Job Info for 6303-51-001

County: SAN PATRICIO Highway: SH0035 Date: 05/16/2017 (7 years ago) Engineer's Estimate: $147,618 Control Number: 6303-51-001
Project: BPM - 630351001 District: CORPUS CHRISTI Time: 35 W Type: CONCRETE STRUCTURE REPAIR

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $147,617.50
BXB GROUP INCORPORATION   $205,545.00 1
39.24% | $57,927.50
CHAMPION INFRASTRUCTURE, LLC   $218,032.00 2
47.7% | $70,414.50
6.08% | $12,487.00
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.   $470,074.89 3
218.44% | $322,457.39
128.7% | $264,529.89
115.60% | $252,042.89

Bid Items

Items: 18, 0 filtered
SAN PATRICIO SH0035  |  CORPUS CHRISTI  |  6303-51-001  |  05/16/2017  |  $147,618  |  BPM - 630351001  |  CONC STRUCT REPAIR  |  35 W
Item code Description Unit Quantity Engineer's Estimate BXB GROUP INCORPORATION CHAMPION INFRASTRUCTURE, LLC SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
104 6010 REMOVING CONC (RIPRAP) CY 1.000 $170.000 $1,517.000 $1,800.000 $2,063.540
110 6002 EXCAVATION (CHANNEL) CY 15.000 $25.000 $216.000 $120.000 $277.340
132 6005 EMBANKMENT (FINAL)(ORD COMP)(TY C) CY 37.000 $25.000 $183.000 $110.000 $128.060
132 6007 EMBANKMENT (FINAL)(ORD COMP)(TY D) CY 15.000 $25.000 $249.000 $60.000 $248.460
360 6027 CURB (TYPE II) LF 43.000 $20.000 $76.000 $60.000 $121.170
401 6001 FLOWABLE BACKFILL CY 33.000 $175.000 $362.000 $260.000 $325.020
403 6001 TEMPORARY SPL SHORING SF 391.000 $35.000 $40.000 $32.000 $114.470
407 6005 SHEET PILING (PZ - 22) SF 1,015.000 $35.000 $44.000 $32.000 $91.990
420 6064 CL C CONC (COPING) CY 5.000 $2,500.000 $2,748.000 $2,400.000 $5,840.000
429 6007 CONC STR REPAIR (VERTICAL & OVERHEAD) SF 86.000 $195.000 $283.000 $140.000 $289.480
432 6002 RIPRAP (CONC)(5 IN) CY 17.000 $500.000 $669.000 $1,500.000 $2,105.650
432 6031 RIPRAP (STONE PROTECTION)(12 IN) CY 6.500 $200.000 $480.000 $400.000 $1,164.750
432 6035 RIPRAP (STONE PROTECTION)(24 IN) CY 24.000 $200.000 $480.000 $280.000 $630.910
442 6004 STR STEEL (ROLLED BEAM) LB 5,725.000 $3.500 $3.600 $14.000 $14.740
480 6001 CLEAN EXIST CULVERTS EA 1.000 $1,500.000 $3,810.000 $4,500.000 $4,504.490
500 6001 MOBILIZATION LS 1.000 $13,420.000 $12,900.000 $5,000.000 $88,101.520
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 $3,000.000 $3,750.000 $900.000 $757.520
752 6005 TREE REMOVAL (4" - 12" DIA) EA 7.000 $300.000 $301.000 $300.000 $1,350.490
Totals: $147,617.50 $205,545.00 $218,032.00 $470,074.90