SMITH SH 64 (0245-06-087)

Items: 91

County: SMITH
Length: N/A
Highway: SH 64
District: TYLER
Control Number: 0245-06-087
DBE Goal: N/A
Project: STP 2022(809)HES
Guaranty: N/A
Time: 115 WORKING DAYS
Engineer's Estimate: $1,767,279.58
Date: 08/03/2022 (3 years ago)
Contract Number: N/A
Type: INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT T
Mail/Deliver Bids To: N/A
PAUL SCHNEIDER
TRAVIS SINGLETON
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,767,279.58
$2,208,247.24
Over/Under Est: 24.95% $440,967.66
$2,213,322.79
Over/Under Est: 25.24% $446,043.21
Amt Left: 0.23% $5,075.55
Over/Under Est: 46.19% $816,280.42
Amt Left: 17% $375,312.76
Delta: -16.73% -$370,237.21
Over/Under Est: 48.1% $849,987.26
Amt Left: 18.52% $409,019.60
Delta: -1.30% -$33,706.84
Subcontractor Percentage Amount
STRIPING TECHNOLOGY, L.P. 1.94% $42,840.00
J.C. JOHNSON CONSTRUCTION 1.88% $41,515.05
ISAACS CONSTRUCTION SERVICES LLC 0.98% $21,640.82
CAP RIVER LLC 0.72% $15,899.38
PANOLA SIGN & BARRICADE, INC. 0.46% $10,157.94
PINNACLE GRINDING AND GROOVING LLC 0.39% $8,612.16
SOUTHWEST ENVIRONMENT SERVICES LLC 0.30% $6,624.74
Total: 6.67% $147,290.09

Bid Items & Bid Tabulations

91 Total 0 of 91
SMITH  |  SH 64  |  TYLER  |  0245-06-087  |  08/03/2022  |  $1,767,279.58  |  STP 2022(809)HES  |  INTERS IMPRVS WITH RIGHT AND/OR LEFT...  |  115 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
L. S. EQUIPMENT CO., INC.
REYNOLDS & KAY, LTD.
EAST TEXAS BRIDGE, INC.
TEXAS MATERIALS GROUP, INC.
PREPARING ROW
STA 10.000 $1,000.000 $1,560.000 $2,100.000 $15,000.000 $10,000.000
EXCAVATION (ROADWAY)
CY 4,900.000 $8.000 $12.000 $8.000 $10.000 $9.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 5,451.000 $26.000 $20.000 $4.000 $18.000 $19.000
BLADING
STA 32.700 $200.000 $125.000 $150.000 $300.000 $200.000
FURNISHING AND PLACING TOPSOIL (4")
SY 10,883.000 $2.000 $1.000 $2.000 $1.500 $1.350
BLOCK SODDING
SY 100.000 $10.000 $5.000 $7.500 $10.000 $11.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 5,442.000 $0.200 $0.400 $0.150 $0.250 $0.550
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 10,883.000 $0.850 $0.750 $0.850 $0.800 $0.780
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 5,442.000 $0.650 $0.750 $0.800 $0.800 $0.750
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 5,442.000 $0.650 $0.750 $0.800 $0.800 $0.750
VEGETATIVE WATERING
MG 299.000 $11.500 $0.010 $5.000 $25.000 $36.000
LIME (HYDRATED LIME (DRY))
TON 43.000 $220.000 $300.000 $300.000 $500.000 $265.000
LIME TRT (EXST MATL)(8")
SY 2,882.000 $4.000 $6.000 $8.000 $10.000 $10.000
CEMENT
TON 49.000 $180.000 $600.000 $255.000 $300.000 $235.000
CEMENT TREAT(EXIST MATL)(8")
SY 2,882.000 $4.000 $5.000 $6.500 $8.000 $6.000
EMULS ASPH (EROSN CONT)(CSS-1)
GAL 435.000 $3.700 $5.000 $6.000 $7.000 $4.450
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 7,838.000 $3.050 $6.000 $5.000 $5.000 $6.550
AGGR (TY-PD GR-3 OR TY-PL GR-3)
CY 187.000 $111.000 $150.000 $165.000 $135.000 $130.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 1,000.000 $56.000 $4.000 $72.000 $65.000 $66.000
PLANE ASPH CONC PAV(0" TO 2")
SY 1,600.000 $5.000 $5.000 $6.500 $6.000 $3.250
PLANE ASPH CONC PAV (2")
