Bid Cobra

STARR US 83 (0038-06-045)

Items: 170

County: STARR
Length: N/A
Highway: US 83
District: PHARR
Control Number: 0038-06-045
DBE Goal: N/A
Project: F 2022(185)
Guaranty: N/A
Time: 604 WORKING DAYS
Engineer's Estimate: $29,012,476.17
Date: 12/02/2021 (4 years ago)
Contract Number: N/A
Type: WIDEN ROAD - ADD LANES AND SHOULDERS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (5)
E
Engineer's Estimate
$29,012,476.17
$24,806,298.90
Over/Under Est: -14.5% -$4,206,177.27
Over/Under Est: -7.03% -$2,039,949.05
Amt Left: 8.73% $2,166,228.22
$30,072,354.69
Over/Under Est: 3.65% $1,059,878.52
Amt Left: 21.23% $5,266,055.79
Delta: -11.49% -$3,099,827.57
$30,103,724.59
Over/Under Est: 3.76% $1,091,248.42
Amt Left: 21.36% $5,297,425.69
Delta: -0.10% -$31,369.90
$30,750,000.00
Over/Under Est: 5.99% $1,737,523.83
Amt Left: 23.96% $5,943,701.10
Delta: -2.15% -$646,275.41
Subcontractor Percentage Amount
FLOVERA CONSTRUCTION SERVICES, LLC 4.82% $1,333,529.77
TEXAS ICON CONSTRUCTION, LLC 1.61% $445,432.14
HIGHWAY BARRICADES AND SERVICES, LLC 1.32% $365,199.02
WEBER-BALKE FOUNDATION COMPANY, INC 1.31% $362,432.36
LAREDO STRIPING, INC. 1.19% $329,232.45
EROSION PREVENTION PRODUCTS 0.31% $85,766.44
*AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. 0.28% $77,466.46
GULF COAST CONTRACTORS, INC. 0.27% $74,699.80
AMERICAN FENCE 0.27% $74,699.80
TEXAS HIGHWAY SYSTEMS, INC. 0.21% $58,099.84
ELITECURB & CONCRETE, LLC 0.21% $58,099.84
WILLIAMS ROAD, LLC 0.10% $27,666.59
RIO GRANDE REBAR RODBUSTERS, LLC 0.10% $27,666.59
IZAGUIRRE CONSTRUCTION LLC 0.05% $13,833.30
PENHALL COMPANY 0.04% $11,066.64
SCOTT DERR PAINTING CO, LLC 0.02% $5,533.32
TORO BRAVO CONSTRUCTION, LLC 0.00% $0.00
J N K ADVANCE TREE SERVICE 0.00% $0.00
Total: 12.11% $3,350,424.36

Bid Items & Bid Tabulations

170 Total 0 of 170
STARR  |  US 83  |  PHARR  |  0038-06-045  |  12/02/2021  |  $29,012,476.17  |  F 2022(185)  |  WIDEN ROAD - ADD LANES AND SHOULDERS  |  604 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
IOC COMPANY, LLC
ANDERSON COLUMBIA CO., INC.
REIM CONSTRUCTION, INC.
FOREMOST PAVING, INC.
POSILLICO CIVIL, INC.
