Job Info for 0910-00-126

County: SMITH Highway: VA Date: 06/05/2019 (5 years ago) Engineer's Estimate: $892,205 Control Number: 0910-00-126
Project: C 910-00-126 District: TYLER Time: 75 WORKING DAYS Type: THERMOPLASTIC & PROFILE PAVEMENT MARKINGS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $892,204.60
TOTAL HIGHWAY MAINTENANCE, LLC   $738,213.91 1
-17.26% | -$153,990.69
STRIPE-A-ZONE, INC.   $774,423.61 2
-13.2% | -$117,780.99
4.91% | $36,209.70
STRIPING TECHNOLOGY, L.P.   $965,857.55 3
8.26% | $73,652.95
30.84% | $227,643.64
24.72% | $191,433.94
TRP CONSTRUCTION GROUP, LLC   $983,085.03 4
10.19% | $90,880.43
33.17% | $244,871.12
1.78% | $17,227.48

Bid Items

Items: 22, 0 filtered
SMITH VA  |  TYLER  |  0910-00-126  |  06/05/2019  |  $892,205  |  C 910-00-126  |  THERMOPLASTIC & PROFILE PAVMT MRK  |  75 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate TOTAL HIGHWAY MAINTENANCE, LLC STRIPE-A-ZONE, INC. STRIPING TECHNOLOGY, L.P. TRP CONSTRUCTION GROUP, LLC
500 6001 MOBILIZATION LS 1.000 $30,000.000 $10,000.000 $7,000.000 $40,000.000 $35,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $3,000.000 $2,500.000 $300.000 $4,500.000 $1,500.000
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 26,345.000 $0.800 $0.910 $0.800 $0.660 $0.900
666 6170 REFL PAV MRK TY II (W) 4" (SLD) LF 3,450.000 $0.100 $0.250 $0.250 $1.000 $1.000
666 6178 REFL PAV MRK TY II (W) 8" (SLD) LF 245.000 $0.300 $0.500 $1.000 $1.000 $2.000
666 6205 REFL PAV MRK TY II (Y) 4" (BRK) LF 80.000 $0.100 $0.500 $0.250 $1.000 $1.000
666 6207 REFL PAV MRK TY II (Y) 4" (SLD) LF 3,610.000 $0.200 $0.250 $0.250 $1.000 $1.000
666 6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) LF 81,180.000 $0.350 $0.330 $0.300 $0.360 $0.350
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 61,004.000 $0.300 $0.270 $0.280 $0.320 $0.350
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 39,410.000 $0.350 $0.330 $0.300 $0.360 $0.350
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 240,671.000 $0.300 $0.270 $0.280 $0.320 $0.350
666 6342 REF PROF PAV MRK TY I(W)4"(SLD)(100MIL) LF 438,102.000 $0.500 $0.470 $0.515 $0.580 $0.530
666 6344 REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL) LF 39,040.000 $0.550 $0.470 $0.515 $0.680 $0.600
666 6345 REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL) LF 605,289.000 $0.500 $0.470 $0.515 $0.580 $0.530
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 64,153.000 $0.500 $0.180 $0.300 $0.440 $0.350
677 6003 ELIM EXT PAV MRK & MRKS (8") LF 1,581.000 $0.800 $0.180 $0.500 $0.500 $1.000
677 6028 ELIM EXT PV MRK & MRKS (RUMBLE STRIP) LF 128,349.000 $0.700 $0.180 $0.250 $0.350 $1.000
678 6001 PAV SURF PREP FOR MRK (4") LF 7,140.000 $0.400 $0.450 $0.050 $0.100 $0.250
678 6004 PAV SURF PREP FOR MRK (8") LF 245.000 $0.800 $1.000 $1.000 $1.000 $5.000
6056 6002 PREFORMED CENTERLINE RUMBLE STRIP LF 2,691.000 $6.000 $7.000 $4.000 $8.500 $7.000
6185 6002 TMA (STATIONARY) DAY 55.000 $40.000 $1.000 $10.000 $50.000 $100.000
6185 6005 TMA (MOBILE OPERATION) DAY 38.000 $40.000 $1.000 $10.000 $50.000 $100.000
Totals: $892,204.60 $738,213.91 $774,423.62 $965,857.55 $983,085.03