PREPARING ROW
|
STA
|
12.000
|
$1,200.000
|
$1,000.000
|
$2,500.000
|
$4,370.000
|
$1,000.000
|
|
|
REMOVING CONC (SIDEWALKS)
|
SY
|
50.000
|
$25.000
|
$100.000
|
$40.000
|
$92.000
|
$50.000
|
|
|
REMOVING CONC (CURB AND GUTTER)
|
LF
|
463.000
|
$21.000
|
$20.000
|
$24.000
|
$86.000
|
$20.000
|
|
|
REMOVING CONC (FLUME)
|
SY
|
6.000
|
$50.000
|
$100.000
|
$500.000
|
$115.000
|
$100.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY C)
|
CY
|
27.000
|
$20.000
|
$55.000
|
$50.000
|
$400.000
|
$55.000
|
|
|
BLOCK SODDING
|
SY
|
456.000
|
$4.500
|
$15.000
|
$8.000
|
$18.000
|
$12.000
|
|
|
DRILL SHAFT (TRF SIG POLE) (30 IN)
|
LF
|
55.000
|
$394.000
|
$325.000
|
$280.000
|
$340.000
|
$322.000
|
|
|
DRILL SHAFT (TRF SIG POLE) (36 IN)
|
LF
|
104.000
|
$442.000
|
$375.000
|
$300.000
|
$450.000
|
$328.000
|
|
|
DRILL SHAFT (TRF SIG POLE) (48 IN)
|
LF
|
22.000
|
$618.000
|
$750.000
|
$850.000
|
$600.000
|
$985.000
|
|
|
CL A CONC (MISC)
|
CY
|
2.000
|
$700.000
|
$1,000.000
|
$477.000
|
$3,450.000
|
$2,000.000
|
|
|
CL A CONC (FLUME)
|
CY
|
1.000
|
$620.000
|
$1,000.000
|
$770.000
|
$3,450.000
|
$2,000.000
|
|
|
RIPRAP (CONC)(6 IN)
|
CY
|
6.000
|
$450.000
|
$250.000
|
$350.000
|
$1,725.000
|
$2,000.000
|
|
|
GRATE & FRAME
|
EA
|
1.000
|
$1,860.000
|
$5,000.000
|
$3,500.000
|
$2,875.000
|
$5,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$140,155.000
|
$100,000.000
|
$135,000.000
|
$195,500.000
|
$399,500.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
7.000
|
$6,000.000
|
$5,000.000
|
$4,000.000
|
$6,254.000
|
$3,000.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
138.000
|
$2.000
|
$25.000
|
$20.000
|
$18.000
|
$19.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
138.000
|
$1.420
|
$25.000
|
$20.000
|
$8.000
|
$8.000
|
|
|
COLORED TEXTURED CONC (4")
|
SY
|
118.000
|
$100.000
|
$250.000
|
$340.000
|
$195.000
|
$250.000
|
|
|
CONC CURB & GUTTER (TY II)
|
LF
|
557.000
|
$65.000
|
$70.000
|
$47.000
|
$115.000
|
$75.000
|
|
|
CONC SIDEWALKS (6")
|
SY
|
336.000
|
$110.000
|
$100.000
|
$90.000
|
$207.000
|
$250.000
|
|
|
CURB RAMPS (TY 1)
|
EA
|
5.000
|
$2,300.000
|
$3,500.000
|
$2,000.000
|
$5,175.000
|
$5,000.000
|
|
|
CURB RAMPS (TY 5)
|
EA
|
4.000
|
$4,200.000
|
$4,000.000
|
$1,800.000
|
$5,750.000
|
$9,000.000
|
|
|
CURB RAMPS (TY 7)
|
EA
|
10.000
|
$2,600.000
|
$3,500.000
|
$1,899.000
|
$4,830.000
|
$5,000.000
|
|
|
CURB RAMPS (TY 22)
|
EA
|
3.000
|
$2,600.000
|
$4,500.000
|
$1,899.000
|
$7,475.000
|
$5,000.000
|
|
|
CONCRETE MEDIAN (NOSE)
|
SY
|
10.000
|
$245.000
|
$800.000
|
$500.000
|
$230.000
|
$800.000
|
|
|
IN RD IL (TY SA) 30T-8 (250W EQ) LED
|
EA
|
1.000
|
$5,098.000
|
$4,255.000
|
$5,999.000
|
$6,125.000
|
$6,670.000
|
|
|
CONDT (PVC) (SCH 80) (2")
|
LF
|
400.000
|
$20.000
|
$13.000
|
$10.000
|
