County: SHELBY Highway: FM0414 Date: 03/22/2022 (2 years ago) Engineer's Estimate: $257,292 Control Number: 6397-54-001
Project: MMC - 639754001 District: LUFKIN Time: 120 CALENDAR DAYS Type: AGGREGATE
HCS
Plans

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $257,292.00
TOUCHSTONE RESOURCES, LLC   $320,850.00 1
24.7% | $63,558.00

Bid Items

Items: 7, 0 filtered
SHELBY FM0414  |  LUFKIN  |  6397-54-001  |  03/22/2022  |  $257,292  |  MMC - 639754001  |  AGGREGATE  |  120 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate TOUCHSTONE RESOURCES, LLC
8039 6184 AGGR (TY L GR 3) (DEL) (ST2) TON 400.000 $122.520 $150.000
8039 6185 AGGR (TY L GR 3) (DEL) (ST3) TON 225.000 $122.520 $154.000
8039 6186 AGGR (TY L GR 3) (DEL) (ST4) TON 300.000 $122.520 $155.000
8039 6197 AGGR (TY L GR 4) (DEL) (ST1) TON 450.000 $122.520 $155.000
8039 6198 AGGR (TY L GR 4) (DEL) (ST2) TON 400.000 $122.520 $150.000
8039 6199 AGGR (TY L GR 4) (DEL) (ST3) TON 225.000 $122.520 $154.000
8039 6201 AGGR (TY L GR 4) (DEL) (ST5) TON 100.000 $122.520 $153.000
Totals: $257,292.00 $320,850.00