PREPARING ROW
STA 419.000 $3,200.000 $5,000.000 $500.000 $989.000 $6,500.000 $1,950.000
PREP ROW (TREE)(LESS THAN 24" DIA)
EA 45.000 $400.000 $125.000 $700.000 $767.000 $750.000 $800.000
REMOVING CONC (DRIVEWAYS)
SY 33.000 $25.000 $30.000 $26.000 $15.750 $20.000 $20.000
REMOVING CONCRETE(MOW STRIP)
LF 2,157.000 $4.000 $3.000 $12.000 $6.900 $13.000 $10.000
EXCAVATION (ROADWAY)
CY 170,236.000 $9.000 $4.000 $6.000 $6.550 $9.250 $5.000
EXCAVATION (CHANNEL)
CY 600.000 $17.000 $6.000 $16.000 $11.500 $26.000 $6.000
EXCAVATION (SPECIAL)
CY 25,259.000 $10.000 $0.500 $12.000 $11.250 $10.750 $3.250
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 79,899.000 $8.500 $3.000 $8.500 $5.000 $4.000 $3.500
EMBANKMENT (FINAL) (DENS CONT) (TY C1)
CY 25,259.000 $9.000 $0.500 $12.000 $19.250 $9.000 $3.250
FURNISHING AND PLACING TOPSOIL (4")
SY 273,461.000 $1.000 $0.700 $0.500 $1.450 $2.250 $1.600
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 273,461.000 $0.400 $0.150 $0.200 $0.310 $0.280 $0.300
DRILL SEEDING (TEMP) (WARM)
SY 136,734.000 $0.300 $0.150 $0.180 $0.220 $0.180 $0.250
VEGETATIVE WATERING
MG 4,384.000 $20.000 $30.000 $30.000 $26.500 $40.000 $22.000
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 274,089.000 $1.750 $1.000 $1.100 $1.300 $1.150 $3.000
PLANT MATERIAL (1-GAL)
EA 229.000 $6.500 $72.000 $68.000 $79.500 $68.000 $85.000
PLANT MATERIAL (5-GAL)
EA 106.000 $20.000 $155.000 $150.000 $176.000 $150.000 $180.000
PLANT MAINTENANCE
MO 9.000 $4,000.000 $2,150.000 $2,500.000 $2,710.000 $2,200.000 $2,500.000
SPRINKLING (DUST CONTROL)
MG 2,308.000 $12.000 $1.000 $9.000 $26.500 $1.000 $7.000
PROOF ROLLING
HR 448.000 $75.000 $50.000 $90.000 $58.500 $105.000 $90.000
FL BS (RDWY DEL)(TY E GR 4)(FNAL POS)
CY 105,539.000 $27.000 $25.000 $31.000 $41.750 $32.000 $39.500
CEMENT
TON 3,572.000 $165.000 $182.500 $165.000 $176.000 $149.000 $170.000
CEMENT TREAT (NEW BASE 14")
SY 271,389.000 $2.500 $1.750 $6.000 $4.200 $2.200 $3.750
SALV, HAUL & STKPL RCL APH PV (4 TO 6")
SY 141,469.000 $2.100 $1.500 $2.700 $3.550 $2.400 $6.600
PRIME COAT (MC-30)
GAL 53,203.000 $4.000 $4.000 $4.800 $4.600 $4.250 $1.000
ASPH (AC-10)
GAL 79,817.000 $5.000 $4.000 $4.800 $3.700 $5.000 $3.700
AGGR (TY-D GR-4P)(SAC-B)
CY 2,219.000 $100.000 $75.000 $100.000 $104.000 $45.000 $100.000
CEM STABIL BKFL
CY 546.000 $55.000 $65.000 $160.000 $110.000 $85.000 $120.000
STRUCT EXCAV (SPECIAL)
CY 200.000 $40.000 $50.000 $55.000 $81.500 $53.000 $55.000
SAND BACKFILL
CY 854.000 $15.000 $45.000 $30.000 $65.500 $55.000 $55.000
TRENCH EXCAVATION PROTECTION
LF 723.000 $5.000 $1.000 $8.000 $10.250 $30.000 $20.000
TEMPORARY SPL SHORING
SF 2,683.000 $15.000 $20.000 $20.000 $49.250 $10.000 $30.000
DRILL SHAFT (18 IN)
LF 340.000 $85.000 $70.000 $120.000 $72.500 $100.000 $100.000
DRILL SHAFT (36 IN)
LF 1,330.000 $185.000 $245.000 $280.000 $252.000 $320.000 $360.000
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 60.000 $300.000 $275.000 $290.000 $322.000 $275.000 $400.000
CL C CONC (ABUT)
CY 129.800 $925.000 $800.000 $1,100.000 $855.000 $1,500.000 $1,500.000
REINF CONC SLAB
SF 8,200.000 $22.000 $20.000 $25.000 $36.650 $22.000 $24.000
APPROACH SLAB
CY 185.400 $750.000 $475.000 $600.000 $712.000 $800.000 $750.000
RETAINING WALL (MSE)