$23.000
|
$10.000
|
|
|
CONDT (PVC) (SCH 80) (2") (BORE)
|
LF
|
595.000
|
$34.000
|
$30.000
|
$22.000
|
$36.000
|
$22.000
|
|
|
CONDT (PVC) (SCH 80) (3")
|
LF
|
375.000
|
$31.000
|
$20.000
|
$15.000
|
$25.000
|
$14.500
|
|
|
CONDT (PVC) (SCH 80) (4")
|
LF
|
40.000
|
$32.000
|
$30.000
|
$21.000
|
$34.000
|
$23.000
|
|
|
CONDT (PVC) (SCH 80) (4") (BORE)
|
LF
|
1,195.000
|
$43.000
|
$45.000
|
$45.000
|
$46.000
|
$46.000
|
|
|
ELEC CONDR (NO.12) INSULATED
|
LF
|
2,390.000
|
$1.900
|
$0.850
|
$3.000
|
$3.000
|
$2.500
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
3,590.000
|
$2.100
|
$2.000
|
$4.000
|
$4.000
|
$2.500
|
|
|
ELEC CONDR (NO.6) BARE
|
LF
|
2,520.000
|
$2.700
|
$1.900
|
$3.300
|
$4.000
|
$2.500
|
|
|
ELEC CONDR (NO.6) INSULATED
|
LF
|
130.000
|
$2.700
|
$2.900
|
$3.500
|
$4.000
|
$3.000
|
|
|
GROUND BOX TY D (162922)W/APRON
|
EA
|
20.000
|
$1,612.000
|
$1,250.000
|
$1,510.000
|
$1,850.000
|
$1,450.000
|
|
|
ELC SRV TY D 120/240 070(NS)SS(E)PS(U)
|
EA
|
2.000
|
$12,261.000
|
$8,000.000
|
$8,000.000
|
$8,336.000
|
$8,600.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
1.000
|
$100.000
|
$665.000
|
$1,000.000
|
$1,000.000
|
$850.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
15.000
|
$600.000
|
$745.000
|
$1,000.000
|
$1,200.000
|
$885.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
1.000
|
$200.000
|
$1,020.000
|
$1,050.000
|
$1,650.000
|
$1,400.000
|
|
|
IN SM RD SN SUP&AM TYS80(2)SA(T-2EXT)
|
EA
|
1.000
|
$900.000
|
$2,045.000
|
$3,000.000
|
$2,850.000
|
$2,755.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
9.000
|
$130.000
|
$135.000
|
$100.000
|
$285.000
|
$130.000
|
|
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
|
LF
|
245.000
|
$2.120
|
$5.630
|
$4.000
|
$3.000
|
$3.500
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
3,320.000
|
$1.700
|
$2.200
|
$2.000
|
$3.000
|
$1.250
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
1,113.000
|
$10.000
|
$13.850
|
$8.000
|
$8.000
|
$7.000
|
|
|
PAVEMENT SEALER (ARROW)
|
EA
|
16.000
|
$260.000
|
$77.000
|
$177.000
|
$115.000
|
$115.000
|
|
|
PAVEMENT SEALER (WORD)
|
EA
|
16.000
|
$200.000
|
$85.000
|
$222.000
|
$130.000
|
$173.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
403.000
|
$3.000
|
$3.000
|
$3.000
|
$3.000
|
$2.300
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
|
LF
|
2,800.000
|
$1.500
|
$2.750
|
$2.000
|
$3.000
|
$2.000
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
4,435.000
|
$1.500
|
$1.700
|
$2.000
|
$3.000
|
$2.000
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
16.000
|
$525.000
|
$360.000
|
$333.000
|
$340.000
|
$250.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
16.000
|
$428.000
|
$425.000
|
$333.000
|
$480.000
|
$322.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
