Job Info for 0910-00-107

County: SMITH Highway: VA Date: 01/09/2019 (5 years ago) Engineer's Estimate: $1,947,371 Control Number: 0910-00-107
Project: STP 2019(324) District: TYLER Time: 120 WORKING DAYS Type: THERMOPLASTIC PAVEMENT MARKINGS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,947,371.10
CENTERLINE TECHNOLOGIES, LLC   $1,530,349.74 1
-21.41% | -$417,021.36
MIJELUM   $1,792,801.33 2
-7.94% | -$154,569.77
17.15% | $262,451.59
STRIPING TECHNOLOGY, L.P.   $1,833,898.76 3
-5.83% | -$113,472.34
19.84% | $303,549.02
2.29% | $41,097.43
STRIPE-A-ZONE, INC.   $1,946,497.46 4
-0.04% | -$873.64
27.19% | $416,147.72
6.14% | $112,598.70
TOTAL HIGHWAY MAINTENANCE, LLC   $2,088,230.76 5
7.23% | $140,859.66
36.45% | $557,881.02
7.28% | $141,733.30
TRP CONSTRUCTION GROUP, LLC   $2,578,805.28 6
32.42% | $631,434.18
68.51% | $1,048,455.54
23.49% | $490,574.52

Bid Items

Items: 21, 0 filtered
SMITH VA  |  TYLER  |  0910-00-107  |  01/09/2019  |  $1,947,371  |  STP 2019(324)  |  THERMOPLASTIC PAVMT MRK  |  120 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate CENTERLINE TECHNOLOGIES, LLC MIJELUM STRIPING TECHNOLOGY, L.P. STRIPE-A-ZONE, INC. TOTAL HIGHWAY MAINTENANCE, LLC TRP CONSTRUCTION GROUP, LLC
500 6001 MOBILIZATION LS 1.000 $100,000.000 $1.000 $50,000.000 $50,000.000 $10,000.000 $39,500.000 $200,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 $5,000.000 $1.000 $1,000.000 $2,500.000 $5,000.000 $4,100.000 $7,500.000
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 47,634.000 $0.750 $0.380 $1.300 $0.740 $0.800 $0.780 $0.840
666 6042 REFL PAV MRK TY I (W)12"(SLD)(100MIL) LF 3,452.000 $2.500 $3.000 $3.000 $3.200 $2.450 $2.850 $3.200
666 6045 REFL PAV MRK TY I (W)18"(SLD)(100MIL) LF 680.000 $3.000 $4.000 $4.000 $4.250 $3.850 $5.000 $5.900
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 18,952.000 $4.000 $3.500 $4.999 $5.200 $4.500 $5.450 $6.100
666 6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) LF 175,251.000 $0.300 $0.250 $0.239 $0.300 $0.380 $0.360 $0.370
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 2,190,785.000 $0.250 $0.240 $0.239 $0.260 $0.289 $0.310 $0.350
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 118,430.000 $0.300 $0.250 $0.239 $0.300 $0.340 $0.360 $0.370
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 1,816,505.000 $0.250 $0.240 $0.239 $0.260 $0.295 $0.310 $0.350
666 6342 REF PROF PAV MRK TY I(W)4"(SLD)(100MIL) LF 97,180.000 $0.800 $0.470 $0.600 $0.600 $0.555 $0.580 $0.650
666 6344 REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL) LF 16,390.000 $1.000 $0.500 $0.609 $1.000 $0.550 $0.710 $0.850
666 6345 REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL) LF 273,771.000 $0.800 $0.470 $0.609 $0.600 $0.550 $0.580 $0.650
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 468.000 $190.000 $170.000 $180.000 $170.500 $195.000 $185.000 $246.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 367.000 $260.000 $195.000 $290.000 $217.500 $285.000 $249.000 $346.000
668 6089 PREFAB PAV MRK TY C (W) (RR XING) EA 12.000 $550.000 $450.000 $800.000 $480.500 $680.000 $627.000 $803.000
668 6091 PREFAB PAV MRK TY C (W) (18")(YLD TRI) EA 454.000 $30.000 $17.000 $28.000 $22.500 $25.000 $31.000 $57.000
668 6092 PREFAB PAV MRK TY C (W) (36")(YLD TRI) EA 960.000 $35.000 $22.000 $40.000 $32.500 $35.000 $36.000 $61.000
6056 6002 PREFORMED CENTERLINE RUMBLE STRIP LF 5,910.000 $3.000 $5.000 $3.000 $5.500 $4.500 $5.610 $8.000
6185 6002 TMA (STATIONARY) DAY 28.000 $150.000 $1.000 $250.000 $50.000 $10.000 $225.000 $50.000
6185 6005 TMA (MOBILE OPERATION) DAY 180.000 $150.000 $1.000 $150.000 $50.000 $10.000 $100.000 $25.000
Totals: $1,947,371.10 $1,530,349.74 $1,792,801.37 $1,833,898.76 $1,946,497.47 $2,088,230.76 $2,578,805.28