Job Info for 0910-00-100

County: SMITH Highway: VA Date: 01/04/2017 (7 years ago) Engineer's Estimate: $311,113 Control Number: 0910-00-100
Project: STP 2017(230) District: TYLER Time: 26 WORKING DAYS Type: THERMOPLASTIC STRIPING

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $311,113.40
STRIPE-A-ZONE, INC.   $209,929.70 1
-32.52% | -$101,183.70
STRIPING TECHNOLOGY, L.P.   $225,641.05 2
-27.47% | -$85,472.35
7.48% | $15,711.35
BATTERSON, LLP   $247,338.00 3
-20.5% | -$63,775.40
17.82% | $37,408.30
9.62% | $21,696.95
TRP CONSTRUCTION GROUP, LLC   $271,006.40 4
-12.89% | -$40,107.00
29.09% | $61,076.70
9.57% | $23,668.40
TOTAL HIGHWAY MAINTENANCE, LLC   $292,302.00 5
-6.05% | -$18,811.40
39.24% | $82,372.30
7.86% | $21,295.60
HIGHWAY GRAPHICS, LLC   $783,489.00 6
151.83% | $472,375.60
273.21% | $573,559.30
168.04% | $491,187.00

Bid Items

Items: 12, 0 filtered
SMITH VA  |  TYLER  |  0910-00-100  |  01/04/2017  |  $311,113  |  STP 2017(230)  |  THERMOPLASTIC STRIPING  |  26 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate STRIPE-A-ZONE, INC. STRIPING TECHNOLOGY, L.P. BATTERSON, LLP TRP CONSTRUCTION GROUP, LLC TOTAL HIGHWAY MAINTENANCE, LLC HIGHWAY GRAPHICS, LLC
500 6001 MOBILIZATION LS 1.000 $17,155.000 $1.000 $5.000 $4,500.000 $15,000.000 $3,200.000 $45,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 $2,000.000 $1.000 $5.000 $740.000 $1,000.000 $1,250.000 $15,000.000
666 6035 REFL PAV MRK TY I (W)8"(SLD)(090MIL) LF 14,800.000 $0.850 $0.615 $0.600 $0.740 $0.620 $0.650 $4.000
666 6299 RE PM W/RET REQ TY I (W)4"(BRK)(090MIL) LF 45,800.000 $0.340 $0.240 $0.360 $0.230 $0.280 $0.300 $0.700
666 6302 RE PM W/RET REQ TY I (W)4"(SLD)(090MIL) LF 335,100.000 $0.290 $0.205 $0.220 $0.228 $0.250 $0.290 $0.650
666 6311 RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL) LF 19,880.000 $0.330 $0.250 $0.360 $0.230 $0.280 $0.300 $0.700
666 6314 RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL) LF 339,600.000 $0.310 $0.205 $0.220 $0.228 $0.250 $0.290 $0.650
666 6359 REFL PAV MRK TY II (B) 5" (SLD)(100MIL) LF 5,580.000 $1.050 $0.010 $0.500 $0.800 $1.000 $0.250 $0.500
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 264.000 $12.000 $9.350 $13.000 $15.000 $10.000 $13.000 $12.000
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 110.000 $185.000 $150.000 $168.650 $210.000 $200.000 $207.000 $400.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 57.000 $230.000 $265.000 $203.750 $280.000 $225.000 $274.000 $400.000
668 6092 PREFAB PAV MRK TY C (W) (36")(YLD TRI) EA 368.000 $28.000 $33.750 $22.500 $38.000 $40.000 $50.000 $250.000
Totals: $311,113.40 $209,929.70 $225,641.05 $247,338.00 $271,006.40 $292,302.00 $783,489.00