STONEWALL US 380 (0106-04-036)
Items: 82
County: STONEWALL
Length: N/A
Highway: US 380
District: ABILENE
Control Number: 0106-04-036
DBE Goal: N/A
Project: BR 2022(829)
Guaranty: N/A
Time: 506 WORKING DAYS
Engineer's Estimate: $16,680,276.70
Date: 08/03/2022 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
STEWART CHAPMAN
MAXIE ALLEN
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$16,680,276.70 | |||
| $14,662,526.00 |
-12.1%
-$2,017,750.70
|
|||
| $18,693,987.00 |
12.07%
$2,013,710.30
|
27.49%
$4,031,461.00
|
||
| $22,341,408.10 |
33.94%
$5,661,131.40
|
52.37%
$7,678,882.10
|
-19.51%
-$3,647,421.10
|
E
Engineer's Estimate
$16,680,276.70
1
Awarded
$14,662,526.00
Over/Under Est:
-12.1%
-$2,017,750.70
$18,693,987.00
Over/Under Est:
12.07%
$2,013,710.30
Amt Left:
27.49%
$4,031,461.00
$22,341,408.10
Over/Under Est:
33.94%
$5,661,131.40
Amt Left:
52.37%
$7,678,882.10
Delta:
-19.51%
-$3,647,421.10
| Subcontractor | Percentage | Amount |
|---|---|---|
| M & D FOUNDATION DRILLING INDUSTRIES, INC. | 3.91% | $577,776.75 |
| J. H. STRAIN & SONS, INC. | 1.75% | $258,595.73 |
| JB PINNACLE GROUP, LLC | 0.64% | $94,572.15 |
| TORO BRAVO CONSTRUCTION, LLC | 0.31% | $45,808.39 |
| CONTRACTORS SERVICE, LTD. | 0.30% | $44,330.70 |
| BARRICADES UNLIMITED | 0.28% | $41,375.32 |
| TRP CONSTRUCTION GROUP, LLC | 0.28% | $41,375.32 |
| SCOTT DERR PAINTING CO, LLC | 0.25% | $36,942.25 |
| LANCO TURF & SEEDING, INC. | 0.15% | $22,165.35 |
| MARCOM'S MOWING SERVICE, LLC | 0.15% | $22,165.35 |
| PRIMATE CONSTRUCTION, LP | 0.13% | $19,209.97 |
| TORO BRAVO CONSTRUCTION, LLC | 0.09% | $13,299.21 |
| PROFESSIONAL TRAFFIC CONTROL LLC | 0.05% | $7,388.45 |
| PINNACLE GRINDING AND GROOVING LLC | 0.05% | $7,388.45 |
| Total: | 8.34% | $1,232,393.39 |
Bid Items & Bid Tabulations
82
Total
0 of 82