Show Job Controls
Bid Cobra

SOMERVELL VA (0902-41-002)

Items: 48

County: SOMERVELL
Length: N/A
Highway: VA
District: FORT WORTH
Control Number: 0902-41-002
DBE Goal: 700.0%
Project: STP 2022(832)TAPS
Guaranty: N/A
Time: 215 WORKING DAYS
Engineer's Estimate: $1,628,621.00
Date: 08/02/2024 (1 year ago)
Contract Number: N/A
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Mail/Deliver Bids To: N/A
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$1,628,621.00
$1,348,858.00
Over/Under Est: -17.18% -$279,763.00
Over/Under Est: -14.78% -$240,694.20
Amt Left: 2.9% $39,068.80
$1,396,733.33
Over/Under Est: -14.24% -$231,887.67
Amt Left: 3.55% $47,875.33
Delta: -0.63% -$8,806.53
$1,398,638.92
Over/Under Est: -14.12% -$229,982.08
Amt Left: 3.69% $49,780.92
Delta: -0.14% -$1,905.59
Over/Under Est: -11.97% -$194,966.42
Amt Left: 6.29% $84,796.58
Delta: -2.50% -$35,015.66
$1,499,997.98
Over/Under Est: -7.9% -$128,623.02
Amt Left: 11.21% $151,139.98
Delta: -4.63% -$66,343.40
$1,926,850.00
Over/Under Est: 18.31% $298,229.00
Amt Left: 42.85% $577,992.00
Delta: -28.46% -$426,852.02
Subcontractor Percentage Amount
WG ENGINEERING & CONSTRUCTION, LLC 2.80% $38,081.32
EJT TRUCKING, LLC 2.79% $37,945.31
ROAD MASTER STRIPING, LLC 0.74% $10,064.35
Total: 6.33% $86,090.98

