SAN AUGUSTINE US 96 (0809-03-040)

Items: 103

County: SAN AUGUSTINE
Length: N/A
Highway: US 96
District: LUFKIN
Control Number: 0809-03-040
DBE Goal: N/A
Project: C 809-3-40
Guaranty: N/A
Time: 160 WORKING DAYS
Engineer's Estimate: $5,763,105.40
Date: 05/07/2020 (6 years ago)
Contract Number: N/A
Type: CONSTRUCT NEW ROADWAY LANES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$5,763,105.40
$4,885,972.00
Over/Under Est: -15.22% -$877,133.40
Over/Under Est: -13.68% -$788,448.63
Amt Left: 1.82% $88,684.77
$5,221,911.74
Over/Under Est: -9.39% -$541,193.66
Amt Left: 6.88% $335,939.74
Delta: -4.97% -$247,254.97
Over/Under Est: 5.67% $326,784.48
Amt Left: 24.64% $1,203,917.88
Delta: -16.62% -$867,978.14
Over/Under Est: 11.09% $638,975.70
Amt Left: 31.03% $1,516,109.10
Delta: -5.13% -$312,191.22

Bid Items & Bid Tabulations

103 Total 0 of 103
SAN AUGUSTINE  |  US 96  |  LUFKIN  |  0809-03-040  |  05/07/2020  |  $5,763,105.40  |  C 809-3-40  |  CONSTRUCT NEW ROADWAY LANES  |  160 WORKING DAYS
Alt
Item Code
Description
Unit
Quantity
Engineer's Estimate
MADDEN CONTRACTING COMPANY, LLC.
MOORE BROTHERS CONSTRUCTION COMPANY
A. L. HELMCAMP, INC.
EAST TEXAS BRIDGE, INC.
L. S. EQUIPMENT CO., INC.
PREPARING ROW
STA 138.320 $800.000 $500.000 $490.000 $900.000 $1,500.000 $750.000
REMOVING CONC (RIPRAP)
SY 26.000 $50.000 $13.000 $14.000 $14.000 $30.000 $20.000
REMOVING CONC (FLUME)
SY 231.000 $20.000 $13.000 $14.000 $14.000 $20.000 $25.000
SUBGRADE WIDENING (ORD COMP)
STA 114.600 $275.000 $341.000 $365.000 $275.000 $800.000 $400.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 16,088.000 $10.000 $8.190 $8.750 $18.000 $15.000 $30.000
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 27.000 $135.000 $138.000 $150.000 $160.000 $300.000 $50.000
FURNISHING AND PLACING TOPSOIL (4")
SY 134,411.000 $1.000 $1.000 $1.070 $0.500 $1.250 $1.250
BLOCK SODDING
SY 1,149.000 $5.000 $5.000 $5.600 $6.000 $6.000 $3.500
BROADCAST SEED (TEMP) (WARM)
SY 67,205.000 $0.150 $0.110 $0.100 $0.070 $0.110 $0.150
BROADCAST SEED (TEMP) (COOL)
SY 67,205.000 $0.150 $0.100 $0.160 $0.070 $0.110 $0.150
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 134,411.000 $0.300 $0.350 $0.320 $0.300 $0.320 $0.350
VEGETATIVE WATERING
MG 5,395.080 $15.000 $0.010 $0.010 $0.010 $12.000 $0.010
CEM TRT(PLNT MX) (CL N)(TYA)(GR1-2)(6")
SY 14,910.000 $29.190 $22.900 $24.500 $20.000 $0.000 $0.000
EMULS ASPH (EROSN CONT)(SS-1)
GAL 1,844.000 $3.250 $4.000 $4.280 $4.200 $5.000 $3.500
ASPH (AC-10-2TR)
TON 114.000 $800.000 $675.000 $725.000 $750.000 $1,000.000 $822.000
ASPH (RC-250)
TON 16.000 $647.000 $732.000 $785.000 $900.000 $0.000 $0.000
AGGR (TY-PE, E, L OR PL GR 3)
CY 865.000 $135.000 $134.000 $143.000 $110.000 $125.000 $125.000
AGGR (TY E OR L GR 5)
CY 115.000 $150.000 $128.000 $140.000 $180.000 $0.000 $0.000
CEM STABIL BKFL
CY 7.000 $300.000 $145.000 $155.000 $150.000 $300.000 $400.000
TRENCH EXCAVATION PROTECTION
LF 25.000 $100.000 $12.000 $13.000 $13.000 $10.000 $15.000
TEMPORARY SPL SHORING
SF 875.000 $50.000 $30.000 $32.000 $31.000 $40.000 $25.000
CL A CONC (FLUME)
CY 10.000 $1,000.000 $525.000 $562.000 $550.000 $700.000 $700.000
CL A CONC (COLLAR)
EA 20.000 $1,000.000 $500.000 $535.000 $520.000 $700.000 $950.000
CL A CONC (PLUG)
EA 2.000 $1,500.000 $550.000 $588.000 $570.000 $1,000.000 $250.000
RIPRAP (CONC)(6 IN)
CY 24.000 $650.000 $520.000 $556.000 $540.000 $500.000 $500.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 5.000 $350.000 $188.000 $201.000 $190.000 $200.000 $144.000
CONC BOX CULV (5 FT X 5 FT)(EXTEND)
LF 6.000 $550.000 $648.000 $695.000 $650.000 $800.000 $750.000
RC PIPE (CL III)(18 IN)
LF 444.000 $50.000 $41.000 $44.000 $42.000 $40.000 $70.000
RC PIPE (CL III)(24 IN)
LF 132.000 $55.000 $59.000 $63.000 $60.000 $55.000 $95.000
RC PIPE (CL III)(30 IN)
LF 98.000 $75.000 $93.000 $100.000 $95.000 $70.000 $175.000
RC PIPE (CL III)(36 IN)
LF 28.000 $110.000 $150.000 $106.000 $155.000 $100.000 $195.000
