Show Job Controls
Bid Cobra

SMITH US0069 (6330-93-001)

Items: 49

County: SMITH
Length: N/A
Highway: US0069
District: TYLER
Control Number: 6330-93-001
DBE Goal: N/A
Project: RMC - 633093001
Guaranty: N/A
Time: 730 W
Engineer's Estimate: $475,621.80
Date: 06/06/2018 (7 years ago)
Contract Number: N/A
Type: GUARDRAIL REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$475,621.80
1
$400,142.00
Over/Under Est: -15.87% -$75,479.80
$463,844.00
Over/Under Est: -2.48% -$11,777.80
Amt Left: 15.92% $63,702.00
Over/Under Est: 4.55% $21,624.20
Amt Left: 24.27% $97,104.00
Delta: -7.20% -$33,402.00

Bid Items & Bid Tabulations

49 Total 0 of 49
SMITH  |  US0069  |  TYLER  |  6330-93-001  |  06/06/2018  |  $475,621.80  |  RMC - 633093001  |  GUARDRAIL REPAIR  |  730 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
CATOCON, INC.
IIPL USA LLC
T&L CLEANING SERVICES LLC
CONC STR REPAIR (STANDARD)
SF 20.000 $100.000 $60.000 $50.000 $40.000
MOBILIZATION (CALLOUT)
EA 40.000 $300.000 $150.000 $500.000 $100.000
MTL W-BEAM GD FEN (TIM POST)
LF 100.000 $16.000 $10.000 $10.000 $20.000
MTL THRIE-BEAM GD FEN (TIM POST)
LF 50.000 $30.000 $10.000 $20.000 $20.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $1,250.000 $500.000 $500.000 $1,500.000
MTL BEAM GD FEN TRANS (T101)
EA 2.000 $862.000 $1.000 $1.000 $1,000.000
MTL W-BEAM GD FEN ADJUSTMENT
LF 550.000 $10.000 $1.000 $2.000 $2.000
MTL THRIE-BEAM GD FEN ADJUSTMENT
LF 50.000 $3.600 $1.000 $5.000 $2.000
TRANSITION ADJUSTMENT
EA 2.000 $136.000 $1.000 $10.000 $2.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,175.000 $1.000 $1.000 $1,200.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 50.000 $17.250 $1.000 $1.000 $20.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 50.000 $22.750 $1.000 $5.000 $40.000
REMOVE METAL BEAM GUARD FENCE
LF 100.000 $4.000 $4.000 $2.000 $2.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $288.500 $1.000 $30.000 $100.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 2.000 $283.500 $100.000 $100.000 $500.000
GDRAIL END TRT(INST)(WOOD POST)(TY I)
EA 4.000 $1,943.250 $100.000 $800.000 $3,000.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,181.000 $100.000 $100.000 $1,000.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 4,150.000 $20.000 $21.000 $25.000 $19.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 50.000 $30.000 $29.000 $20.000 $21.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 10.000 $30.000 $30.000 $20.000 $22.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 200.000 $45.000 $45.000 $40.000 $60.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 6.000 $20.750 $60.000 $50.000 $100.000
REPAIR STEEL POST WITH BASE PLATE
EA 4.000 $174.500 $100.000 $1.000 $200.000
REALIGN POSTS
EA 240.000 $28.000 $20.000 $25.000 $20.000
INSTALL BLOCKOUT (TYPE SPECIFIED)
EA 12.000 $10.000 $100.000 $10.000 $10.000
REMOVE & REPLACE BLOCKOUT
EA 10.000 $10.000 $100.000 $50.000 $10.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 600.000 $25.000 $27.000 $30.000 $30.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 24.000 $59.000 $80.000 $80.000 $50.000
REPLACE TERMINAL ANCHOR POSTS
EA 2.000 $58.750 $1.000 $1.000 $1.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 76.000 $2,600.000 $2,590.000 $2,600.000 $3,000.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 10.000 $900.000 $975.000 $800.000 $900.000
REM & RESET SGT IMPACT HEAD
EA 4.000 $56.000 $500.000 $100.000 $50.000
REPLACE SGT CABLE ASSEMBLY
EA 4.000 $42.500 $1.000 $50.000 $50.000
REPLACE SGT CABLE ANCHOR
EA 4.000 $200.000 $1.000 $50.000 $80.000
REPLACE SGT STRUT
EA 2.000 $46.700 $1.000 $50.000 $80.000
REPLACE SGT OBJECT MARKER
EA 4.000 $23.750 $40.000 $1.000 $30.000
REPAIR RAIL ELEMENT(W - BEAM FURNISHED)
LF 50.000 $7.500 $15.000 $7.000 $14.000
REMOVE AND REPLACE (TRACC)
EA 2.000 $4,520.500 $2,000.000 $2,000.000 $12,000.000
REPAIR (TRACC)
EA 2.000 $1,678.500 $1,000.000 $1,000.000 $500.000
REPAIR (WIDE TRACC)
EA 2.000 $1,235.750 $400.000 $400.000 $1,500.000
REPAIR (NARROW QUAD)
EA 2.000 $1,146.000 $600.000 $600.000 $1,500.000
REPAIR (QUAD) (N) (BAY)
EA 4.000 $516.000 $750.000 $450.000 $700.000
REMOVE AND REPLACE (FASTRACC)
EA 2.000 $5,456.700 $4,000.000 $4,000.000 $15,000.000
REPAIR (FASTRACC) (BAY)
EA 10.000 $440.500 $620.000 $300.000 $500.000
QUAD(N)(BAY)NOSE ASSMBLY(REMOVE&REPLAC)
EA 10.000 $800.000 $670.000 $1,000.000 $700.000
REPAIR (STEEL POST W/ W-BEAM - T101)
LF 400.000 $77.400 $30.000 $40.000 $40.000
REPAIR (STL POST W/ DOUBLED W-BEAMS-T6)
LF 10.000 $37.000 $34.000 $30.000 $100.000
REPAIR(STEEL POST W/ CHANNEL IRON RAIL)
LF 50.000 $36.250 $20.000 $10.000 $100.000
TMA (STATIONARY)
DAY 80.000 $370.000 $125.000 $500.000 $100.000
Totals: $475,621.800 $400,142.000 $463,844.000 $497,246.000