SF 13,134.000 $50.000 $70.000 $84.000 $46.500 $96.000 $60.000
PRESTR CONC GIRDER (TX46)
LF 1,019.250 $148.000 $210.000 $200.000 $241.000 $196.000 $280.000
RIPRAP (CONC)(5 IN)
CY 1,454.000 $450.000 $325.000 $370.000 $453.000 $365.000 $400.000
RIPRAP (STONE COMMON)(DRY)(8 IN)
CY 119.000 $115.000 $135.000 $147.000 $222.000 $150.000 $200.000
RIPRAP (MOW STRIP)(4 IN)
CY 365.000 $400.000 $350.000 $360.000 $502.000 $365.000 $390.000
RIPRAP (MOW STRIP)(6 IN)
CY 48.300 $555.000 $375.000 $370.000 $452.000 $800.000 $390.000
RAIL (TY SSTR)
LF 1,551.010 $55.000 $145.000 $125.000 $131.000 $70.000 $45.000
RAIL (TY SSTR) (W/DRAIN SLOTS)
LF 245.000 $55.000 $145.000 $170.000 $149.000 $85.000 $20.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 178.000 $200.000 $150.000 $170.000 $162.000 $165.000 $155.000
CONC BOX CULV (3 FT X 2 FT)
LF 205.000 $250.000 $150.000 $200.000 $153.000 $199.000 $250.000
CONC BOX CULV (4 FT X 4 FT)
LF 67.000 $300.000 $245.000 $280.000 $254.000 $291.000 $410.000
CONC BOX CULV (6 FT X 3 FT)
LF 254.000 $370.000 $300.000 $410.000 $371.000 $390.000 $570.000
CONC BOX CULV (8 FT X 5 FT)
LF 25.000 $450.000 $700.000 $645.000 $593.000 $615.000 $950.000
RC PIPE (CL IV)(18 IN)
LF 509.000 $60.000 $53.000 $45.000 $55.750 $43.000 $90.000
RC PIPE (CL IV)(24 IN)
LF 1,915.000 $80.000 $60.000 $51.000 $64.500 $49.000 $100.000
RC PIPE (CL IV)(30 IN)
LF 414.000 $110.000 $75.000 $75.000 $85.500 $74.000 $130.000
RC PIPE (CL IV)(36 IN)
LF 1,168.000 $120.000 $96.000 $99.000 $119.000 $94.000 $175.000
RC PIPE (CL IV)(42 IN)
LF 330.000 $140.000 $115.000 $125.000 $138.500 $120.000 $220.000
INLET (COMPL)(TY MSE1)
EA 5.000 $2,000.000 $3,000.000 $3,800.000 $2,680.000 $3,650.000 $5,000.000
INLET (COMPL)(TY MSE2)
EA 1.000 $2,500.000 $3,400.000 $4,040.000 $3,330.000 $3,850.000 $5,500.000
HEADWALL (CH - FW - 0) (DIA= 42 IN)
EA 1.000 $5,000.000 $9,000.000 $8,250.000 $8,500.000 $7,900.000 $8,000.000
HEADWALL (CH - PW - 0) (DIA= 30 IN)
EA 4.000 $7,000.000 $7,500.000 $8,670.000 $6,850.000 $8,265.000 $8,000.000
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 10.000 $8,000.000 $8,500.000 $8,950.000 $7,460.000 $8,520.000 $8,500.000
HEADWALL (CH - PW - 0) (DIA= 42 IN)
EA 4.000 $9,000.000 $10,000.000 $9,800.000 $10,900.000 $9,350.000 $9,000.000
HEADWALL (CH - PW - S) (DIA= 36 IN)
EA 1.000 $8,000.000 $12,500.000 $9,600.000 $9,690.000 $9,150.000 $9,500.000
WINGWALL (PW - 1) (HW=10 FT)
EA 2.000 $16,000.000 $50,000.000 $19,820.000 $40,500.000 $18,875.000 $15,000.000
WINGWALL (PW - 1) (HW=11 FT)
EA 1.000 $16,750.000 $61,000.000 $24,830.000 $53,600.000 $23,650.000 $15,000.000
WINGWALL (PW - 1) (HW=5 FT)
EA 2.000 $11,500.000 $21,500.000 $16,425.000 $14,600.000 $15,600.000 $10,000.000
WINGWALL (PW - 1) (HW=6 FT)
EA 3.000 $13,860.000 $24,000.000 $18,740.000 $18,000.000 $17,850.000 $11,000.000
WINGWALL (PW - 1) (HW=7 FT)
EA 2.000 $13,889.000 $27,000.000 $19,580.000 $21,800.000 $19,000.000 $12,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 22.000 $1,000.000 $900.000 $1,310.000 $1,120.000 $1,250.000 $1,500.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 95.000 $1,200.000 $1,250.000 $1,730.000 $1,670.000 $1,650.000 $1,600.000
SET (TY II) (36 IN) (RCP) (6: 1) (C)
EA 2.000 $3,400.000 $3,500.000 $4,720.000 $5,440.000 $4,500.000 $1,600.000
CLEAN EXIST CULVERTS
