Job Info for 6417-38-001

County: SAN AUGUSTINE Highway: US0096 Date: 01/18/2023 (1 year ago) Engineer's Estimate: $185,265 Control Number: 6417-38-001
Project: RMC - 641738001 District: LUFKIN Time: 365 CALENDAR DAYS Type: REPAIR/UPGRADE & MAINTENANCE OF MBGF
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6
Plans

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $185,265.00
JCW CONSTRUCTION, LLC   $169,773.00 1
-8.36% | -$15,492.00
DIGG COMMERCIAL, LLC   $189,853.00 2
2.48% | $4,588.00
11.83% | $20,080.00
ACE CONTRACTORS, INC.   $192,326.00 3
3.81% | $7,061.00
13.28% | $22,553.00
1.30% | $2,473.00
GARRET SHIELDS INFRASTRUCTURE   $222,500.00 4
20.1% | $37,235.00
31.06% | $52,727.00
15.69% | $30,174.00

Bid Items

Items: 26, 0 filtered
SAN AUGUSTINE US0096  |  LUFKIN  |  6417-38-001  |  01/18/2023  |  $185,265  |  RMC - 641738001  |  REPAIR/UPGRADE & MAINT OF MBGF  |  365 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate JCW CONSTRUCTION, LLC DIGG COMMERCIAL, LLC ACE CONTRACTORS, INC. GARRET SHIELDS INFRASTRUCTURE
450 6018 RAIL (TY T631) LF 75.000 $140.000 $50.000 $50.000 $145.000 $60.000
500 6033 MOBILIZATION (CALLOUT) EA 12.000 $2,000.000 $1.000 $1.000 $750.000 $2,000.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 800.000 $45.000 $20.000 $14.000 $33.000 $50.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $1,200.000 $1,700.000 $1.000 $750.000 $1,500.000
540 6008 MTL BEAM GD FEN TRANS (T101) EA 8.000 $1,115.000 $900.000 $1.000 $1,500.000 $500.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 2,000.000 $3.100 $10.000 $1.000 $2.000 $5.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 6.000 $250.000 $1.000 $1.000 $1.000 $100.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 6.000 $2,875.000 $2,500.000 $2,300.000 $3,000.000 $4,500.000
658 6016 INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI) EA 10.000 $30.000 $1.000 $50.000 $40.000 $40.000
770 6001 REPAIR RAIL ELEMENT (W - BEAM) LF 1,200.000 $17.000 $15.000 $14.000 $26.000 $40.000
770 6010 REM / REPL TIMBER/STL POST W/O CONC FND EA 75.000 $60.000 $100.000 $100.000 $60.000 $50.000
770 6011 REM / REPL TIMBER / STL POST W/CONC FND EA 15.000 $70.000 $100.000 $100.000 $85.000 $80.000
770 6016 REPAIR STEEL POST WITH BASE PLATE EA 10.000 $115.000 $300.000 $1.000 $60.000 $200.000
770 6017 REALIGN POSTS EA 30.000 $20.000 $100.000 $330.000 $25.000 $30.000
770 6018 INSTALL BLOCKOUT (TYPE SPECIFIED) EA 15.000 $33.000 $20.000 $1.000 $20.000 $20.000
770 6019 REMOVE & REPLACE BLOCKOUT EA 5.000 $20.000 $1,000.000 $1.000 $25.000 $30.000
770 6021 REPLACE SINGLE GDRAIL TERMINAL RAIL LF 125.000 $30.000 $25.000 $22.000 $50.000 $10.000
770 6022 REPLACE SINGLE GDRAIL TERMINAL POST EA 15.000 $85.000 $500.000 $200.000 $75.000 $50.000
770 6023 REPAIR OF TERMINAL ANCHORS POSTS EA 20.000 $15.000 $1.000 $100.000 $1.000 $30.000
770 6027 REMOVE GDRAIL END TRT / REPL WITH SGT EA 6.000 $3,650.000 $4,300.000 $2,300.000 $5,500.000 $4,500.000
770 6028 REPL SINGLE GDRAIL TERM IMPACT HEAD EA 8.000 $1,050.000 $650.000 $1.000 $1,250.000 $1,000.000
770 6029 REM & RESET SGT IMPACT HEAD EA 8.000 $125.000 $100.000 $1.000 $400.000 $200.000
770 6034 REPAIR RAIL ELEMENT(W - BEAM FURNISHED) LF 50.000 $15.000 $15.000 $25.000 $1.000 $10.000
774 6017 REPAIR (WIDE QUAD) EA 2.000 $1,500.000 $2,500.000 $1.000 $2,500.000 $1,000.000
776 6020 REPAIR (TY T101RC) LF 25.000 $45.000 $100.000 $1.000 $50.000 $80.000
6185 6002 TMA (STATIONARY) DAY 20.000 $300.000 $600.000 $5,000.000 $500.000 $300.000
Totals: $185,265.00 $169,773.00 $189,853.00 $192,326.00 $222,500.00