246.000
|
$8.000
|
$11.300
|
$12.000
|
$6.000
|
$7.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
222.000
|
$10.000
|
$11.300
|
$12.000
|
$6.000
|
$7.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
325.000
|
$1.150
|
$3.000
|
$3.000
|
$1.000
|
$2.300
|
|
|
ELIM EXT PAV MRK & MRKS (6")
|
LF
|
7,079.000
|
$1.000
|
$1.000
|
$1.000
|
$1.000
|
$1.150
|
|
|
ELIM EXT PAV MRK & MRKS (8")
|
LF
|
3,348.000
|
$2.000
|
$2.000
|
$1.000
|
$1.000
|
$1.150
|
|
|
ELIM EXT PAV MRK & MRKS (24")
|
LF
|
1,164.000
|
$4.000
|
$6.000
|
$3.000
|
$1.500
|
$3.500
|
|
|
ELIM EXT PAV MRK & MRKS (ARROW)
|
EA
|
22.000
|
$90.000
|
$80.000
|
$200.000
|
$54.000
|
$115.000
|
|
|
ELIM EXT PAV MRK & MRKS (WORD)
|
EA
|
12.000
|
$25.000
|
$90.000
|
$111.000
|
$68.000
|
$115.000
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
403.000
|
$0.200
|
$0.500
|
$0.500
|
$1.000
|
$0.230
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
245.000
|
$0.500
|
$1.000
|
$0.500
|
$1.000
|
$0.230
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
3,320.000
|
$0.600
|
$1.000
|
$0.500
|
$1.000
|
$0.400
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
1,113.000
|
$1.500
|
$3.000
|
$1.000
|
$1.000
|
$0.850
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
16.000
|
$115.000
|
$60.000
|
$100.000
|
$35.000
|
$58.000
|
|
|
PAV SURF PREP FOR MRK (WORD)
|
EA
|
16.000
|
$135.000
|
$65.000
|
$88.000
|
$41.000
|
$58.000
|
|
|
INSTALL HWY TRF SIG (ISOLATED)
|
EA
|
3.000
|
$30,989.000
|
$23,000.000
|
$46,970.000
|
$52,050.000
|
$44,850.000
|
|
|
REMOVING TRAFFIC SIGNALS
|
EA
|
3.000
|
$9,833.000
|
$5,000.000
|
$6,000.000
|
$7,200.000
|
$5,865.000
|
|
|
VEH SIG SEC (12")LED(GRN)
|
EA
|
25.000
|
$299.000
|
$290.000
|
$370.000
|
$405.000
|
$345.000
|
|
|
VEH SIG SEC (12")LED(GRN ARW)
|
EA
|
11.000
|
$301.000
|
$290.000
|
$380.000
|
$405.000
|
$345.000
|
|
|
VEH SIG SEC (12")LED(YEL)
|
EA
|
27.000
|
$306.000
|
$290.000
|
$380.000
|
$405.000
|
$345.000
|
|
|
VEH SIG SEC (12")LED(YEL ARW)
|
EA
|
21.000
|
$300.000
|
$290.000
|
$380.000
|
$405.000
|
$345.000
|
|
|
VEH SIG SEC (12")LED(RED)
|
EA
|
25.000
|
$308.000
|
$290.000
|
$380.000
|
$405.000
|
$345.000
|
|
|
VEH SIG SEC (12")LED(RED ARW)
|
EA
|
10.000
|
$309.000
|
$290.000
|
$300.000
|
$405.000
|
$345.000
|
|
|
PED SIG SEC (LED)(COUNTDOWN)
|
EA
|
24.000
|
$796.000
|
$700.000
|
$999.000
|
$784.000
|
$1,050.000
|
|
|
BACKPLATE W/REFL BRDR(3 SEC)ALUM
|
EA
|
24.000
|
$218.000
|
$150.000
|
$250.000
|
$258.000
|
$219.000
|
|
|
BACKPLATE W/REFL BRDR(4 SEC)ALUM
|
EA
|
10.000
|
$266.000
|
$250.000
|
$260.000
|
$285.000
|
$241.000
|
|
|
BACKPLATE W/REFL BRDR(5 SEC)ALUM
|
EA
|
1.000
|
$495.000
|
$250.000
|
$280.000
|
$320.000
|
$265.000
|
|
|
TRF SIG CBL (TY A)(14 AWG)(5 CONDR)
|
LF
|
1,980.000
|
$3.400
|
$2.250
|
$6.000
|
