Job Info for 0910-00-115

County: SMITH Highway: VA Date: 09/01/2021 (3 years ago) Engineer's Estimate: $2,453,269 Control Number: 0910-00-115
Project: F 2022(095) District: TYLER Time: 66 WORKING DAYS Type: PREVENTIVE MAINTENANCE
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5
Plans

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,453,268.58
TOTAL HIGHWAY MAINTENANCE, LLC   $2,493,889.71 1
1.66% | $40,621.13
STRIPING TECHNOLOGY, L.P.   $2,539,513.48 2
3.52% | $86,244.90
1.83% | $45,623.77
TRP CONSTRUCTION GROUP, LLC   $2,549,240.72 3
3.91% | $95,972.14
2.22% | $55,351.01
0.38% | $9,727.24
STRIPE-A-ZONE, INC.   $2,608,677.59 4
6.33% | $155,409.01
4.6% | $114,787.88
2.33% | $59,436.87
BATTERSON, LLP   $2,678,867.29 5
9.2% | $225,598.71
7.42% | $184,977.58
2.69% | $70,189.70

Bid Items

Items: 27, 0 filtered
SMITH VA  |  TYLER  |  0910-00-115  |  09/01/2021  |  $2,453,269  |  F 2022(095)  |  PREVENT MAINT  |  66 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate TOTAL HIGHWAY MAINTENANCE, LLC STRIPING TECHNOLOGY, L.P. TRP CONSTRUCTION GROUP, LLC STRIPE-A-ZONE, INC. BATTERSON, LLP
500 6001 MOBILIZATION LS 1.000 $50,000.000 $50,000.000 $25,000.000 $49,000.000 $1.000 $25,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $2,500.000 $500.000 $10,000.000 $2,500.000 $1.000 $3,500.000
666 6006 REFL PAV MRK TY I (W)4"(DOT)(100MIL) LF 4,610.000 $1.000 $1.750 $0.500 $0.900 $0.500 $1.560
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 81,787.000 $0.650 $1.000 $0.740 $0.720 $0.650 $0.700
666 6042 REFL PAV MRK TY I (W)12"(SLD)(100MIL) LF 800.000 $3.000 $3.000 $3.000 $3.000 $4.000 $3.000
666 6045 REFL PAV MRK TY I (W)18"(SLD)(100MIL) LF 1,050.000 $5.000 $5.000 $4.000 $4.150 $5.000 $3.950
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 16,204.000 $5.000 $6.000 $5.000 $5.500 $6.000 $5.510
666 6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) LF 126,990.000 $0.300 $0.340 $0.320 $0.330 $0.360 $0.290
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 374,525.000 $0.270 $0.300 $0.300 $0.300 $0.320 $0.290
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 43,940.000 $0.300 $0.340 $0.320 $0.330 $0.360 $0.290
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 457,130.000 $0.270 $0.300 $0.300 $0.300 $0.320 $0.290
666 6342 REF PROF PAV MRK TY I(W)4"(SLD)(100MIL) LF 1,881,805.000 $0.490 $0.465 $0.500 $0.490 $0.520 $0.550
666 6344 REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL) LF 90,900.000 $0.490 $0.550 $0.600 $0.580 $0.520 $0.550
666 6345 REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL) LF 1,602,027.000 $0.490 $0.470 $0.500 $0.490 $0.520 $0.550
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 370.000 $185.500 $200.000 $173.500 $200.000 $250.000 $185.000
668 6078 PREFAB PAV MRK TY C (W) (DBL ARROW) EA 6.000 $300.000 $397.000 $235.500 $330.000 $300.000 $350.000
668 6083 PREFAB PAV MRK TY C (W) (LNDP ARROW) EA 36.000 $300.000 $428.000 $320.500 $420.000 $425.000 $400.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 309.000 $215.500 $260.000 $215.500 $265.000 $245.000 $230.000
668 6089 PREFAB PAV MRK TY C (W) (RR XING) EA 6.000 $495.500 $675.000 $535.500 $700.000 $625.000 $600.000
668 6091 PREFAB PAV MRK TY C (W) (18")(YLD TRI) EA 40.000 $25.000 $49.000 $45.000 $46.000 $38.000 $30.000
668 6092 PREFAB PAV MRK TY C (W) (36")(YLD TRI) EA 434.000 $27.500 $49.000 $35.250 $53.000 $45.000 $30.000
668 6101 PREFAB PAV MRK TY C (Y) (4") (SLD) LF 510.000 $3.500 $2.200 $3.000 $2.150 $4.000 $2.000
668 6113 PRE PM TY C(ACC PRK)(BL&WH)(W/BORDR)LG EA 1.000 $300.000 $336.000 $250.000 $234.000 $225.000 $250.000
668 6115 PREFAB PAV MRK TY C (MULTI) (SHIELD) EA 5.000 $2,045.000 $3,000.000 $1,750.000 $1,850.000 $2,500.000 $2,500.000
6056 6002 PREFORMED CENTERLINE RUMBLE STRIP LF 9,010.000 $4.000 $4.750 $4.300 $5.500 $4.000 $3.500
6185 6002 TMA (STATIONARY) DAY 68.000 $50.000 $25.000 $1.000 $10.000 $1.000 $1.000
6185 6005 TMA (MOBILE OPERATION) DAY 28.000 $50.000 $25.000 $1.000 $10.000 $1.000 $1.000
Totals: $2,453,268.58 $2,493,889.72 $2,539,513.48 $2,549,240.72 $2,608,677.59 $2,678,867.29