SHELBY CR (0911-39-063)
Items: 35
County: SHELBY
Length: N/A
Highway: CR
District: LUFKIN
Control Number: 0911-39-063
DBE Goal: N/A
Project: BR 2B20(125)
Guaranty: N/A
Time: 48 WORKING DAYS
Engineer's Estimate: $421,440.75
Date: 05/04/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$421,440.75 | |||
| $425,319.60 |
0.92%
$3,878.85
|
|||
| $444,459.52 |
5.46%
$23,018.77
|
4.5%
$19,139.92
|
||
| $499,923.90 |
18.62%
$78,483.15
|
17.54%
$74,604.30
|
-12.48%
-$55,464.38
|
|
| $500,942.25 |
18.86%
$79,501.50
|
17.78%
$75,622.65
|
-0.20%
-$1,018.35
|
|
| $546,351.00 |
29.64%
$124,910.25
|
28.46%
$121,031.40
|
-9.06%
-$45,408.75
|
|
| $566,628.30 |
34.45%
$145,187.55
|
33.22%
$141,308.70
|
-3.71%
-$20,277.30
|
|
| $599,727.95 |
42.3%
$178,287.20
|
41.01%
$174,408.35
|
-5.84%
-$33,099.65
|
|
| $678,947.15 |
61.1%
$257,506.40
|
59.63%
$253,627.55
|
-13.21%
-$79,219.20
|
E
Engineer's Estimate
$421,440.75
1
Awarded
$425,319.60
Over/Under Est:
0.92%
$3,878.85
$444,459.52
Over/Under Est:
5.46%
$23,018.77
Amt Left:
4.5%
$19,139.92
$499,923.90
Over/Under Est:
18.62%
$78,483.15
Amt Left:
17.54%
$74,604.30
Delta:
-12.48%
-$55,464.38
$500,942.25
Over/Under Est:
18.86%
$79,501.50
Amt Left:
17.78%
$75,622.65
Delta:
-0.20%
-$1,018.35
$546,351.00
Over/Under Est:
29.64%
$124,910.25
Amt Left:
28.46%
$121,031.40
Delta:
-9.06%
-$45,408.75
$566,628.30
Over/Under Est:
34.45%
$145,187.55
Amt Left:
33.22%
$141,308.70
Delta:
-3.71%
-$20,277.30
$599,727.95
Over/Under Est:
42.3%
$178,287.20
Amt Left:
41.01%
$174,408.35
Delta:
-5.84%
-$33,099.65
$678,947.15
Over/Under Est:
61.1%
$257,506.40
Amt Left:
59.63%
$253,627.55
Delta:
-13.21%
-$79,219.20
Bid Items & Bid Tabulations
35
Total
0 of 35