PREPARING ROW
|
STA
|
419.000
|
$3,200.000
|
$5,000.000
|
$500.000
|
$989.000
|
$6,500.000
|
$1,950.000
|
|
|
PREP ROW (TREE)(LESS THAN 24" DIA)
|
EA
|
45.000
|
$400.000
|
$125.000
|
$700.000
|
$767.000
|
$750.000
|
$800.000
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
33.000
|
$25.000
|
$30.000
|
$26.000
|
$15.750
|
$20.000
|
$20.000
|
|
|
REMOVING CONCRETE(MOW STRIP)
|
LF
|
2,157.000
|
$4.000
|
$3.000
|
$12.000
|
$6.900
|
$13.000
|
$10.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
170,236.000
|
$9.000
|
$4.000
|
$6.000
|
$6.550
|
$9.250
|
$5.000
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
600.000
|
$17.000
|
$6.000
|
$16.000
|
$11.500
|
$26.000
|
$6.000
|
|
|
EXCAVATION (SPECIAL)
|
CY
|
25,259.000
|
$10.000
|
$0.500
|
$12.000
|
$11.250
|
$10.750
|
$3.250
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
79,899.000
|
$8.500
|
$3.000
|
$8.500
|
$5.000
|
$4.000
|
$3.500
|
|
|
EMBANKMENT (FINAL) (DENS CONT) (TY C1)
|
CY
|
25,259.000
|
$9.000
|
$0.500
|
$12.000
|
$19.250
|
$9.000
|
$3.250
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
273,461.000
|
$1.000
|
$0.700
|
$0.500
|
$1.450
|
$2.250
|
$1.600
|
|
|
DRILL SEEDING (PERM) (RURAL) (SANDY)
|
SY
|
273,461.000
|
$0.400
|
$0.150
|
$0.200
|
$0.310
|
$0.280
|
$0.300
|
|
|
DRILL SEEDING (TEMP) (WARM)
|
SY
|
136,734.000
|
$0.300
|
$0.150
|
$0.180
|
$0.220
|
$0.180
|
$0.250
|
|
|
VEGETATIVE WATERING
|
MG
|
4,384.000
|
$20.000
|
$30.000
|
$30.000
|
$26.500
|
$40.000
|
$22.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY B)
|
SY
|
274,089.000
|
$1.750
|
$1.000
|
$1.100
|
$1.300
|
$1.150
|
$3.000
|
|
|
PLANT MATERIAL (1-GAL)
|
EA
|
229.000
|
$6.500
|
$72.000
|
$68.000
|
$79.500
|
$68.000
|
$85.000
|
|
|
PLANT MATERIAL (5-GAL)
|
EA
|
106.000
|
$20.000
|
$155.000
|
$150.000
|
$176.000
|
$150.000
|
$180.000
|
|
|
PLANT MAINTENANCE
|
MO
|
9.000
|
$4,000.000
|
$2,150.000
|
$2,500.000
|
$2,710.000
|
$2,200.000
|
$2,500.000
|
|
|
SPRINKLING (DUST CONTROL)
|
MG
|
2,308.000
|
$12.000
|
$1.000
|
$9.000
|
$26.500
|
$1.000
|
$7.000
|
|
|
PROOF ROLLING
|
HR
|
448.000
|
$75.000
|
$50.000
|
$90.000
|
$58.500
|
$105.000
|
$90.000
|
|
|
FL BS (RDWY DEL)(TY E GR 4)(FNAL POS)
|
CY
|
105,539.000
|
$27.000
|
$25.000
|
$31.000
|
$41.750
|
$32.000
|
$39.500
|
|
|
CEMENT
|
TON
|
3,572.000
|
$165.000
|
$182.500
|
$165.000
|
$176.000
|
$149.000
|
$170.000
|
|
|
CEMENT TREAT (NEW BASE 14")
|
SY
|
271,389.000
|
$2.500
|
$1.750
|
$6.000
|
$4.200
|
$2.200
|
$3.750
|
|
|
SALV, HAUL & STKPL RCL APH PV (4 TO 6")
|
SY
|
141,469.000
|
$2.100
|
$1.500
|
$2.700
|
$3.550
|
$2.400
|
$6.600
|
|
|
PRIME COAT (MC-30)
|
GAL
|
53,203.000
|
$4.000
|
$4.000
|
$4.800
|
$4.600
|
$4.250
|
$1.000
|
|
|
ASPH (AC-10)
|
GAL
|
79,817.000
|
$5.000
|
$4.000
|
$4.800
|
$3.700
|
$5.000
|
$3.700
|
|
|
AGGR (TY-D GR-4P)(SAC-B)
|
CY
|
2,219.000
|
$100.000
|
$75.000
|
$100.000
|
$104.000
|
$45.000
|
$100.000