EA 12.000 $1,200.000 $1,500.000 $2,626.000 $3,520.000 $2,500.000 $2,500.000
REMOV STR (SET)
EA 60.000 $300.000 $200.000 $370.000 $273.000 $350.000 $200.000
REMOV STR (WINGWALL)
EA 6.000 $1,000.000 $3,000.000 $1,040.000 $2,300.000 $9,900.000 $350.000
REMOV STR (HEADWALL)
EA 3.000 $1,200.000 $6,500.000 $890.000 $1,630.000 $850.000 $350.000
REMOV STR (PIPE)
LF 1,440.000 $6.000 $5.000 $6.000 $16.000 $5.000 $11.000
REMOV STR (BOX CULVERT)
LF 170.000 $26.000 $15.000 $94.000 $47.000 $85.000 $23.000
REMOV STR (CATTLE GUARD)
EA 5.000 $250.000 $2,500.000 $3,140.000 $639.000 $1,250.000 $145.000
MOBILIZATION
LS 1.000 $2,900,000.000 $2,000,000.000 $1,730,000.000 $1,800,000.000 $2,700,000.000 $1,249,023.100
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 38.000 $8,500.000 $730.690 $1,060.000 $3,010.000 $4,500.000 $7,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 4,229.000 $30.000 $28.000 $29.000 $35.750 $28.000 $25.000
ROCK FILTER DAMS (INSTALL) (TY 4)
LF 868.000 $40.000 $52.500 $55.000 $69.500 $52.000 $25.000
ROCK FILTER DAMS (REMOVE)
LF 5,097.000 $12.000 $27.250 $15.000 $17.000 $15.000 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 1,887.000 $40.000 $27.250 $28.000 $20.750 $28.000 $10.000
CONSTRUCTION EXITS (REMOVE)
SY 1,887.000 $15.000 $10.000 $15.000 $8.100 $15.000 $5.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 40.000 $90.000 $50.000 $90.000 $53.500 $125.000 $75.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 30,505.000 $3.000 $3.250 $3.000 $3.500 $2.800 $2.650
TEMP SEDMT CONT FENCE (REMOVE)
LF 30,505.000 $1.500 $1.250 $1.200 $1.550 $1.200 $1.300
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 2,280.000 $6.000 $5.950 $6.000 $7.450 $5.900 $5.600
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,280.000 $1.000 $1.250 $1.200 $1.450 $1.200 $1.300
CONSTRUCTING DETOURS
SY 5,690.000 $50.000 $60.000 $70.000 $92.500 $75.000 $70.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 13,560.000 $32.000 $65.000 $30.000 $66.000 $25.000 $55.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 21,150.000 $5.000 $5.000 $9.000 $3.950 $9.000 $12.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 13,560.000 $7.000 $10.000 $17.000 $12.750 $9.500 $8.000
DRIVEWAYS (ACP)
SY 4,831.000 $36.000 $42.720 $40.000 $32.500 $40.000 $52.000
RUMBLE STRIPS (SHOULDER)
LF 98,411.000 $0.270 $0.180 $0.150 $0.210 $0.400 $0.300
MTL W-BEAM GD FEN (TIM POST)
LF 5,225.000 $25.000 $27.490 $31.000 $34.500 $26.000 $35.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $1,820.000 $1,949.210 $2,900.000 $2,660.000 $1,900.000 $3,000.000
MTL W-BEAM GD FEN ADJUSTMENT
LF 625.000 $10.000 $5.490 $32.000 $11.750 $6.500 $20.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 10.000 $2,200.000 $1,449.210 $1,440.000 $1,610.000 $1,325.000 $2,500.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 500.000 $30.000 $30.490 $30.000 $34.250 $33.000 $45.000
MTL BM GD FEN TRANS (NON - SYM)
EA 1.000 $900.000 $749.210 $860.000 $958.000 $900.000 $500.000
REMOVE METAL BEAM GUARD FENCE
LF 1,443.000 $3.000 $1.490 $4.200 $4.000 $0.950 $6.000
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $200.000 $195.210 $290.000 $289.000 $200.000 $750.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 2.000 $200.000 $195.210 $290.000 $289.000 $200.000 $750.000