SY 2,499.000 $2.200 $4.000 $7.500 $6.000 $4.450
CL C CONC (COLLAR)
EA 3.000 $1,200.000 $1,800.000 $1,000.000 $1,500.000 $1,540.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 310.000 $140.000 $200.000 $135.000 $225.000 $185.000
CONC BOX CULV (7 FT X 4 FT)(EXTEND)
LF 34.000 $600.000 $950.000 $800.000 $1,000.000 $855.000
RC PIPE (CL III)(18 IN)
LF 378.000 $55.000 $60.000 $55.000 $55.000 $55.000
RC PIPE (CL III)(24 IN)
LF 70.000 $70.000 $130.000 $75.000 $75.000 $125.000
RC PIPE (CL III)(30 IN)
LF 6.000 $90.000 $300.000 $130.000 $100.000 $206.000
RC PIPE (CL III)(36 IN)
LF 42.000 $101.000 $275.000 $150.000 $150.000 $235.000
HEADWALL (CH - FW - 0) (DIA= 30 IN)
EA 1.000 $4,750.000 $8,500.000 $5,000.000 $5,000.000 $6,300.000
WINGWALL (PW - 2) (HW=6 FT)
EA 1.000 $10,000.000 $15,000.000 $22,000.000 $10,000.000 $11,500.000
SET (TY I)(S= 7 FT)(HW= 5 FT)(4:1) (C)
EA 1.000 $10,140.000 $15,000.000 $16,000.000 $10,000.000 $12,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 24.000 $650.000 $995.000 $950.000 $750.000 $900.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 4.000 $1,400.000 $1,200.000 $1,500.000 $1,200.000 $1,035.000
SET (TY II) (30 IN) (RCP) (6: 1) (C)
EA 1.000 $2,000.000 $2,990.000 $2,300.000 $2,000.000 $2,650.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 1.000 $4,000.000 $4,000.000 $2,500.000 $2,500.000 $3,200.000
SET (TY II) (36 IN) (RCP) (6: 1) (C)
EA 1.000 $4,500.000 $5,000.000 $4,500.000 $3,300.000 $3,700.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 2.000 $4,500.000 $4,900.000 $4,500.000 $5,500.000 $4,250.000
CLEAN EXIST CULVERTS
EA 1.000 $2,000.000 $1,000.000 $2,300.000 $2,000.000 $1,650.000
REMOV STR (PIPE)
EA 13.000 $250.000 $500.000 $500.000 $1,000.000 $650.000
MOBILIZATION
LS 1.000 $89,054.300 $95,950.000 $263,500.000 $250,000.000 $260,003.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $5,000.000 $2,000.000 $4,500.000 $15,000.000 $39,769.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 240.000 $28.000 $50.000 $30.000 $35.000 $31.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 120.000 $32.000 $35.000 $36.000 $40.000 $37.000
ROCK FILTER DAMS (REMOVE)
LF 360.000 $10.500 $15.000 $8.000 $8.000 $11.000
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
CY 100.000 $20.000 $150.000 $15.000 $50.000 $6.250
BACKHOE WORK (EROSION & SEDMT CONT)
HR 100.000 $75.000 $125.000 $60.000 $65.000 $1.050
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,500.000 $3.000 $3.500 $3.000 $4.000 $3.250
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,500.000 $1.500 $1.000 $0.500 $0.500 $1.050
TRACKHOE WORK (EROSION & SEDMT CONT)
HR 100.000 $95.000 $125.000 $100.000 $85.000 $0.110
INTERSECTIONS (ACP)
SY 194.000 $38.000 $45.000 $57.510 $65.000 $44.000
DRIVEWAYS (ACP)
SY 1,442.000 $40.000 $55.000 $44.620 $45.000 $49.000
TURNOUTS (ACP)
SY 22.000 $75.000 $55.000 $79.980 $100.000 $44.000
RUMBLE STRIPS (SHOULDER)
LF 6,128.000 $0.200 $1.000 $0.850 $1.000 $0.520
RUMBLE STRIPS (CENTERLINE)
LF 3,064.000 $0.200 $1.000 $1.000 $1.000 $0.520
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 12.000 $250.000 $300.000 $405.000 $400.000 $365.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 3.000 $260.000 $350.000 $450.000 $500.000 $420.000