|
|
|
CEM STABIL BKFL
|
CY
|
546.000
|
$55.000
|
$65.000
|
$160.000
|
$110.000
|
$85.000
|
$120.000
|
|
|
STRUCT EXCAV (SPECIAL)
|
CY
|
200.000
|
$40.000
|
$50.000
|
$55.000
|
$81.500
|
$53.000
|
$55.000
|
|
|
SAND BACKFILL
|
CY
|
854.000
|
$15.000
|
$45.000
|
$30.000
|
$65.500
|
$55.000
|
$55.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
723.000
|
$5.000
|
$1.000
|
$8.000
|
$10.250
|
$30.000
|
$20.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
2,683.000
|
$15.000
|
$20.000
|
$20.000
|
$49.250
|
$10.000
|
$30.000
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
340.000
|
$85.000
|
$70.000
|
$120.000
|
$72.500
|
$100.000
|
$100.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
1,330.000
|
$185.000
|
$245.000
|
$280.000
|
$252.000
|
$320.000
|
$360.000
|
|
|
DRILL SHAFT (TRF SIG POLE) (36 IN)
|
LF
|
60.000
|
$300.000
|
$275.000
|
$290.000
|
$322.000
|
$275.000
|
$400.000
|
|
|
CL C CONC (ABUT)
|
CY
|
129.800
|
$925.000
|
$800.000
|
$1,100.000
|
$855.000
|
$1,500.000
|
$1,500.000
|
|
|
REINF CONC SLAB
|
SF
|
8,200.000
|
$22.000
|
$20.000
|
$25.000
|
$36.650
|
$22.000
|
$24.000
|
|
|
APPROACH SLAB
|
CY
|
185.400
|
$750.000
|
$475.000
|
$600.000
|
$712.000
|
$800.000
|
$750.000
|
|
|
RETAINING WALL (MSE)
|
SF
|
13,134.000
|
$50.000
|
$70.000
|
$84.000
|
$46.500
|
$96.000
|
$60.000
|
|
|
PRESTR CONC GIRDER (TX46)
|
LF
|
1,019.250
|
$148.000
|
$210.000
|
$200.000
|
$241.000
|
$196.000
|
$280.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
1,454.000
|
$450.000
|
$325.000
|
$370.000
|
$453.000
|
$365.000
|
$400.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(8 IN)
|
CY
|
119.000
|
$115.000
|
$135.000
|
$147.000
|
$222.000
|
$150.000
|
$200.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
365.000
|
$400.000
|
$350.000
|
$360.000
|
$502.000
|
$365.000
|
$390.000
|
|
|
RIPRAP (MOW STRIP)(6 IN)
|
CY
|
48.300
|
$555.000
|
$375.000
|
$370.000
|
$452.000
|
$800.000
|
$390.000
|
|
|
RAIL (TY SSTR)
|
LF
|
1,551.010
|
$55.000
|
$145.000
|
$125.000
|
$131.000
|
$70.000
|
$45.000
|
|
|
RAIL (TY SSTR) (W/DRAIN SLOTS)
|
LF
|
245.000
|
$55.000
|
$145.000
|
$170.000
|
$149.000
|
$85.000
|
$20.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
|
LF
|
178.000
|
$200.000
|
$150.000
|
$170.000
|
$162.000
|
$165.000
|
$155.000
|
|
|
CONC BOX CULV (3 FT X 2 FT)
|
LF
|
205.000
|
$250.000
|
$150.000
|
$200.000
|
$153.000
|
$199.000
|
$250.000
|
|
|
CONC BOX CULV (4 FT X 4 FT)
|
LF
|
67.000
|
$300.000
|
$245.000
|
$280.000
|
$254.000
|
$291.000
|
$410.000
|
|
|
CONC BOX CULV (6 FT X 3 FT)
|
LF
|
254.000
|
$370.000
|
$300.000
|
$410.000
|
$371.000
|
$390.000
|
$570.000
|
|
|
CONC BOX CULV (8 FT X 5 FT)
|
LF
|
25.000
|
$450.000
|
$700.000
|
$645.000
|
$593.000
|
$615.000
|
$950.000
|
|
|
RC PIPE (CL IV)(18 IN)
|
LF
|
509.000
|
$60.000
|
$53.000
|
$45.000
|
$55.750
|
$43.000
|
$90.000
|
|
|
RC PIPE (CL IV)(24 IN)
|
LF
