Job Info for 0911-39-069

County: SHELBY Highway: CR Date: 06/06/2024 (5 months ago) Engineer's Estimate: $703,110 Control Number: 0911-39-069
Project: BR 2B23(045) District: LUFKIN Time: 103 WORKING DAYS Type: BRIDGE REPLACEMENT
Bidder's List
Informational:
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $703,110.00
THK CONSTRUCTION LLC   $584,994.70 1
-16.8% | -$118,115.30
SKYLINE BRIDGE LLC   $687,267.00 2
-2.25% | -$15,843.00
17.48% | $102,272.30
TALBERT COMPANIES LLC   $790,118.24 3
12.37% | $87,008.24
35.06% | $205,123.54
14.97% | $102,851.24
EAST TEXAS BRIDGE, INC.   $834,226.00 4
18.65% | $131,116.00
42.6% | $249,231.30
5.58% | $44,107.76
DREWERY CONSTRUCTION COMPANY, INCORPORATED   $868,292.60 5
23.49% | $165,182.60
48.43% | $283,297.90
4.08% | $34,066.60
DCC CONSTRUCTION AND SERVICES, L.L.C.   $890,884.00 6
26.71% | $187,774.00
52.29% | $305,889.30
2.60% | $22,591.40
Subcontractor Percentage Amount
HODGES AND SON CONSTRUCTION COMPANY, INC. 16.26% $95,120.14
MORRIS COUNTY CONTRACTORS, L.L.C. 4.36% $25,505.77
J. H. ODEN CONTRACTING COMPANY 1.74% $10,178.91
PANOLA SIGN & BARRICADE, INC. 1.12% $6,551.94
Total: 23.48% $137,356.76

Bid Items

Items: 31, 0 filtered
SHELBY CR  |  LUFKIN  |  0911-39-069  |  06/06/2024  |  $703,110  |  BR 2B23(045)  |  BRIDGE REPL  |  103 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate THK CONSTRUCTION LLC SKYLINE BRIDGE LLC TALBERT COMPANIES LLC EAST TEXAS BRIDGE, INC. DREWERY CONSTRUCTION COMPANY, INCORPORATED DCC CONSTRUCTION AND SERVICES, L.L.C.
100 6002 PREPARING ROW STA 6.500 $5,000.000 $1,500.000 $4,000.000 $2,737.500 $8,000.000 $420.000 $2,000.000
110 6001 EXCAVATION (ROADWAY) CY 191.000 $30.000 $15.000 $22.000 $54.750 $40.000 $48.000 $30.000
132 6003 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 280.000 $60.000 $15.000 $35.000 $54.750 $50.000 $37.000 $35.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 924.000 $5.500 $3.500 $5.000 $6.710 $7.000 $6.700 $4.000
164 6054 BOND FBR MTRX SEED (PERM)(RURAL)(SAND) SY 924.000 $2.000 $3.150 $3.500 $1.100 $2.500 $2.850 $5.000
164 6055 BONDED FBR MTRX SEED (TEMP)(WARM) SY 462.000 $2.000 $0.010 $2.500 $1.100 $2.000 $2.850 $5.000
164 6056 BONDED FBR MTRX SEED (TEMP)(COOL) SY 462.000 $2.000 $0.010 $2.500 $1.100 $2.000 $2.850 $5.000
168 6001 VEGETATIVE WATERING MG 37.000 $20.000 $20.000 $1.000 $136.880 $50.000 $130.000 $20.000
247 6073 FL BS (CMP IN PLC)(TY D GR 1-2) (6") SY 1,474.000 $50.000 $34.250 $48.500 $71.180 $65.000 $46.000 $65.000
400 6005 CEM STABIL BKFL CY 48.000 $275.000 $400.000 $300.000 $246.380 $350.000 $295.000 $325.000
416 6002 DRILL SHAFT (24 IN) LF 423.000 $300.000 $278.450 $350.000 $246.380 $300.000 $320.000 $325.000
420 6013 CL C CONC (ABUT) CY 20.400 $2,000.000 $1,100.000 $1,100.000 $1,177.130 $2,100.000 $2,000.000 $2,500.000
420 6029 CL C CONC (CAP) CY 6.600 $2,000.000 $1,500.000 $1,800.000 $1,259.250 $2,500.000 $2,500.000 $2,500.000
420 6037 CL C CONC (COLUMN) CY 1.400 $2,000.000 $3,714.290 $5,000.000 $1,204.500 $3,000.000 $3,400.000 $2,500.000
422 6007 REINF CONC SLAB (SLAB BEAM) SF 2,600.000 $30.000 $24.000 $24.000 $24.910 $30.000 $40.000 $24.000
425 6012 PRESTR CONC SLAB BEAM (5SB15) LF 495.000 $215.000 $285.000 $300.000 $220.640 $300.000 $318.000 $350.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 118.000 $250.000 $252.720 $250.000 $355.880 $275.000 $260.000 $250.000
450 6019 RAIL (TY T631LS) LF 224.000 $75.000 $68.250 $85.000 $82.130 $85.000 $79.000 $125.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 1.000 $25,000.000 $5,000.000 $10,000.000 $27,375.000 $30,000.000 $34,000.000 $40,000.000
500 6001 MOBILIZATION LS 1.000 $70,000.000 $55,000.000 $60,000.000 $90,000.000 $85,000.000 $170,000.000 $125,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 $3,000.000 $988.130 $1,500.000 $14,371.880 $3,500.000 $1,755.000 $3,500.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 40.000 $45.000 $52.500 $50.000 $54.750 $55.000 $54.000 $200.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 40.000 $10.000 $21.000 $10.000 $21.900 $22.000 $16.000 $2.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,217.000 $4.000 $4.200 $3.500 $4.380 $5.000 $4.000 $17.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,217.000 $1.000 $0.580 $1.500 $0.600 $1.000 $2.000 $2.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 76.000 $32.000 $28.880 $30.000 $41.060 $33.000 $40.000 $40.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 2.000 $1,500.000 $1,417.500 $1,600.000 $1,697.250 $3,500.000 $1,600.000 $1,500.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 2.000 $3,500.000 $3,150.000 $3,500.000 $3,317.850 $3,500.000 $3,600.000 $4,000.000
644 6076 REMOVE SM RD SN SUP&AM EA 2.000 $180.000 $250.000 $250.000 $1,642.500 $150.000 $255.000 $250.000
658 6016 INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI) EA 4.000 $20.000 $21.000 $50.000 $32.850 $45.000 $24.000 $50.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 4.000 $20.000 $26.250 $50.000 $54.750 $50.000 $41.000 $50.000
Totals: $703,110.00 $584,994.71 $687,267.00 $790,118.24 $834,226.00 $868,292.60 $890,884.00