Job Info for 0916-28-071

County: SAN PATRICIO Highway: PR 25A Date: 03/07/2023 (1 year ago) Engineer's Estimate: $2,407,786 Control Number: 0916-28-071
Project: C 916-28-71 District: CORPUS CHRISTI Time: 78 WORKING DAYS Type: STATE PARK IMPROVEMENTS
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans: Plans | Revision | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,407,785.52
J. CARROLL WEAVER, INC.   $2,440,688.70 1
1.37% | $32,903.18
CK NEWBERRY, LLC   $2,647,012.05 2
9.94% | $239,226.53
8.45% | $206,323.35
LCR TOTAL TRANSPORT LLC   $2,687,699.00 3
11.63% | $279,913.48
10.12% | $247,010.30
1.54% | $40,686.95
J E CONSTRUCTION SERVICES, LLC   $2,987,020.60 4
24.06% | $579,235.08
22.38% | $546,331.90
11.14% | $299,321.60
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.   $2,987,795.32 5
24.09% | $580,009.80
22.42% | $547,106.62
0.03% | $774.72
ANDERSON COLUMBIA CO., INC.   $2,991,924.10 6
24.26% | $584,138.58
22.59% | $551,235.40
0.14% | $4,128.78
FNH CONSTRUCTION, LLC   $3,000,180.50 7
24.6% | $592,394.98
22.92% | $559,491.80
0.28% | $8,256.40
BRANNAN PAVING CO., LTD.   $3,600,356.08 8
49.53% | $1,192,570.56
47.51% | $1,159,667.38
20.00% | $600,175.58
HUNTER INDUSTRIES, LTD.   $5,555,536.11 9
130.73% | $3,147,750.59
127.62% | $3,114,847.41
54.31% | $1,955,180.03
Subcontractor Percentage Amount
BROOKE PAVING AND CONSTRUCTION LLC 13.95% $340,476.07
HIGHWAY BARRICADES AND SERVICES, LLC 2.04% $49,790.05
Total: 15.99% $390,266.12

