Job Info for 0923-22-025

County: STEPHENS Highway: CS Date: 01/05/2023 (1 year ago) Engineer's Estimate: $1,089,180 Control Number: 0923-22-025
Project: BR 2021(578) District: BROWNWOOD Time: 115 WORKING DAYS Type: BRIDGE REPLACEMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans: Vol 1 | Vol 2 | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,089,180.00
PROJECT ALLIED RESOURCES, LLC   $1,073,352.20 1
-1.45% | -$15,827.80
HODGES AND SON CONSTRUCTION COMPANY, INC.   $1,210,619.80 2
11.15% | $121,439.80
12.79% | $137,267.60
Subcontractor Percentage Amount
RAYDON, INC. 5.00% $53,667.61
Total: 5.00% $53,667.61

Bid Items

Items: 39, 0 filtered
STEPHENS CS  |  BROWNWOOD  |  0923-22-025  |  01/05/2023  |  $1,089,180  |  BR 2021(578)  |  BRIDGE REPL  |  115 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate PROJECT ALLIED RESOURCES, LLC HODGES AND SON CONSTRUCTION COMPANY, INC.
100 6002 PREPARING ROW STA 3.400 $2,000.000 $2,820.000 $10,000.000
104 6001 REMOVING CONC (PAV) SY 46.000 $25.000 $12.500 $50.000
104 6029 REMOVING CONC (CURB OR CURB & GUTTER) LF 91.000 $20.000 $17.300 $35.000
104 6044 REMOVING CONC (FLUME) SY 50.000 $30.000 $37.300 $40.000
110 6001 EXCAVATION (ROADWAY) CY 180.000 $30.000 $34.100 $35.000
132 6005 EMBANKMENT (FINAL)(ORD COMP)(TY C) CY 284.000 $30.000 $19.400 $35.000
164 6025 CELL FBR MLCH SEED(PERM)(URBAN)(SANDY) SY 210.000 $5.000 $11.400 $12.000
164 6029 CELL FBR MLCH SEED(TEMP)(WARM) SY 105.000 $4.000 $5.700 $20.000
164 6031 CELL FBR MLCH SEED(TEMP)(COOL) SY 105.000 $4.000 $5.700 $20.000
168 6001 VEGETATIVE WATERING MG 4.800 $50.000 $149.000 $1.000
169 6002 SOIL RETENTION BLANKETS (CL 1) (TY B) SY 210.000 $15.000 $5.500 $6.000
247 6055 FL BS (CMP IN PLC)(TY D GR 3)(FNAL POS) CY 207.000 $150.000 $138.000 $150.000
310 6012 PRIME COAT (RC-250) GAL 186.000 $40.000 $23.600 $30.000
316 6017 ASPH (AC-20-5TR) GAL 312.000 $40.000 $17.600 $25.000
316 6177 AGGR(TY-B GR-5 SAC-B) CY 7.000 $1,500.000 $645.000 $1,400.000
316 6222 AGGR(TY-PB GR-3 SAC-B) CY 9.000 $1,500.000 $474.000 $1,400.000
360 6001 CONC PVMT (CONT REINF - CRCP) (7") SY 482.000 $200.000 $237.000 $280.000
360 6027 CURB (TYPE II) LF 228.000 $35.000 $33.000 $35.000
400 6005 CEM STABIL BKFL CY 360.000 $400.000 $243.000 $250.000
402 6001 TRENCH EXCAVATION PROTECTION LF 70.000 $15.000 $90.000 $5.000
420 6051 CL C CONC (CULV) CY 167.800 $1,750.000 $1,910.000 $1,800.000
420 6057 CL C CONC (WINGWALLS) CY 76.700 $1,750.000 $1,720.000 $1,800.000
432 6023 RIPRAP (STONE COMMON)(DRY)(8 IN) CY 131.000 $300.000 $203.000 $200.000
442 6007 STR STEEL (MISC NON - BRIDGE) LB 144.000 $25.000 $34.600 $35.000
450 6032 RAIL (TY C223) LF 275.000 $215.000 $200.000 $225.000
464 6007 RC PIPE (CL III)(30 IN) LF 20.000 $220.000 $212.000 $150.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 2.000 $15,000.000 $19,100.000 $40,000.000
500 6001 MOBILIZATION LS 1.000 $93,000.000 $119,000.000 $100,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 $2,500.000 $3,460.000 $11,500.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 65.000 $20.000 $16.100 $1.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 580.000 $6.000 $5.400 $1.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 580.000 $2.000 $1.570 $1.000
506 6053 ROCK FILTER DAMS (INSTALL) (TY 2) (6:1) LF 65.000 $70.000 $92.000 $1.000
529 6008 CONC CURB & GUTTER (TY II) LF 168.000 $40.000 $47.200 $50.000
531 6002 CONC SIDEWALKS (5") SY 205.000 $100.000 $100.000 $85.000
531 6005 CURB RAMPS (TY 2) EA 2.000 $5,000.000 $3,550.000 $5,000.000
531 6010 CURB RAMPS (TY 7) EA 2.000 $5,000.000 $3,190.000 $5,000.000
644 6076 REMOVE SM RD SN SUP&AM EA 6.000 $200.000 $287.000 $100.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 12.000 $50.000 $43.100 $30.000
Totals: $1,089,180.00 $1,073,352.20 $1,210,619.80