Job Info for 0059-05-045

County: SHELBY Highway: SH 7 Date: 11/06/2018 (6 years ago) Engineer's Estimate: $10,852,736 Control Number: 0059-05-045
Project: STP 2019(181) District: LUFKIN Time: 82 WORKING DAYS Type: RESURFACE WITH SEAL COAT

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $10,852,736.30
MISSOURI PETROLEUM PRODUCTS COMPANY LLC   $10,961,024.55 1
1% | $108,288.25
A. L. HELMCAMP, INC.   $11,782,725.17 2
8.57% | $929,988.87
7.5% | $821,700.62
CLARK CONSTRUCTION OF TEXAS, INC.   $12,213,502.55 3
12.54% | $1,360,766.25
11.43% | $1,252,478.00
3.66% | $430,777.38

Bid Items

Items: 36, 0 filtered
SHELBY SH 7  |  LUFKIN  |  0059-05-045  |  11/06/2018  |  $10,852,736  |  STP 2019(181)  |  RESURF WITH SEAL COAT  |  82 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate MISSOURI PETROLEUM PRODUCTS COMPANY LLC A. L. HELMCAMP, INC. CLARK CONSTRUCTION OF TEXAS, INC.
316 6035 ASPH (TIER I) TON 3,114.000 $675.000 $651.000 $745.000 $750.000
316 6036 ASPH (TIER II) TON 3,740.000 $675.000 $651.000 $735.000 $705.000
316 6404 AGGR (TY-PB GR-4 OR TY-PL GR-4 SAC-A) CY 5,616.000 $95.000 $115.000 $140.000 $118.000
316 6433 AGGR(TY PE,TY-PL,TY-E,TY-L GR-4)(SAC-B) CY 7,676.000 $85.000 $121.000 $140.000 $101.000
316 6434 AGGR (TY-PB GR-4 OR TY-PL GR-4 ( SAC-B) CY 8,727.000 $85.000 $105.000 $140.000 $118.000
316 6459 AGGR(TY-PE OR TY-PL)(GR-4)(SAC-B) CY 9,376.000 $85.000 $110.000 $140.000 $118.000
316 6477 AGGR (TY-PE OR PL)(GR-5)(SAC-B) CY 3,173.000 $85.000 $93.000 $130.000 $118.000
500 6001 MOBILIZATION LS 1.000 $1,200,000.000 $1,872,000.000 $885,000.000 $1,650,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $7,500.000 $1,000.000 $21,000.000 $12,500.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 500.000 $10.000 $3.000 $4.500 $0.010
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 500.000 $10.000 $3.000 $1.500 $0.010
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 6,291.000 $1.000 $0.600 $0.600 $1.500
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 94,029.000 $1.000 $0.600 $0.600 $0.450
666 6167 REFL PAV MRK TY II (W) 4" (BRK) LF 83,820.000 $0.350 $0.120 $0.110 $0.150
666 6170 REFL PAV MRK TY II (W) 4" (SLD) LF 2,073,343.000 $0.350 $0.110 $0.110 $0.150
666 6178 REFL PAV MRK TY II (W) 8" (SLD) LF 22,268.000 $1.000 $0.500 $0.260 $0.500
666 6205 REFL PAV MRK TY II (Y) 4" (BRK) LF 151,020.000 $0.350 $0.120 $0.110 $0.150
666 6207 REFL PAV MRK TY II (Y) 4" (SLD) LF 1,653,784.000 $0.350 $0.110 $0.110 $0.150
666 6224 PAVEMENT SEALER 4" LF 67,235.000 $0.350 $0.085 $0.320 $0.150
668 6075 PREFAB PAV MRK TY C (W) (18") (SLD) LF 357.000 $10.000 $8.490 $10.500 $5.500
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 5,596.000 $15.000 $11.000 $12.340 $11.000
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 92.000 $200.000 $190.000 $189.000 $200.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 78.000 $300.000 $295.000 $231.000 $265.000
668 6089 PREFAB PAV MRK TY C (W) (RR XING) EA 2.000 $500.000 $800.000 $787.500 $475.000
672 6007 REFL PAV MRKR TY I-C EA 2,754.000 $3.000 $2.390 $2.570 $3.000
672 6009 REFL PAV MRKR TY II-A-A EA 31,115.000 $3.000 $2.390 $2.570 $2.660
672 6010 REFL PAV MRKR TY II-C-R EA 1,895.000 $3.000 $2.390 $2.570 $3.000
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 285,681.000 $0.350 $0.160 $0.300 $0.800
677 6003 ELIM EXT PAV MRK & MRKS (8") LF 585.000 $0.450 $0.440 $2.000 $5.500
677 6007 ELIM EXT PAV MRK & MRKS (24") LF 8,808.000 $3.000 $1.800 $2.500 $4.000
677 6008 ELIM EXT PAV MRK & MRKS (ARROW) EA 92.000 $100.000 $31.000 $50.000 $185.000
677 6012 ELIM EXT PAV MRK & MRKS (WORD) EA 78.000 $100.000 $31.000 $50.000 $185.000
677 6016 ELIM EXT PAV MRK & MRKS (RR XING) EA 2.000 $250.000 $100.000 $50.000 $400.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $15,000.000 $6,000.000 $20,000.000 $5,000.000
6185 6001 TMA (STATIONARY) EA 2.000 $10,000.000 $8,000.000 $20,000.000 $5,000.000
6185 6005 TMA (MOBILE OPERATION) DAY 116.000 $235.000 $0.010 $100.000 $3,500.000
Totals: $10,852,736.30 $10,961,024.56 $11,782,725.17 $12,213,502.55