|
1,915.000
|
$80.000
|
$60.000
|
$51.000
|
$64.500
|
$49.000
|
$100.000
|
|
|
RC PIPE (CL IV)(30 IN)
|
LF
|
414.000
|
$110.000
|
$75.000
|
$75.000
|
$85.500
|
$74.000
|
$130.000
|
|
|
RC PIPE (CL IV)(36 IN)
|
LF
|
1,168.000
|
$120.000
|
$96.000
|
$99.000
|
$119.000
|
$94.000
|
$175.000
|
|
|
RC PIPE (CL IV)(42 IN)
|
LF
|
330.000
|
$140.000
|
$115.000
|
$125.000
|
$138.500
|
$120.000
|
$220.000
|
|
|
INLET (COMPL)(TY MSE1)
|
EA
|
5.000
|
$2,000.000
|
$3,000.000
|
$3,800.000
|
$2,680.000
|
$3,650.000
|
$5,000.000
|
|
|
INLET (COMPL)(TY MSE2)
|
EA
|
1.000
|
$2,500.000
|
$3,400.000
|
$4,040.000
|
$3,330.000
|
$3,850.000
|
$5,500.000
|
|
|
HEADWALL (CH - FW - 0) (DIA= 42 IN)
|
EA
|
1.000
|
$5,000.000
|
$9,000.000
|
$8,250.000
|
$8,500.000
|
$7,900.000
|
$8,000.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 30 IN)
|
EA
|
4.000
|
$7,000.000
|
$7,500.000
|
$8,670.000
|
$6,850.000
|
$8,265.000
|
$8,000.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 36 IN)
|
EA
|
10.000
|
$8,000.000
|
$8,500.000
|
$8,950.000
|
$7,460.000
|
$8,520.000
|
$8,500.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 42 IN)
|
EA
|
4.000
|
$9,000.000
|
$10,000.000
|
$9,800.000
|
$10,900.000
|
$9,350.000
|
$9,000.000
|
|
|
HEADWALL (CH - PW - S) (DIA= 36 IN)
|
EA
|
1.000
|
$8,000.000
|
$12,500.000
|
$9,600.000
|
$9,690.000
|
$9,150.000
|
$9,500.000
|
|
|
WINGWALL (PW - 1) (HW=10 FT)
|
EA
|
2.000
|
$16,000.000
|
$50,000.000
|
$19,820.000
|
$40,500.000
|
$18,875.000
|
$15,000.000
|
|
|
WINGWALL (PW - 1) (HW=11 FT)
|
EA
|
1.000
|
$16,750.000
|
$61,000.000
|
$24,830.000
|
$53,600.000
|
$23,650.000
|
$15,000.000
|
|
|
WINGWALL (PW - 1) (HW=5 FT)
|
EA
|
2.000
|
$11,500.000
|
$21,500.000
|
$16,425.000
|
$14,600.000
|
$15,600.000
|
$10,000.000
|
|
|
WINGWALL (PW - 1) (HW=6 FT)
|
EA
|
3.000
|
$13,860.000
|
$24,000.000
|
$18,740.000
|
$18,000.000
|
$17,850.000
|
$11,000.000
|
|
|
WINGWALL (PW - 1) (HW=7 FT)
|
EA
|
2.000
|
$13,889.000
|
$27,000.000
|
$19,580.000
|
$21,800.000
|
$19,000.000
|
$12,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
22.000
|
$1,000.000
|
$900.000
|
$1,310.000
|
$1,120.000
|
$1,250.000
|
$1,500.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
95.000
|
$1,200.000
|
$1,250.000
|
$1,730.000
|
$1,670.000
|
$1,650.000
|
$1,600.000
|
|
|
SET (TY II) (36 IN) (RCP) (6: 1) (C)
|
EA
|
2.000
|
$3,400.000
|
$3,500.000
|
$4,720.000
|
$5,440.000
|
$4,500.000
|
$1,600.000
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
12.000
|
$1,200.000
|
$1,500.000
|
$2,626.000
|
$3,520.000
|
$2,500.000
|
$2,500.000
|
|
|
REMOV STR (SET)
|
EA
|
60.000
|
$300.000
|
$200.000
|
$370.000
|
$273.000
|
$350.000
|
$200.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
6.000
|
$1,000.000
|
$3,000.000
|
$1,040.000
|
$2,300.000
|
$9,900.000
|
$350.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
3.000
|
$1,200.000
|
$6,500.000
|
$890.000
|