GUARDRAIL END TREATMENT (INSTALL)
EA 39.000 $2,112.000 $3,349.210 $3,470.000 $3,880.000 $3,275.000 $5,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 13.000 $150.000 $195.210 $290.000 $289.000 $280.000 $1,000.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 17.000 $3,850.000 $915.210 $1,150.000 $1,170.000 $1,200.000 $3,000.000
CRASH CUSH ATTEN (REMOVE)
EA 20.000 $1,600.000 $915.210 $1,050.000 $844.000 $700.000 $1,500.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 20.000 $10,000.000 $9,662.850 $8,740.000 $11,000.000 $8,830.000 $15,000.000
CHAIN LINK FENCE (INSTALL) (6')
LF 2,559.000 $35.000 $30.000 $33.000 $36.250 $65.000 $20.000
PIPE UNDERDRAINS (TY 6) (6")
LF 1,475.000 $20.000 $40.810 $26.000 $31.500 $38.000 $15.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 15.000 $300.000 $215.000 $225.000 $252.000 $275.000 $280.000
CONDT (PVC) (SCH 80) (2")
LF 286.000 $9.000 $8.000 $9.000 $9.400 $8.000 $22.000
ELEC CONDR (NO.6) BARE
LF 44.000 $1.500 $1.800 $2.000 $2.100 $2.000 $3.000
ELEC CONDR (NO.6) INSULATED
LF 22.000 $1.700 $2.000 $2.100 $2.300 $2.000 $3.000
TRAY CABLE (4 CONDR) (12 AWG)
LF 421.000 $2.000 $2.200 $2.300 $2.600 $2.250 $3.000
ZINC-COAT STL WIRE STRAND (3/8")
LF 280.000 $2.500 $2.500 $3.000 $2.950 $2.500 $6.000
REMOVE ELECTRICAL SERVICES
EA 1.000 $1,500.000 $650.000 $680.000 $762.000 $650.000 $1,000.000
ELC SRV TY T 120/240 000(NS)GS(L)TS(O)
EA 1.000 $5,000.000 $2,100.000 $2,200.000 $2,460.000 $2,100.000 $8,000.000
ELC SRV TY T 120/240 000(NS)GS(L)TS(U)
EA 1.000 $5,500.000 $1,530.000 $1,600.000 $1,790.000 $1,550.000 $8,000.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 47.000 $540.000 $785.000 $820.000 $921.000 $736.000 $1,500.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 25.000 $640.000 $850.000 $900.000 $997.000 $780.000 $1,200.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $680.000 $1,150.000 $1,200.000 $1,350.000 $1,000.000 $1,600.000
IN SM RD SN SUP&AM TYS80(2)SA(T-2EXT)
EA 1.000 $1,500.000 $2,450.000 $2,580.000 $2,870.000 $2,200.000 $3,300.000
RELOCATE SM RD SN SUP&AM TY S80
EA 3.000 $565.000 $575.000 $600.000 $651.000 $800.000 $800.000
REMOVE SM RD SN SUP&AM
EA 19.000 $80.000 $75.000 $79.000 $88.000 $100.000 $150.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 61.000 $26.000 $15.000 $16.000 $17.500 $25.000 $20.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 11.000 $20.000 $15.000 $16.000 $17.500 $25.000 $20.000
INSTL DEL ASSM (D-DY)SZ 2(WC)GND
EA 6.000 $90.000 $45.000 $48.000 $53.000 $60.000 $60.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 273.000 $35.000 $18.000 $19.000 $21.000 $40.000 $26.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 50.000 $18.000 $21.000 $22.000 $24.750 $40.000 $30.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 134.000 $90.000 $60.000 $63.000 $70.500 $50.000 $81.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 2,148.000 $3.330 $4.500 $5.000 $5.300 $4.500 $6.000
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 810.000 $0.600 $0.440 $0.500 $0.500 $0.450 $0.450
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 149,130.000 $0.600 $0.400 $0.400 $0.480 $0.400 $0.400
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 151,424.000 $0.600 $0.400 $0.400 $0.480 $0.400 $0.400