$3.500
|
$3.750
|
|
|
TRF SIG CBL (TY A)(14 AWG)(7 CONDR)
|
LF
|
650.000
|
$3.700
|
$2.950
|
$5.000
|
$4.000
|
$3.750
|
|
|
TRF SIG CBL (TY A)(14 AWG)(20 CONDR)
|
LF
|
1,710.000
|
$6.700
|
$5.250
|
$6.000
|
$4.500
|
$3.750
|
|
|
TRF SIG CBL (TY C)(12 AWG)(2 CONDR)
|
LF
|
3,250.000
|
$2.400
|
$2.000
|
$6.000
|
$3.500
|
$3.750
|
|
|
INS TRF SIG PL AM(S)1 ARM(24')LUM
|
EA
|
1.000
|
$11,350.000
|
$12,460.000
|
$11,211.000
|
$12,500.000
|
$12,000.000
|
|
|
INS TRF SIG PL AM (S)1 ARM(28')
|
EA
|
1.000
|
$9,605.000
|
$10,400.000
|
$12,344.000
|
$10,500.000
|
$12,700.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(32')LUM
|
EA
|
2.000
|
$12,612.000
|
$13,270.000
|
$13,440.000
|
$12,900.000
|
$13,685.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(36')LUM
|
EA
|
1.000
|
$13,966.000
|
$13,930.000
|
$15,000.000
|
$13,800.000
|
$14,950.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(40')LUM
|
EA
|
2.000
|
$15,299.000
|
$14,500.000
|
$29,000.000
|
$14,600.000
|
$28,750.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(44')
|
EA
|
1.000
|
$14,144.000
|
$12,380.000
|
$35,000.000
|
$13,500.000
|
$35,000.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(44')LUM
|
EA
|
4.000
|
$17,121.000
|
$14,750.000
|
$39,000.000
|
$15,400.000
|
$38,000.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(50')LUM
|
EA
|
1.000
|
$36,727.000
|
$34,700.000
|
$40,111.000
|
$34,650.000
|
$40,250.000
|
|
|
PED POLE ASSEMBLY
|
EA
|
19.000
|
$3,574.000
|
$2,500.000
|
$4,500.000
|
$2,233.000
|
$2,900.000
|
|
|
PED DETECT PUSH BUTTON (APS)
|
EA
|
24.000
|
$1,138.000
|
$1,500.000
|
$3,007.000
|
$858.000
|
$2,900.000
|
|
|
PED DETECTOR CONTROLLER UNIT
|
EA
|
3.000
|
$4,102.000
|
$3,500.000
|
$4,222.000
|
$3,928.000
|
$2,900.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
30.000
|
$104.000
|
$200.000
|
$1.000
|
$205.000
|
$250.000
|
|
|
BBU SYSTEM (EXTERNAL BATT CABINET)
|
EA
|
3.000
|
$9,422.000
|
$7,300.000
|
$7,500.000
|
$7,225.000
|
$7,475.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
7.000
|
$315.000
|
$200.000
|
$800.000
|
$315.000
|
$400.000
|
|
|
VIVDS PROSR SYS
|
EA
|
3.000
|
$12,447.000
|
$10,500.000
|
$15,250.000
|
$14,625.000
|
$15,800.000
|
|
|
VIVDS CAM ASSY FXD LNS
|
EA
|
12.000
|
$4,314.000
|
$4,500.000
|
$8,800.000
|
$6,850.000
|
$8,300.000
|
|
|
VIVDS CNTRL SOFTWARE
|
EA
|
3.000
|
$802.000
|
$1,000.000
|
$1,477.000
|
$15.000
|
$605.000
|
|
|
VIVDS CABLING
|
LF
|
2,375.000
|
$3.100
|
$5.000
|
$6.770
|
$3.000
|
$5.000
|
|
|
LEAD LED CHEVRON
|
EA
|
2.000
|
$3,500.000
|
$7,280.000
|
$2,700.000
|
$3,220.000
|
$11,500.000
|
|
|
LED CHEVRON
|
EA
|
24.000
|
$2,500.000
|
$4,500.000
|
$2,000.000
|
$2,740.000
|
$4,300.000
|
|
Totals: |
$1,449,885.710
|
$1,416,148.300
|
$1,757,145.750
|
$1,832,242.000
|
$2,143,499.040
|