$1,630.000
|
$850.000
|
$350.000
|
|
|
REMOV STR (PIPE)
|
LF
|
1,440.000
|
$6.000
|
$5.000
|
$6.000
|
$16.000
|
$5.000
|
$11.000
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
170.000
|
$26.000
|
$15.000
|
$94.000
|
$47.000
|
$85.000
|
$23.000
|
|
|
REMOV STR (CATTLE GUARD)
|
EA
|
5.000
|
$250.000
|
$2,500.000
|
$3,140.000
|
$639.000
|
$1,250.000
|
$145.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$2,900,000.000
|
$2,000,000.000
|
$1,730,000.000
|
$1,800,000.000
|
$2,700,000.000
|
$1,249,023.100
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
38.000
|
$8,500.000
|
$730.690
|
$1,060.000
|
$3,010.000
|
$4,500.000
|
$7,500.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
4,229.000
|
$30.000
|
$28.000
|
$29.000
|
$35.750
|
$28.000
|
$25.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 4)
|
LF
|
868.000
|
$40.000
|
$52.500
|
$55.000
|
$69.500
|
$52.000
|
$25.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
5,097.000
|
$12.000
|
$27.250
|
$15.000
|
$17.000
|
$15.000
|
$15.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
1,887.000
|
$40.000
|
$27.250
|
$28.000
|
$20.750
|
$28.000
|
$10.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
1,887.000
|
$15.000
|
$10.000
|
$15.000
|
$8.100
|
$15.000
|
$5.000
|
|
|
BACKHOE WORK (EROSION & SEDMT CONT)
|
HR
|
40.000
|
$90.000
|
$50.000
|
$90.000
|
$53.500
|
$125.000
|
$75.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
30,505.000
|
$3.000
|
$3.250
|
$3.000
|
$3.500
|
$2.800
|
$2.650
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
30,505.000
|
$1.500
|
$1.250
|
$1.200
|
$1.550
|
$1.200
|
$1.300
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
2,280.000
|
$6.000
|
$5.950
|
$6.000
|
$7.450
|
$5.900
|
$5.600
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
2,280.000
|
$1.000
|
$1.250
|
$1.200
|
$1.450
|
$1.200
|
$1.300
|
|
|
CONSTRUCTING DETOURS
|
SY
|
5,690.000
|
$50.000
|
$60.000
|
$70.000
|
$92.500
|
$75.000
|
$70.000
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
13,560.000
|
$32.000
|
$65.000
|
$30.000
|
$66.000
|
$25.000
|
$55.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
21,150.000
|
$5.000
|
$5.000
|
$9.000
|
$3.950
|
$9.000
|
$12.000
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
13,560.000
|
$7.000
|
$10.000
|
$17.000
|
$12.750
|
$9.500
|
$8.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
4,831.000
|
$36.000
|
$42.720
|
$40.000
|
$32.500
|
$40.000
|
$52.000
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
98,411.000
|
$0.270
|
$0.180
|
$0.150
|
$0.210
|
$0.400
|
$0.300
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
5,225.000
|
$25.000
|
$27.490
|
$31.000
|
$34.500
|
$26.000
|
$35.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$1,820.000
|
$1,949.210
|
$2,900.000
|
$2,660.000
|
$1,900.000
|
$3,000.000
|
|
|
MTL W-BEAM GD FEN ADJUSTMENT
|
LF
|
625.000
|
$10.000
|
$5.490
|
$32.000
|
