Bid Cobra

TARRANT IH 820 (0008-15-052)

Items: 37

County: TARRANT
Length: N/A
Highway: IH 820
District: FORT WORTH
Control Number: 0008-15-052
DBE Goal: N/A
Project: C 8-15-52
Guaranty: N/A
Time: 128 WORKING DAYS
Engineer's Estimate: $4,833,226.03
Date: 05/07/2020 (6 years ago)
Contract Number: N/A
Type: RESURFACE ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$4,833,226.03
$3,195,838.30
Over/Under Est: -33.88% -$1,637,387.73
$4,235,996.87
Over/Under Est: -12.36% -$597,229.16
Amt Left: 32.55% $1,040,158.57
Over/Under Est: -7.04% -$340,198.03
Amt Left: 40.59% $1,297,189.70
Delta: -6.07% -$257,031.13
$4,597,438.38
Over/Under Est: -4.88% -$235,787.65
Amt Left: 43.86% $1,401,600.08
Delta: -2.32% -$104,410.38
Over/Under Est: -0.24% -$11,642.73
Amt Left: 50.87% $1,625,745.00
Delta: -4.88% -$224,144.92
$4,999,811.35
Over/Under Est: 3.45% $166,585.32
Amt Left: 56.45% $1,803,973.05
Delta: -3.70% -$178,228.05

Bid Items & Bid Tabulations

37 Total 0 of 37
TARRANT  |  IH 820  |  FORT WORTH  |  0008-15-052  |  05/07/2020  |  $4,833,226.03  |  C 8-15-52  |  RESURF ROADWAY  |  128 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
O. TREVINO CONSTRUCTION, LLC
DIAMOND SURFACE, INC.
RAGLE CONSTRUCTION, INC.
ROADWORX, INC.
SEMA CONSTRUCTION, INC.
3LW CIVIL LLC
FULL-DEPTH REPAIR CRCP (8"-10")
SY 2,050.000 $200.000 $210.000 $361.000 $375.000 $327.750 $250.000 $575.000
RIPRAP (MOW STRIP)(5 IN)
CY 816.000 $400.000 $565.000 $450.000 $840.000 $589.950 $475.000 $525.000
MOBILIZATION
LS 1.000 $480,000.000 $315,000.000 $868,115.000 $440,000.000 $617,579.950 $480,000.000 $450,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $9,500.000 $25,000.000 $2,082.000 $97,000.000 $89,693.250 $120,000.000 $30,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 500.000 $2.200 $2.500 $2.190 $1.750 $8.630 $1.900 $3.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 500.000 $0.650 $0.900 $0.750 $0.750 $4.030 $0.750 $1.500
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 500.000 $3.250 $4.000 $3.570 $3.750 $6.330 $5.400 $7.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 500.000 $0.860 $1.250 $1.070 $0.500 $4.600 $1.000 $2.000
MTL W-BEAM GD FEN (TIM POST)
LF 11,103.000 $21.260 $19.000 $21.250 $17.000 $19.550 $19.000 $23.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 46.000 $1,100.000 $1,100.000 $1,250.000 $1,000.000 $1,150.000 $1,100.000 $1,300.000
MTL BM GD FEN TRANS (31"-28")(25')
EA 38.000 $1,200.000 $470.000 $531.250 $425.000 $488.750 $500.000 $54.000
REMOVE METAL BEAM GUARD FENCE
LF 15,088.000 $2.900 $2.000 $2.190 $1.750 $2.010 $2.000 $3.000
GUARDRAIL END TREATMENT (INSTALL)
EA 58.000 $2,600.000 $2,600.000 $3,000.000 $2,400.000 $2,760.000 $2,700.000 $2,800.000
GUARDRAIL END TREATMENT (REMOVE)
EA 58.000 $275.000 $245.000 $275.000 $220.000 $253.000 $250.000 $330.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BR)
EA 270.000 $30.000 $31.000 $35.630 $28.500 $32.780 $30.000 $32.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 27,250.000 $0.750 $0.500 $0.330 $0.400 $0.630 $0.500 $0.520
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 47,430.000 $0.300 $0.500 $0.270 $0.400 $0.520 $0.500 $0.520
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 23,040.000 $0.890 $0.700 $0.500 $0.600 $0.860 $0.700 $0.780
WK ZN PAV MRK NON-REMOV (W)12"(SLD)
LF 1,240.000 $4.000 $2.400 $1.440 $2.000 $4.600 $2.300 $2.600
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 55,570.000 $0.300 $0.500 $0.260 $0.400 $0.520 $0.500 $0.520
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 37,500.000 $1.250 $0.920 $1.000 $1.250 $2.620 $1.650 $2.000
PAVEMENT SEALER (SYMBOL)
EA 7.000 $60.000 $300.000 $181.250 $250.000 $115.000 $270.000 $325.000
PREFAB PAV MRK TY C (MULTI) (SHIELD)
EA 7.000 $2,000.000 $2,400.000 $4,125.000 $2,000.000 $4,600.000 $2,200.000 $2,600.000
REFL PAV MRKR TY II-C-R
EA 1,470.000 $4.500 $4.500 $4.380 $3.750 $5.750 $4.100 $4.500
ELIM EXT PAV MRK & MRKS (6")
LF 11,445.000 $0.600 $0.500 $0.440 $0.400 $1.150 $0.500 $0.520
PAV SURF PREP FOR MRK (6")
LF 8,115.000 $0.750 $0.120 $0.250 $0.100 $0.580 $0.120 $0.150
PAV SURF PREP FOR MRKS (SHIELD)
EA 7.000 $11.500 $240.000 $62.500 $200.000 $212.750 $220.000 $260.000
CONTINUOUS DIAMOND GRINDING CONC PVMT
SY 204,130.000 $10.000 $4.400 $4.750 $5.400 $4.510 $7.500 $5.500
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 1,470.000 $110.000 $40.000 $81.250 $20.000 $86.250 $85.000 $200.000
MULTIPOLYMER PAV MRK (W)(6")(SLD)
LF 47,430.000 $0.500 $0.950 $0.690 $0.800 $0.670 $0.900 $0.750
MULTIPOLYMER PAV MRK (W)(6")(BRK)
LF 27,250.000 $0.670 $0.950 $0.690 $0.800 $0.750 $0.900 $0.850
MULTIPOLYMER PAV MRK (W)(8")(SLD)
LF 23,040.000 $1.500 $1.200 $1.060 $1.000 $0.970 $1.100 $1.600
MULTIPOLYMER PAV MRK (W)(12")(SLD)
LF 1,240.000 $4.000 $3.500 $2.500 $3.000 $4.600 $3.300 $5.000
MULTIPOLYMER PAV MRK (W)(12")(LNDP)
LF 570.000 $2.250 $3.500 $3.130 $3.000 $3.280 $3.300 $3.000
MULTIPOLYMER PAV MRK (Y)(6")(SLD)
LF 55,570.000 $0.560 $0.950 $0.690 $0.800 $0.670 $0.900 $0.800
MULTIPOLYMER PAV MRK (BLK)(6")(BRK)
LF 27,250.000 $0.600 $0.950 $0.690 $0.800 $0.750 $0.900 $1.250
TMA (STATIONARY)
DAY 1,470.000 $350.000 $40.000 $231.250 $100.000 $225.590 $150.000 $275.000
Totals: $4,833,226.030 $3,195,838.300 $4,235,996.870 $4,493,028.000 $4,597,438.380 $4,821,583.300 $4,999,811.350