MAILBOX INSTALL-M (TWG-POST) TY 2
EA 4.000 $425.000 $500.000 $830.000 $700.000 $740.000
CONDT (PVC) (SCH 40) (2")
LF 40.000 $10.000 $20.000 $23.000 $25.000 $22.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $625.000 $1,000.000 $950.000 $1,200.000 $900.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 5.000 $300.000 $500.000 $540.000 $900.000 $500.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 1.000 $440.000 $500.000 $700.000 $1,000.000 $640.000
REMOVE SM RD SN SUP&AM
EA 10.000 $82.000 $200.000 $120.000 $150.000 $115.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 8.000 $55.000 $150.000 $85.000 $200.000 $82.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 6,530.000 $0.150 $0.500 $0.550 $0.550 $0.550
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 2,530.000 $0.300 $0.500 $0.550 $0.550 $0.550
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 105.000 $3.600 $5.000 $4.500 $5.000 $4.350
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 8,596.000 $0.200 $0.600 $0.550 $0.550 $0.550
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 105.000 $7.000 $16.000 $9.000 $9.000 $8.250
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 127.000 $0.820 $1.500 $1.150 $2.000 $1.080
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 860.000 $0.550 $1.500 $1.150 $2.000 $1.080
WK ZN PAV MRK SHT TERM RMV (W)(4")
LF 567.000 $1.450 $3.000 $1.450 $2.000 $1.050
WK ZN PAV MRK SHT TERM RMV (Y)(4")
LF 1,935.000 $1.300 $3.000 $1.450 $2.000 $1.050
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,530.000 $0.750 $1.100 $1.150 $1.100 $1.050
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 6,530.000 $0.350 $1.100 $1.150 $1.100 $1.050
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 8,596.000 $0.400 $1.100 $1.150 $1.100 $1.050
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 105.000 $12.000 $16.000 $17.000 $20.000 $16.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 10.000 $180.000 $250.000 $260.000 $300.000 $245.000
PREFAB PAV MRK TY C (W) (WORD)
EA 10.000 $260.000 $300.000 $295.000 $300.000 $265.000
PREFAB PAV MRK TY C (Y) (4") (SLD)
LF 300.000 $2.000 $5.000 $5.500 $6.000 $5.250
REFL PAV MRKR TY I-C
EA 127.000 $3.720 $5.000 $4.500 $5.000 $4.250
REFL PAV MRKR TY II-A-A
EA 430.000 $3.150 $5.000 $4.500 $5.000 $4.250
TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
LF 40.000 $2.200 $20.000 $7.000 $7.000 $6.350
RELOCATE RDSD FLASH BEACON ASSEMBLY
EA 2.000 $3,500.000 $2,500.000 $2,400.000 $3,000.000 $2,100.000
SP MIXES SP-B PG64-22
TON 4,197.000 $100.000 $150.000 $143.000 $145.000 $136.000
SP MIXES SP-C PG64-22
TON 843.000 $100.000 $160.000 $147.000 $147.000 $143.000
SP MIXES SP-C SAC-A PG70-22
TON 2,053.000 $108.000 $170.000 $160.000 $160.000 $155.000
SP MIXES SP-D PG64-22 (LEVEL-UP)
TON 386.000 $150.000 $175.000 $155.000 $170.000 $180.000
TACK COAT
GAL 2,233.000 $3.600 $5.000 $4.750 $5.000 $4.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 134.000 $102.000 $92.000 $85.000 $150.000 $60.000
TMA (STATIONARY)
DAY 50.000 $200.000 $178.000 $90.000 $300.000 $295.000
TMA (MOBILE OPERATION)
DAY 20.000 $5,000.000 $223.000 $85.000 $300.000 $245.000
Totals: $1,767,279.580 $2,208,247.240 $2,213,322.790 $2,583,560.000 $2,617,266.840