$11.750
|
$6.500
|
$20.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
10.000
|
$2,200.000
|
$1,449.210
|
$1,440.000
|
$1,610.000
|
$1,325.000
|
$2,500.000
|
|
|
MTL BM GD FEN (LONG SPAN SYSTEM)
|
LF
|
500.000
|
$30.000
|
$30.490
|
$30.000
|
$34.250
|
$33.000
|
$45.000
|
|
|
MTL BM GD FEN TRANS (NON - SYM)
|
EA
|
1.000
|
$900.000
|
$749.210
|
$860.000
|
$958.000
|
$900.000
|
$500.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,443.000
|
$3.000
|
$1.490
|
$4.200
|
$4.000
|
$0.950
|
$6.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
1.000
|
$200.000
|
$195.210
|
$290.000
|
$289.000
|
$200.000
|
$750.000
|
|
|
REMOVE DOWNSTREAM ANCHOR TERMINAL
|
EA
|
2.000
|
$200.000
|
$195.210
|
$290.000
|
$289.000
|
$200.000
|
$750.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
39.000
|
$2,112.000
|
$3,349.210
|
$3,470.000
|
$3,880.000
|
$3,275.000
|
$5,000.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
13.000
|
$150.000
|
$195.210
|
$290.000
|
$289.000
|
$280.000
|
$1,000.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
17.000
|
$3,850.000
|
$915.210
|
$1,150.000
|
$1,170.000
|
$1,200.000
|
$3,000.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
20.000
|
$1,600.000
|
$915.210
|
$1,050.000
|
$844.000
|
$700.000
|
$1,500.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
20.000
|
$10,000.000
|
$9,662.850
|
$8,740.000
|
$11,000.000
|
$8,830.000
|
$15,000.000
|
|
|
CHAIN LINK FENCE (INSTALL) (6')
|
LF
|
2,559.000
|
$35.000
|
$30.000
|
$33.000
|
$36.250
|
$65.000
|
$20.000
|
|
|
PIPE UNDERDRAINS (TY 6) (6")
|
LF
|
1,475.000
|
$20.000
|
$40.810
|
$26.000
|
$31.500
|
$38.000
|
$15.000
|
|
|
MAILBOX INSTALL-S (TWW-POST) TY 4
|
EA
|
15.000
|
$300.000
|
$215.000
|
$225.000
|
$252.000
|
$275.000
|
$280.000
|
|
|
CONDT (PVC) (SCH 80) (2")
|
LF
|
286.000
|
$9.000
|
$8.000
|
$9.000
|
$9.400
|
$8.000
|
$22.000
|
|
|
ELEC CONDR (NO.6) BARE
|
LF
|
44.000
|
$1.500
|
$1.800
|
$2.000
|
$2.100
|
$2.000
|
$3.000
|
|
|
ELEC CONDR (NO.6) INSULATED
|
LF
|
22.000
|
$1.700
|
$2.000
|
$2.100
|
$2.300
|
$2.000
|
$3.000
|
|
|
TRAY CABLE (4 CONDR) (12 AWG)
|
LF
|
421.000
|
$2.000
|
$2.200
|
$2.300
|
$2.600
|
$2.250
|
$3.000
|
|
|
ZINC-COAT STL WIRE STRAND (3/8")
|
LF
|
280.000
|
$2.500
|
$2.500
|
$3.000
|
$2.950
|
$2.500
|
$6.000
|
|
|
REMOVE ELECTRICAL SERVICES
|
EA
|
1.000
|
$1,500.000
|
$650.000
|
$680.000
|
$762.000
|
$650.000
|
$1,000.000
|
|
|
ELC SRV TY T 120/240 000(NS)GS(L)TS(O)
|
EA
|
1.000
|
$5,000.000
|
$2,100.000
|
$2,200.000
|
$2,460.000
|
$2,100.000
|
$8,000.000
|
|
|
ELC SRV TY T 120/240 000(NS)GS(L)TS(U)
|
EA
|
1.000
|
$5,500.000
|
$1,530.000
|
$1,600.000
|
$1,790.000
|
$1,550.000
|
$8,000.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
47.000
|
$540.000
|
$785.000
|
$820.000
|
$921.000
|
$736.000
|
$1,500.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
25.000
|
$640.000
|
$850.000
|
$900.000
|
$997.000
|
