $0.300 $0.300 $0.220 $0.200 $0.200
PAV SURF PREP FOR MRK (12")
LF 210.000 $0.290 $1.000 $1.000 $0.600 $0.600 $1.100 $1.000 $1.000
PAV SURF PREP FOR MRK (24")
LF 235.000 $1.010 $2.000 $2.000 $0.700 $0.700 $2.150 $2.000 $2.000
PAV SURF PREP FOR MRK (ARROW)
EA 18.000 $16.400 $30.000 $30.000 $10.000 $10.000 $33.000 $30.000 $30.000
PAV SURF PREP FOR MRK (WORD)
EA 18.000 $17.400 $40.000 $40.000 $10.000 $10.000 $44.000 $40.000 $40.000
PAV SURF PREP FOR MRK (RPM)
EA 643.000 $0.500 $1.000 $1.000 $0.400 $0.400 $1.100 $1.000 $1.000
SPALLING REPAIR (HYDRAULIC CEMENT)
CF 921.000 $275.000 $25.000 $190.000 $259.000 $100.000 $270.000 $225.000 $350.000
FULL - WIDTH MOWING
AC 14.150 $33.000 $450.000 $100.000 $400.000 $500.000 $700.000 $550.000 $200.000
LITTER REMOVAL
AC 14.150 $16.000 $20.000 $819.050 $400.000 $250.000 $1,000.000 $850.000 $2,500.000
TREE TRIMMING / BRUSH REMOVAL
MI 2.650 $2,077.000 $37,000.000 $36,645.000 $5,000.000 $1,000.000 $40,000.000 $36,650.000 $37,000.000
DITCH CLEANING AND RESHAPING (FOOT)
LF 13,557.000 $1.600 $1.500 $0.830 $2.000 $6.000 $4.000 $4.500 $1.500
Totals: $8,675,951.770 $8,547,147.170 $9,179,734.922 $9,657,481.980 $9,778,196.170 $10,383,526.655 $10,430,912.950 $11,700,978.700
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (PART) $5,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $40,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $50,000.00
Total: $100,000.00