SCURRY US 180 (0053-17-037)

Items: 32

County: SCURRY
Length: 2.6590 MILES
Highway: US 180
District: ABILENE
Control Number: 0053-17-037
DBE Goal: 0.0%
Project: C 53-17-37
Guaranty: $46,000.00
Time: 51 WORKING DAYS
Engineer's Estimate: $2,299,725.00
Date: 09/06/2024 (1 year ago)
Contract Number: 9243226
Type: RESURFACE ROADWAY
Project ID: A00135521
Project Description: MILL AND OVERLAY
Mail/Deliver Bids To: N/A
ANTHONY BOUCHER
MAXIE ALLEN
JOSE CABRERA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$2,299,725.00
1
$2,179,456.14
Over/Under Est: -5.23% -$120,268.86
Over/Under Est: 11.67% $268,442.60
Amt Left: 17.84% $388,711.46
Subcontractor Percentage Amount
DOUBLE A CONTRACTING, L.P. 4.04% $88,050.03
HJC FARMS, INC. 3.00% $65,383.68
TEXOP CONSTRUCTION 1.30% $28,332.93
FC TRAFFIC CONTROL, INC. 0.88% $19,179.21
CHEROKEE SERVICES 0.56% $12,204.95
Total: 9.78% $213,150.80

Bid Items & Bid Tabulations

32 Total 0 of 32
SCURRY  |  US 180  |  ABILENE  |  0053-17-037  |  09/06/2024  |  $2,299,725.00  |  C 53-17-37  |  RESURF ROADWAY  |  51 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RK HALL, LLC
NOBLES ROAD CONSTRUCTION, INC.
BACKFILL (TY B)
STA 22.370 $100.000 $1,622.180 $400.000
TOM-C PG76-22 SAC-B
TON 7,006.000 $215.000 $208.050 $232.000
TACK COAT
GAL 12,185.000 $6.000 $5.270 $3.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 1,000.000 $75.000 $81.530 $100.000
PLANE ASPH CONC PAV(0" TO 1")
SY 23,354.000 $6.500 $3.800 $6.400
RIPRAP (MOW STRIP)(4 IN)
CY 37.000 $815.000 $862.500 $1,000.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 168.000 $100.000 $82.800 $200.000
MOBILIZATION
LS 1.000 $200,000.000 $177,322.650 $250,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $20,000.000 $21,114.780 $27,000.000
TMA (STATIONARY)
DAY 31.000 $250.000 $429.630 $500.000
TMA (MOBILE OPERATION)
DAY 6.000 $500.000 $610.440 $1,500.000
MTL W-BEAM GD FEN (TIM POST)
LF 450.000 $40.000 $30.180 $30.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $2,500.000 $2,701.350 $2,600.000
MTL BM GD FEN TRANS (NON - SYM)
EA 2.000 $1,200.000 $1,242.000 $1,200.000
REMOVE METAL BEAM GUARD FENCE
LF 450.000 $30.000 $1.150 $5.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,500.000 $3,466.100 $3,300.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $30.000 $230.000 $220.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $50.000 $39.040 $460.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB (BR)
EA 6.000 $50.000 $21.790 $135.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 2,462.000 $2.000 $3.470 $3.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,930.000 $2.000 $4.080 $3.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,860.000 $1.000 $1.090 $2.200
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 8,210.000 $0.900 $0.910 $1.200
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 34,000.000 $0.900 $0.830 $2.500
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 900.000 $0.900 $1.090 $2.200
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 37,170.000 $0.900 $0.830 $1.100
PREFAB PM TY C (W)(24")(SLD)
LF 684.000 $25.000 $18.400 $15.000
PREFAB PM TY C (W)(ARROW)
EA 18.000 $500.000 $402.500 $270.000
PREFAB PM TY C (W)(DBL ARROW)
EA 1.000 $500.000 $747.500 $410.000
PREFAB PM TY C (W)(WORD)
EA 9.000 $650.000 $0.450 $350.000
REFL PAV MRKR TY I-C
EA 410.000 $4.000 $4.310 $5.000
REFL PAV MRKR TY II-A-A
EA 446.000 $6.000 $4.310 $5.000
Totals: $2,299,725.000 $2,179,456.147 $2,568,167.600