$780.000
|
$1,200.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
1.000
|
$680.000
|
$1,150.000
|
$1,200.000
|
$1,350.000
|
$1,000.000
|
$1,600.000
|
|
|
IN SM RD SN SUP&AM TYS80(2)SA(T-2EXT)
|
EA
|
1.000
|
$1,500.000
|
$2,450.000
|
$2,580.000
|
$2,870.000
|
$2,200.000
|
$3,300.000
|
|
|
RELOCATE SM RD SN SUP&AM TY S80
|
EA
|
3.000
|
$565.000
|
$575.000
|
$600.000
|
$651.000
|
$800.000
|
$800.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
19.000
|
$80.000
|
$75.000
|
$79.000
|
$88.000
|
$100.000
|
$150.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
|
EA
|
61.000
|
$26.000
|
$15.000
|
$16.000
|
$17.500
|
$25.000
|
$20.000
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
|
EA
|
11.000
|
$20.000
|
$15.000
|
$16.000
|
$17.500
|
$25.000
|
$20.000
|
|
|
INSTL DEL ASSM (D-DY)SZ 2(WC)GND
|
EA
|
6.000
|
$90.000
|
$45.000
|
$48.000
|
$53.000
|
$60.000
|
$60.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
273.000
|
$35.000
|
$18.000
|
$19.000
|
$21.000
|
$40.000
|
$26.000
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
|
EA
|
50.000
|
$18.000
|
$21.000
|
$22.000
|
$24.750
|
$40.000
|
$30.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND
|
EA
|
134.000
|
$90.000
|
$60.000
|
$63.000
|
$70.500
|
$50.000
|
$81.000
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
2,148.000
|
$3.330
|
$4.500
|
$5.000
|
$5.300
|
$4.500
|
$6.000
|
|
|
WK ZN PAV MRK REMOV (W)4"(BRK)
|
LF
|
810.000
|
$0.600
|
$0.440
|
$0.500
|
$0.500
|
$0.450
|
$0.450
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
149,130.000
|
$0.600
|
$0.400
|
$0.400
|
$0.480
|
$0.400
|
$0.400
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
151,424.000
|
$0.600
|
$0.400
|
$0.400
|
$0.480
|
$0.400
|
$0.400
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
6,428.000
|
$1.690
|
$0.440
|
$0.500
|
$0.500
|
$0.450
|
$0.450
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
72.000
|
$6.090
|
$14.000
|
$15.000
|
$16.500
|
$14.000
|
$15.000
|
|
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
|
LF
|
2,009.000
|
$5.300
|
$3.000
|
$3.000
|
$3.500
|
$3.000
|
$3.000
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
19,010.000
|
$0.600
|
$0.420
|
$0.450
|
$0.500
|
$0.450
|
$0.450
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
78,318.000
|
$0.340
|
$0.400
|
$0.400
|
$0.480
|
$0.400
|
$0.400
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
10,126.000
|
$0.340
|
$0.420
|
$0.450
|
$0.500
|
$0.450
|
$0.450
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
79,035.000
|
$0.440
|
$0.400
|
$0.400
|
$0.480
|
$0.400
|
$0.400
|
|
PREFAB PAV MRK TY B (W)(4")(BRK)CNTST
|
LF
|
50.000
|
$48.000
|
$12.000
|
$12.000
|
$14.000
|
$12.000
|
$12.000
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
24.000
|
$260.000
|
$175.000
|
$180.000
|
$205.000
|
$175.000
|
$300.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
16.000
|
$280.000
