Job Info for 0916-28-068

County: SAN PATRICIO Highway: CS Date: 08/08/2017 (7 years ago) Engineer's Estimate: $132,782 Control Number: 0916-28-068
Project: STP 1702(430)TAPS District: CORPUS CHRISTI Time: 90 WORKING DAYS Type: CONSTRUCT SIDEWALK

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $132,782.00
ENCINO LANDSCAPE, INC.   $119,588.00 1
-9.94% | -$13,194.00
TI-ZACK CONCRETE, INC.   $123,079.00 2
-7.31% | -$9,703.00
2.92% | $3,491.00
MAIN LANE INDUSTRIES LTD.   $138,606.00 3
4.39% | $5,824.00
15.9% | $19,018.00
12.62% | $15,527.00
TCB CONSTRUCTION, INC   $185,459.00 4
39.67% | $52,677.00
55.08% | $65,871.00
33.80% | $46,853.00
JIMMY EVANS COMPANY, LTD.   $190,442.00 5
43.42% | $57,660.00
59.25% | $70,854.00
2.69% | $4,983.00
FNH CONSTRUCTION, LLC   $196,105.00 6
47.69% | $63,323.00
63.98% | $76,517.00
2.97% | $5,663.00
SJ&J CONSTRUCTION, LLC   $197,590.00 7
48.81% | $64,808.00
65.23% | $78,002.00
0.76% | $1,485.00
MHB CONSTRUCTION, INC.   $220,601.40 8
66.14% | $87,819.40
84.47% | $101,013.40
11.65% | $23,011.40

Bid Items

Items: 14, 0 filtered
SAN PATRICIO CS  |  CORPUS CHRISTI  |  0916-28-068  |  08/08/2017  |  $132,782  |  STP 1702(430)TAPS  |  CONSTRUCT SIDEWALK  |  90 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate ENCINO LANDSCAPE, INC. TI-ZACK CONCRETE, INC. MAIN LANE INDUSTRIES LTD. TCB CONSTRUCTION, INC JIMMY EVANS COMPANY, LTD. FNH CONSTRUCTION, LLC SJ&J CONSTRUCTION, LLC MHB CONSTRUCTION, INC.
100 6002 PREPARING ROW STA 12.700 $800.000 $300.000 $500.000 $1,000.000 $2,500.000 $3,000.000 $500.000 $1,000.000 $772.000
104 6015 REMOVING CONC (SIDEWALKS) SY 472.000 $16.000 $10.000 $15.000 $20.000 $55.000 $20.000 $20.000 $30.000 $30.000
104 6017 REMOVING CONC (DRIVEWAYS) SY 97.000 $22.000 $10.000 $15.000 $20.000 $65.000 $33.000 $20.000 $30.000 $30.000
104 6022 REMOVING CONC (CURB AND GUTTER) LF 146.000 $10.000 $5.000 $6.000 $20.000 $7.000 $18.000 $20.000 $30.000 $35.000
104 6028 REMOVING CONC (MISC) SY 39.000 $30.000 $10.000 $45.000 $20.000 $75.000 $33.000 $20.000 $30.000 $35.000
351 6004 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 90.000 $250.000 $50.000 $75.000 $160.000 $54.000 $300.000 $200.000 $90.000 $300.000
500 6001 MOBILIZATION LS 1.000 $16,000.000 $25,000.000 $25,000.000 $13,500.000 $30,000.000 $17,000.000 $19,500.000 $60,000.000 $50,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $3,500.000 $3,000.000 $1,000.000 $2,000.000 $2,292.000 $3,000.000 $8,500.000 $4,000.000 $7,000.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 48.000 $6.000 $10.000 $5.000 $10.000 $14.000 $25.000 $12.000 $8.000 $20.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 48.000 $1.000 $1.000 $1.000 $2.000 $6.000 $12.000 $8.000 $2.000 $10.000
530 6004 DRIVEWAYS (CONC) SY 149.000 $80.000 $60.000 $75.000 $100.000 $81.000 $100.000 $85.000 $110.000 $88.000
531 6001 CONC SIDEWALKS (4") SY 630.000 $45.000 $50.000 $70.000 $75.000 $63.000 $72.000 $85.000 $70.000 $60.000
531 6024 CURB RAMPS (TY 7) SY 100.000 $150.000 $100.000 $115.000 $100.000 $125.000 $95.000 $250.000 $150.000 $200.000
752 6005 TREE REMOVAL (4" - 12" DIA) EA 11.000 $200.000 $1,500.000 $250.000 $200.000 $750.000 $750.000 $1,000.000 $200.000 $900.000
Totals: $132,782.00 $119,588.00 $123,079.00 $138,606.00 $185,459.00 $190,442.00 $196,105.00 $197,590.00 $220,601.40