Bid Items

Items: 38, 0 filtered
SAN PATRICIO PR 25A  |  CORPUS CHRISTI  |  0916-28-071  |  03/07/2023  |  $2,407,786  |  C 916-28-71  |  STATE PARK IMPRVS  |  78 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate J. CARROLL WEAVER, INC. CK NEWBERRY, LLC LCR TOTAL TRANSPORT LLC J E CONSTRUCTION SERVICES, LLC SALINAS CONSTRUCTION TECHNOLOGIES, LTD. ANDERSON COLUMBIA CO., INC. FNH CONSTRUCTION, LLC BRANNAN PAVING CO., LTD. HUNTER INDUSTRIES, LTD.
104 6011 REMOVING CONC (MEDIANS) SY 56.000 $18.000 $91.410 $50.000 $30.000 $34.000 $49.660 $35.000 $50.000 $54.320 $398.500
104 6013 REMOVING CONC (FOUNDATIONS) SY 2.000 $60.000 $2,559.420 $500.000 $15.000 $94.000 $507.810 $35.000 $500.000 $390.000 $542.500
110 6001 EXCAVATION (ROADWAY) CY 170.000 $10.000 $56.070 $35.000 $15.000 $18.000 $39.550 $35.000 $30.000 $74.850 $292.500
134 6005 BACKFILL TY A CY 253.000 $10.000 $178.870 $100.000 $28.000 $62.000 $89.800 $277.000 $100.000 $78.840 $388.500
247 6366 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) CY 136.000 $100.000 $146.630 $150.000 $170.000 $145.000 $162.300 $188.000 $100.000 $162.830 $1,014.710
275 6001 CEMENT TON 731.000 $225.000 $223.740 $210.000 $255.000 $240.000 $249.840 $244.000 $225.000 $318.640 $550.000
275 6009 CEMENT TREAT (NEW BASE) (8") SY 610.000 $6.000 $19.970 $3.500 $4.500 $6.300 $17.190 $5.000 $15.000 $18.190 $79.200
275 6011 CEMENT TREAT(EXIST MATL)(8") SY 43,757.000 $6.000 $4.630 $3.500 $4.500 $5.300 $7.330 $5.100 $8.000 $7.100 $26.400
310 6009 PRIME COAT (MC-30) GAL 8,878.000 $5.000 $4.840 $6.000 $6.750 $5.800 $7.370 $5.800 $10.000 $9.180 $21.000
316 6001 ASPH (MULTI OPTION) GAL 30,179.000 $5.000 $4.010 $4.000 $4.900 $4.000 $5.450 $4.100 $8.000 $10.210 $21.000
316 6413 ASPH(AC-15P, HFRS-2P OR CRS-2P) GAL 4,261.000 $4.000 $4.620 $4.250 $4.900 $5.500 $6.120 $3.400 $10.000 $10.210 $21.000
316 6427 AGGR(TY-PB GR-4S OR TY-PB GR-4)(SAC-B) CY 112.000 $150.000 $266.860 $230.000 $214.000 $365.000 $421.020 $350.000 $300.000 $354.160 $302.500
316 6430 AGGR(TY-PB GR-3 OR TY-PB GR-3S)(SAC-B) CY 810.000 $150.000 $175.150 $225.000 $213.000 $282.000 $311.400 $332.000 $300.000 $358.770 $302.500
351 6012 FLEXIBLE PAVEMENT STRUCTURE REPAIR(2") SY 14.000 $50.000 $680.840 $150.000 $42.000 $132.000 $378.820 $144.000 $200.000 $250.000 $1,364.800
400 6012 CUT AND RESTORE PAV (FLEX BASE) SY 46.000 $75.000 $106.400 $275.000 $69.000 $155.000 $273.630 $311.000 $200.000 $253.040 $250.060
464 6001 RC PIPE (CL III)(12 IN) LF 64.000 $70.000 $157.820 $115.000 $100.000 $95.000 $108.890 $121.000 $85.000 $113.410 $116.270
464 6002 RC PIPE (CL III)(15 IN) LF 32.000 $50.000 $219.590 $130.000 $108.000 $98.000 $191.190 $124.000 $95.000 $120.160 $119.840
464 6005 RC PIPE (CL III)(24 IN) LF 108.000 $80.000 $150.960 $150.000 $190.000 $132.000 $155.010 $156.000 $105.000 $183.310 $147.120
467 6322 SET (TY II) (12 IN) (RCP) (3: 1) (C) EA 4.000 $500.000 $2,464.000 $2,000.000 $1,125.000 $1,300.000 $1,477.220 $2,230.000 $1,850.000 $2,019.000 $2,078.100
467 6336 SET (TY II) (15 IN) (RCP) (3: 1) (C) EA 2.000 $500.000 $2,688.000 $2,400.000 $1,428.000 $1,300.000 $1,477.220 $2,170.000 $2,250.000 $2,061.000 $2,319.790
467 6388 SET (TY II) (24 IN) (RCP) (3: 1) (C) EA 6.000 $500.000 $3,584.000 $2,800.000 $3,770.000 $1,500.000 $1,836.320 $2,340.000 $3,000.000 $2,606.000 $3,221.770
496 6007 REMOV STR (PIPE) LF 204.000 $20.000 $51.190 $20.000 $23.000 $24.000 $26.080 $48.000 $30.000 $6.120 $45.920
500 6001 MOBILIZATION LS 1.000 $157,397.700 $84,233.620 $250,000.000 $268,000.000 $20,000.000 $234,550.490 $160,000.000 $300,000.000 $292,147.000 $473,409.920
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $5,000.000 $3,360.000 $10,000.000 $623.000 $1,500.000 $1,363.580 $5,400.000 $8,000.000 $3,160.000 $6,361.250
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 500.000 $5.000 $13.440 $8.000 $8.000 $5.000 $11.810 $8.450 $12.000 $10.000 $7.250
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 500.000 $2.000 $2.240 $4.000 $1.700 $2.000 $2.460 $3.500 $6.000 $5.000 $3.000
666 6041 REFL PAV MRK TY I (W)12"(SLD)(090MIL) LF 36.000 $3.000 $22.400 $21.000 $23.000 $24.000 $25.550 $23.000 $6.000 $7.400 $8.000
666 6302 RE PM W/RET REQ TY I (W)4"(SLD)(090MIL) LF 15,738.000 $0.290 $1.120 $1.050 $1.100 $1.200 $1.120 $1.150 $1.750 $1.200 $1.500
666 6317 RE PM W/RET REQ TY I (Y)6"(BRK)(090MIL) LF 5,104.000 $0.700 $1.680 $1.600 $1.800 $2.000 $1.680 $1.750 $2.000 $2.200 $1.750
666 6356 REFL PAV MRK TY II (R&W)6"(FIRE LANE) LF 50.000 $2.500 $28.000 $27.000 $28.000 $31.000 $30.060 $29.000 $8.000 $9.000 $2.000
668 6055 PRE PM TY B(ACC PRK)(BL&WH)(W/BORDR)LG EA 21.000 $500.000 $336.000 $325.000 $340.000 $374.000 $336.090 $349.000 $500.000 $280.000 $425.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 34.000 $250.000 $392.000 $375.000 $397.000 $435.000 $400.050 $407.000 $350.000 $260.000 $250.000
672 6008 REFL PAV MRKR TY I-R EA 12.000 $8.000 $11.200 $11.000 $11.000 $12.000 $21.660 $12.000 $6.000 $12.800 $8.000
1004 6002 TREE PROTECTION AC 7.000 $8,500.000 $3,427.590 $5,000.000 $5,750.000 $3,500.000 $3,845.240 $1,160.000 $5,000.000 $25,000.000 $1,500.000
3076 6042 D-GR HMA TY-D SAC-B PG70-22 TON 8,370.000 $150.000 $155.820 $165.000 $164.000 $223.000 $168.880 $195.000 $140.000 $183.960 $198.000
5008 6002 MOVE AND RESET PRECAST CONC WHEEL STOPS EA 488.000 $66.000 $28.490 $35.000 $30.000 $37.000 $48.940 $25.000 $150.000 $75.000 $200.040
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 72.000 $100.000 $95.200 $40.000 $110.000 $105.000 $142.760 $99.000 $100.000 $250.000 $128.200
6185 6002 TMA (STATIONARY) DAY 72.000 $150.000 $280.000 $250.000 $170.000 $198.000 $245.590 $10.000 $200.000 $250.000 $238.400
Totals: $2,407,785.52 $2,440,688.70 $2,647,012.05 $2,687,699.00 $2,987,020.60 $2,987,795.32 $2,991,924.10 $3,000,180.50 $3,600,356.08 $5,555,536.11