|
$250.000
|
$260.000
|
$293.000
|
$250.000
|
$350.000
|
|
REFL PAV MRKR TY I-A
|
EA
|
100.000
|
$3.060
|
$4.500
|
$5.000
|
$5.300
|
$4.500
|
$7.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
547.000
|
$3.200
|
$4.500
|
$5.000
|
$5.300
|
$4.500
|
$7.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,160.000
|
$3.430
|
$4.250
|
$5.000
|
$5.000
|
$4.250
|
$6.000
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
736.000
|
$4.800
|
$4.500
|
$5.000
|
$5.300
|
$4.500
|
$6.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
79,241.000
|
$0.600
|
$0.320
|
$0.400
|
$0.370
|
$0.350
|
$0.350
|
|
|
INSTALL HWY TRF SIG (FLASH BEACON)
|
EA
|
2.000
|
$20,000.000
|
$1,850.000
|
$1,900.000
|
$2,170.000
|
$1,900.000
|
$8,000.000
|
|
|
REMOVING TRAFFIC SIGNALS
|
EA
|
1.000
|
$7,500.000
|
$1,250.000
|
$1,300.000
|
$1,470.000
|
$1,300.000
|
$3,500.000
|
|
|
VEH SIG SEC (12")LED(YEL)
|
EA
|
5.000
|
$230.000
|
$225.000
|
$240.000
|
$264.000
|
$230.000
|
$600.000
|
|
|
VEH SIG SEC (12")LED(RED)
|
EA
|
6.000
|
$230.000
|
$225.000
|
$240.000
|
$264.000
|
$230.000
|
$600.000
|
|
|
BACK PLATE (12")(1 SEC)
|
EA
|
11.000
|
$70.000
|
$50.000
|
$52.000
|
$58.500
|
$50.000
|
$110.000
|
|
|
TRF SIG CBL (TY A)(12 AWG)(5 CONDR)
|
LF
|
1,214.000
|
$2.000
|
$2.400
|
$2.500
|
$2.800
|
$2.400
|
$3.500
|
|
|
INS TRF SIG PL AM (S)STR(TY D)LUM
|
EA
|
4.000
|
$7,000.000
|
$9,200.000
|
$9,660.000
|
$10,800.000
|
$9,200.000
|
$15,000.000
|
|
|
POTHOLE REPAIR (STANDARD)
|
SY
|
1,000.000
|
$150.000
|
$24.240
|
$120.000
|
$71.000
|
$68.000
|
$90.000
|
|
|
STRIP MOWING
|
AC
|
558.000
|
$310.000
|
$90.000
|
$94.000
|
$158.000
|
$285.000
|
$750.000
|
|
|
LITTER REMOVAL
|
AC
|
558.000
|
$95.000
|
$30.000
|
$150.000
|
$84.000
|
$80.000
|
$15.000
|
|
|
CLEANING / SWEEPING (SPOT)
|
MI
|
18.600
|
$820.000
|
$622.870
|
$580.000
|
$578.000
|
$550.000
|
$3,000.000
|
|
|
SP MIXES SP-D SAC-A PG76-22
|
TON
|
58,066.000
|
$125.000
|
$105.000
|
$110.000
|
$132.000
|
$110.000
|
$130.000
|
|
|
BONDING COURSE
|
GAL
|
29,198.000
|
$4.000
|
$3.000
|
$4.000
|
$5.000
|
$3.500
|
$2.000
|
|
|
INTRLCK ART CONC BLKS (4" MIN)
|
SF
|
13,988.000
|
$10.000
|
$6.170
|
$10.000
|
$7.500
|
$22.000
|
$20.000
|
|
|
GEOGRID BASE REINFORCEMENT (TY II)
|
SY
|
276,868.000
|
$1.300
|
$1.500
|
$1.150
|
$1.100
|
$1.350
|
$2.250
|
|
|
BIRD EXCLUSION METHOD
|
SF
|
14,740.000
|
$4.260
|
$1.500
|
$4.800
|
$2.850
|
$4.000
|
$10.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$10,000.000
|
$850.000
|
$32,000.000
|
$11,700.000
|
$7,500.000
|
$15,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
1,812.000
|
$200.000
|
$15.000
|
$30.000
|
$57.500
|
$0.010
|
$100.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
722.000
|
$150.000
|
$25.000
|
$70.000
|
$63.500
|
$0.010
|
$600.000
|
|
Totals: |
$29,012,476.170
|
$24,806,298.902
|
$26,972,527.120
|
$30,072,354.690
|
$30,103,724.590
|
$30,750,000.000
|