Job Info for 0069-03-060

County: STERLING Highway: US 87 Date: 07/02/2021 (3 years ago) Engineer's Estimate: $3,746,698 Control Number: 0069-03-060
Project: F 2021(714) District: SAN ANGELO Time: 178 WORKING DAYS Type: HAZARD ELIMINATION & SAFETY

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,746,698.00
SCR CIVIL CONSTRUCTION, LLC   $3,494,698.90 1
-6.73% | -$251,999.10
VECTOR UTILITIES LLC   $3,499,950.74 2
-6.59% | -$246,747.26
0.15% | $5,251.84
ROADWAY SPECIALTIES, INC.   $3,619,761.27 3
-3.39% | -$126,936.73
3.58% | $125,062.37
3.42% | $119,810.53
MASSANA CONSTRUCTION INC.   $4,101,090.00 4
9.46% | $354,392.00
17.35% | $606,391.10
13.30% | $481,328.73
GRATIOT CONSTRUCTION, LTD.   $4,180,796.30 5
11.59% | $434,098.30
19.63% | $686,097.40
1.94% | $79,706.30
ALTUS CONSTRUCTION LLC   $4,342,506.88 6
15.9% | $595,808.88
24.26% | $847,807.98
3.87% | $161,710.58
CLORE EQUIPMENT LLC   $4,695,966.45 7
25.34% | $949,268.45
34.37% | $1,201,267.55
8.14% | $353,459.57

Bid Items

Items: 18, 0 filtered
STERLING US 87  |  SAN ANGELO  |  0069-03-060  |  07/02/2021  |  $3,746,698  |  F 2021(714)  |  HAZARD ELIM & SAFETY  |  178 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate SCR CIVIL CONSTRUCTION, LLC VECTOR UTILITIES LLC ROADWAY SPECIALTIES, INC. MASSANA CONSTRUCTION INC. GRATIOT CONSTRUCTION, LTD. ALTUS CONSTRUCTION LLC CLORE EQUIPMENT LLC
150 6002 BLADING HR 274.900 $130.000 $300.000 $102.020 $210.000 $96.000 $113.640 $186.880 $124.670
164 6034 DRILL SEEDING (PERM) (RURAL) (SANDY) AC 29.100 $500.000 $625.000 $701.160 $583.360 $600.000 $631.340 $692.170 $556.000
164 6042 DRILL SEEDING (TEMP) (WARM) AC 29.100 $600.000 $300.000 $506.050 $421.400 $405.000 $456.060 $500.000 $402.000
164 6044 DRILL SEEDING (TEMP) (COOL) AC 29.100 $800.000 $300.000 $538.770 $449.320 $430.000 $486.270 $533.130 $428.000
330 6002 LRA PAV TY-I GR-A TON 192.000 $200.000 $264.000 $190.640 $481.250 $180.000 $284.090 $311.460 $196.670
432 6006 RIPRAP (CONC)(CL B) CY 4,275.000 $450.000 $365.000 $381.130 $394.690 $400.000 $428.410 $470.130 $402.370
500 6001 MOBILIZATION LS 1.000 $267,538.000 $113,100.000 $216,996.940 $131,353.550 $132,406.600 $379,545.450 $429,820.310 $457,856.720
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 9.000 $15,000.000 $3,450.000 $4,279.980 $131.500 $12,500.000 $3,539.770 $12,458.560 $3,230.500
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 444.000 $25.000 $54.900 $62.940 $34.470 $50.000 $55.810 $23.140 $21.200
506 6024 CONSTRUCTION EXITS (REMOVE) SY 444.000 $15.000 $9.950 $11.330 $15.850 $9.000 $10.100 $7.890 $6.920
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 2,081.000 $6.000 $10.600 $12.590 $10.440 $9.500 $10.780 $4.290 $8.980
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 2,081.000 $1.000 $1.000 $1.260 $0.950 $1.000 $0.970 $1.250 $1.190
543 6002 CABLE BARRIER SYSTEM (TL-4) LF 101,322.000 $8.000 $11.700 $10.260 $11.430 $14.000 $12.780 $12.170 $15.310
543 6006 CABLE BARRIER SYSTEM (TL-4) (10'-0") LF 6,414.000 $15.000 $12.000 $13.000 $15.680 $15.000 $15.060 $15.460 $20.940
543 6020 CABLE BARRIER TERMINAL SECTION (TL-4) EA 131.000 $2,500.000 $1,950.000 $2,034.450 $1,918.480 $3,500.000 $2,468.750 $1,853.220 $4,360.900
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 3.000 $600.000 $1,600.000 $772.860 $1,726.380 $1,100.000 $568.180 $562.790 $1,237.510
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 122.000 $60.000 $45.000 $188.820 $181.890 $55.000 $125.000 $62.290 $300.000
6185 6002 TMA (STATIONARY) DAY 122.000 $125.000 $330.000 $188.820 $197.250 $100.000 $170.450 $161.960 $375.000
Totals: $3,746,698.00 $3,494,698.90 $3,499,950.77 $3,619,761.28 $4,101,090.00 $4,180,796.32 $4,342,506.89 $4,695,966.45