Bid Items & Bid Tabulations

48 Total 0 of 48
SOMERVELL  |  VA  |  FORT WORTH  |  0902-41-002  |  08/02/2024  |  $1,628,621.00  |  STP 2022(832)TAPS  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  215 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GARRET SHIELDS INFRASTRUCTURE
RISE UP CONSTRUCTION LLC
TALBERT COMPANIES LLC
TI-ZACK CONCRETE, LLC
PROJECT ALLIED RESOURCES, LLC
ENCINO LANDSCAPE, INC.
FNH CONSTRUCTION, LLC
REMOVING CONC (DRIVEWAYS)
SY 1,771.000 $30.000 $40.000 $35.000 $20.900 $43.260 $15.300 $19.500 $50.000
REMOVING CONC (CURB OR CURB & GUTTER)
LF 1,457.000 $40.000 $20.000 $20.000 $11.000 $13.140 $8.500 $19.500 $50.000
REMOVING CONC (SIDEWALK OR RAMP)
SY 62.000 $60.000 $40.000 $40.000 $33.000 $30.890 $17.000 $30.000 $30.000
REMOVING STAB BASE AND ASPH PAV (2"-6")
SY 442.000 $15.000 $20.000 $40.000 $20.350 $32.500 $5.600 $38.000 $50.000
EXCAVATION (SPECIAL)
CY 10.000 $250.000 $100.000 $400.000 $88.000 $478.800 $55.000 $50.000 $250.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 8.000 $110.000 $100.000 $70.000 $99.000 $119.700 $102.000 $50.000 $100.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 773.000 $3.000 $2.000 $2.600 $4.400 $3.300 $14.900 $0.100 $3.000
CONCRETE PAINT FINISH
SF 156.000 $10.000 $10.000 $50.000 $106.980 $13.200 $11.500 $50.000 $25.000
RIPRAP (CONC)(4 IN)
CY 2.000 $900.000 $600.000 $877.000 $770.000 $718.520 $1,080.000 $1,000.000 $1,200.000
RAIL (HANDRAIL)(TY B)
LF 39.000 $200.000 $300.000 $250.000 $187.000 $275.000 $513.000 $800.000 $250.000
ADJUSTING MANHOLES (SANITARY)
EA 4.000 $3,500.000 $1,000.000 $1,000.000 $660.000 $2,394.000 $2,160.000 $1,000.000 $2,500.000
ADJUSTING MANHOLES (WATER VALVE BOX)
EA 5.000 $1,700.000 $500.000 $700.000 $275.000 $191.520 $1,730.000 $500.000 $1,500.000
ADJUSTING MANHOLES (WATER METER)
EA 10.000 $1,100.000 $500.000 $150.000 $440.000 $957.600 $1,930.000 $500.000 $1,500.000
MOBILIZATION
LS 1.000 $173,428.000 $140,000.000 $138,000.000 $209,000.000 $149,469.300 $151,000.000 $150,000.000 $200,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $10,000.000 $1,000.000 $4,800.000 $11,550.000 $3,850.000 $7,030.000 $5,000.000 $15,000.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 108.000 $7.000 $5.000 $70.000 $30.800 $1.100 $14.700 $10.000 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 108.000 $10.000 $1.000 $1.000 $8.800 $1.100 $2.870 $1.000 $9.000
CONC CURB (MONO) (TY II)
LF 50.000 $35.000 $40.000 $67.000 $57.200 $56.600 $9.700 $30.000 $65.000
CONC CURB & GUTTER (TY II)
LF 2,226.000 $70.000 $40.000 $47.000 $45.100 $56.600 $36.300 $35.000 $85.000
CONC CURB (TY F1)
LF 14.000 $120.000 $100.000 $150.000 $88.000 $311.330 $262.000 $200.000 $100.000
DRIVEWAYS (CONC)
SY 1,774.000 $150.000 $130.000 $145.000 $112.480 $142.070 $128.000 $120.000 $200.000
CONC SIDEWALKS (4")
SY 3,549.000 $100.000 $140.000 $88.000 $93.940 $111.160 $101.000 $120.000 $85.000
CURB RAMPS (TY 1)
EA 4.000 $3,000.000 $3,000.000 $2,500.000 $24.700 $2,177.320 $3,400.000 $2,500.000 $3,500.000
CURB RAMPS (TY 2)
EA 8.000 $3,500.000 $3,000.000 $2,500.000 $2,640.000 $2,177.320 $3,400.000 $2,500.000 $3,500.000
CURB RAMPS (TY 7)
EA 14.000 $3,500.000 $3,000.000 $3,500.000 $2,530.000 $2,177.320 $3,400.000 $2,500.000 $3,500.000
CURB RAMPS (TY 10)
EA 4.000 $2,800.000 $3,000.000 $2,500.000 $2,750.000 $2,177.320 $3,400.000 $2,500.000 $3,500.000
CONC SIDEWALKS (SPECIAL) (TYPE B)
SY 570.000 $170.000 $130.000 $340.000 $134.200 $273.720 $242.000 $200.000 $100.000
RELOCATE EXISTING MAILBOX
EA 2.000 $1,000.000 $500.000 $500.000 $550.000 $275.000 $548.000 $300.000 $1,250.000
GROUND BOX TY D (162922)W/APRON
EA 1.000 $2,200.000 $3,000.000 $1,500.000 $2,750.000 $1,650.000 $3,100.000 $1,000.000 $1,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 4.000 $2,000.000 $600.000 $950.000 $990.000 $495.000 $1,310.000 $500.000 $1,500.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 19.000 $1,000.000 $400.000 $800.000 $1,100.000 $495.000 $940.000 $300.000 $1,000.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 847.000 $15.000 $10.000 $6.000 $6.120 $10.450 $15.100 $10.000 $20.000
REFL PAV MRK TY II (W) 4" (SLD)
LF 104.000 $2.000 $2.000 $2.000 $1.560 $1.650 $3.860 $5.000 $2.000
REFL PAV MRK TY II (W) 24" (SLD)
LF 847.000 $6.000 $3.000 $5.000 $3.800 $3.250 $9.400 $10.000 $20.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 104.000 $3.000 $4.000 $2.000 $2.210 $3.030 $5.500 $5.000 $2.000
PRE PM TY C(ACC PRK)(BL&WH)(W/BORDR)LG
EA 1.000 $500.000 $500.000 $1,200.000 $550.000 $467.500 $1,360.000 $500.000 $1,500.000
ELIM EXT PAV MRK & MRKS (4")
LF 68.000 $2.000 $2.000 $1.000 $0.590 $1.100 $1.470 $2.000 $2.000
ELIM EXT PAV MRK & MRKS (8")
LF 500.000 $3.000 $2.000 $3.000 $0.680 $1.650 $1.690 $2.000 $6.000
ELIM EXT PAV MRK & MRKS (SYMBOL)
EA 1.000 $150.000 $100.000 $300.000 $82.500 $77.000 $204.000 $200.000 $500.000
PAV SURF PREP FOR MRK (4")
LF 104.000 $1.000 $1.000 $5.000 $0.310 $0.550 $0.760 $2.000 $2.000
PAV SURF PREP FOR MRK (24")
LF 847.000 $3.000 $2.000 $5.000 $0.460 $1.100 $1.140 $2.000 $20.000
RELOCATE OF PEDESTRIAN PUSH BUTTON
EA 1.000 $500.000 $1,000.000 $6,000.000 $517.090 $935.000 $3,350.000 $500.000 $10,000.000
TREE REMOVAL (12" - 18" DIA)
EA 1.000 $650.000 $1,000.000 $1,000.000 $1,650.000 $2,750.000 $1,800.000 $5,342.680 $5,000.000
TREE TRIMMING
EA 13.000 $350.000 $400.000 $1,500.000 $412.500 $165.000 $570.000 $2,300.000 $5,000.000
TREE PROTECTION
EA 13.000 $1,000.000 $500.000 $100.000 $330.000 $165.000 $2,500.000 $3,000.000 $1,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 215.000 $150.000 $1.000 $1.000 $141.010 $1.100 $57.000 $300.000 $150.000
GROUND BOX W/ APRON (ADJUST)
EA 4.000 $1,000.000 $1,500.000 $1,000.000 $1,136.220 $1,650.000 $3,640.000 $1,000.000 $1,500.000
TMA (STATIONARY)
DAY 215.000 $300.000 $100.000 $1.000 $293.230 $1.100 $177.000 $300.000 $250.000
Totals: $1,628,621.000 $1,348,858.000 $1,387,926.800 $1,396,733.330 $1,398,638.920 $1,433,654.580 $1,499,997.980 $1,926,850.000