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 6,428.000 $1.690 $0.440 $0.500 $0.500 $0.450 $0.450
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 72.000 $6.090 $14.000 $15.000 $16.500 $14.000 $15.000
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
LF 2,009.000 $5.300 $3.000 $3.000 $3.500 $3.000 $3.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 19,010.000 $0.600 $0.420 $0.450 $0.500 $0.450 $0.450
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 78,318.000 $0.340 $0.400 $0.400 $0.480 $0.400 $0.400
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 10,126.000 $0.340 $0.420 $0.450 $0.500 $0.450 $0.450
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 79,035.000 $0.440 $0.400 $0.400 $0.480 $0.400 $0.400
PREFAB PAV MRK TY B (W)(4")(BRK)CNTST
LF 50.000 $48.000 $12.000 $12.000 $14.000 $12.000 $12.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 24.000 $260.000 $175.000 $180.000 $205.000 $175.000 $300.000
PREFAB PAV MRK TY C (W) (WORD)
EA 16.000 $280.000 $250.000 $260.000 $293.000 $250.000 $350.000
REFL PAV MRKR TY I-A
EA 100.000 $3.060 $4.500 $5.000 $5.300 $4.500 $7.000
REFL PAV MRKR TY I-C
EA 547.000 $3.200 $4.500 $5.000 $5.300 $4.500 $7.000
REFL PAV MRKR TY II-A-A
EA 1,160.000 $3.430 $4.250 $5.000 $5.000 $4.250 $6.000
REFL PAV MRKR TY II-C-R
EA 736.000 $4.800 $4.500 $5.000 $5.300 $4.500 $6.000
ELIM EXT PAV MRK & MRKS (4")
LF 79,241.000 $0.600 $0.320 $0.400 $0.370 $0.350 $0.350
INSTALL HWY TRF SIG (FLASH BEACON)
EA 2.000 $20,000.000 $1,850.000 $1,900.000 $2,170.000 $1,900.000 $8,000.000
REMOVING TRAFFIC SIGNALS
EA 1.000 $7,500.000 $1,250.000 $1,300.000 $1,470.000 $1,300.000 $3,500.000
VEH SIG SEC (12")LED(YEL)
EA 5.000 $230.000 $225.000 $240.000 $264.000 $230.000 $600.000
VEH SIG SEC (12")LED(RED)
EA 6.000 $230.000 $225.000 $240.000 $264.000 $230.000 $600.000
BACK PLATE (12")(1 SEC)
EA 11.000 $70.000 $50.000 $52.000 $58.500 $50.000 $110.000
TRF SIG CBL (TY A)(12 AWG)(5 CONDR)
LF 1,214.000 $2.000 $2.400 $2.500 $2.800 $2.400 $3.500
INS TRF SIG PL AM (S)STR(TY D)LUM
EA 4.000 $7,000.000 $9,200.000 $9,660.000 $10,800.000 $9,200.000 $15,000.000
POTHOLE REPAIR (STANDARD)
SY 1,000.000 $150.000 $24.240 $120.000 $71.000 $68.000 $90.000
STRIP MOWING
AC 558.000 $310.000 $90.000 $94.000 $158.000 $285.000 $750.000
LITTER REMOVAL
AC 558.000 $95.000 $30.000 $150.000 $84.000 $80.000 $15.000
CLEANING / SWEEPING (SPOT)
MI 18.600 $820.000 $622.870 $580.000 $578.000 $550.000 $3,000.000
SP MIXES SP-D SAC-A PG76-22
TON 58,066.000 $125.000 $105.000 $110.000 $132.000 $110.000 $130.000
BONDING COURSE
GAL 29,198.000 $4.000 $3.000 $4.000 $5.000 $3.500 $2.000
INTRLCK ART CONC BLKS (4" MIN)
SF 13,988.000 $10.000 $6.170 $10.000 $7.500 $22.000 $20.000
GEOGRID BASE REINFORCEMENT (TY II)
SY 276,868.000 $1.300 $1.500 $1.150 $1.100 $1.350 $2.250
BIRD EXCLUSION METHOD
SF 14,740.000 $4.260 $1.500 $4.800 $2.850 $4.000 $10.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,000.000 $850.000 $32,000.000 $11,700.000 $7,500.000 $15,000.000
TMA (STATIONARY)
DAY 1,812.000 $200.000 $15.000 $30.000 $57.500 $0.010 $100.000
TMA (MOBILE OPERATION)
HR 722.000 $150.000 $25.000 $70.000 $63.500 $0.010 $600.000
Totals: $29,012,476.170 $24,806,298.902 $26,972,527.120 $30,072,354.690 $30,103,724.590 $30,750,000.000