RC PIPE (CL III)(42 IN)
LF 128.000 $125.000 $179.000 $190.000 $185.000 $120.000 $225.000
RC PIPE (CL III)(48 IN)
LF 20.000 $140.000 $199.000 $213.000 $210.000 $150.000 $275.000
INLET(COMPL)(PAZD)(FG)(3FTX3FT-3FTX3FT)
EA 1.000 $6,000.000 $5,000.000 $5,350.000 $5,200.000 $6,000.000 $6,500.000
HEADWALL (CH - PW - 0) (DIA= 42 IN)
EA 6.000 $9,000.000 $5,437.000 $5,820.000 $5,700.000 $7,000.000 $14,000.000
HEADWALL (CH - PW - 0) (DIA= 66 IN)
EA 1.000 $10,500.000 $22,902.000 $24,500.000 $23,000.000 $16,000.000 $15,000.000
HEADWALL (CH - PW - 0) (DIA= 72 IN)
EA 3.000 $14,000.000 $25,955.000 $27,770.000 $27,000.000 $20,000.000 $20,000.000
HEADWALL (CH - PW - S) (DIA= 30 IN)
EA 2.000 $6,000.000 $9,794.000 $10,500.000 $10,000.000 $7,000.000 $7,500.000
HEADWALL (CH - PW - S) (DIA= 36 IN)
EA 2.000 $7,000.000 $11,087.000 $11,875.000 $11,500.000 $8,000.000 $9,000.000
HEADWALL (CH - PW - S) (DIA= 72 IN)
EA 2.000 $11,000.000 $21,366.000 $22,875.000 $22,000.000 $26,000.000 $15,000.000
WINGWALL (PW - 2) (HW=7 FT)
EA 1.000 $15,000.000 $15,865.000 $16,975.000 $16,000.000 $1,000.000 $15,000.000
HEADWALL (CH - PW - 0)(DIA= 27IN) (MOD)
EA 1.000 $20,000.000 $14,732.000 $15,750.000 $15,000.000 $8,000.000 $7,500.000
HEADWALL (CH - PW - 0)(DIA= 72IN) (MOD)
EA 1.000 $30,000.000 $25,261.000 $27,000.000 $26,000.000 $15,000.000 $12,500.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 3.000 $600.000 $502.000 $535.000 $530.000 $500.000 $750.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 30.000 $650.000 $539.000 $580.000 $560.000 $575.000 $825.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 2.000 $2,000.000 $961.000 $1,030.000 $1,000.000 $900.000 $900.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 6.000 $2,500.000 $913.000 $975.000 $950.000 $900.000 $900.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 1.000 $2,750.000 $2,123.000 $2,300.000 $2,200.000 $2,000.000 $3,900.000
SET (TY II) (42 IN) (RCP) (6: 1) (P)
EA 2.000 $6,000.000 $5,407.000 $5,800.000 $5,500.000 $6,000.000 $5,000.000
CLEAN EXIST CULVERTS
EA 13.000 $3,000.000 $819.000 $875.000 $830.000 $1,000.000 $1,500.000
REMOV STR (INLET)
EA 1.000 $1,000.000 $448.000 $480.000 $460.000 $500.000 $1,000.000
REMOV STR (SET)
EA 3.000 $450.000 $224.000 $240.000 $230.000 $500.000 $1,000.000
REMOV STR (PIPE)
EA 18.000 $400.000 $250.000 $265.000 $260.000 $500.000 $1,000.000
MOBILIZATION
LS 1.000 $580,000.000 $328,000.000 $280,000.000 $500,000.000 $600,000.000 $650,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $5,000.000 $2,200.000 $1,775.000 $5,000.000 $10,000.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 835.000 $42.000 $34.000 $37.000 $31.000 $38.000 $40.000
ROCK FILTER DAMS (REMOVE)
LF 835.000 $8.000 $13.000 $9.000 $10.000 $13.000 $10.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 234.000 $35.000 $25.000 $37.000 $15.000 $28.000 $25.000
CONSTRUCTION EXITS (REMOVE)
SY 234.000 $10.000 $13.000 $9.000 $3.000 $13.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 9,040.000 $2.500 $2.600 $2.890 $2.700 $3.500 $2.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 9,040.000 $1.000 $1.100 $0.820 $0.650 $1.100 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 216.000 $4.000 $6.000 $5.250 $6.500 $8.000 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 216.000 $1.000 $4.000 $1.050 $1.100 $4.000 $2.000
INTERSECTIONS (ACP)
SY 458.000 $70.000 $73.750 $62.860 $90.000 $95.000 $50.000
DRIVEWAYS (ACP)
SY 8,873.000 $30.000 $33.250 $29.200 $30.000 $55.000 $50.000
TURNOUTS (SURF TREAT)
SY 90.000 $40.000 $39.000 $77.290 $90.000 $55.000 $75.000
DRIVEWAYS (BASE)
SY 205.000 $30.000 $20.000 $21.500 $50.000 $30.000 $30.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 19,134.000 $0.250 $0.400 $0.390 $0.450 $0.450 $0.300
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 9,637.000 $0.200 $0.400 $0.620 $0.450 $0.550 $0.250
MAILBOX INSTALL-M (TWG-POST) TY 2
EA 3.000 $450.000 $535.000 $435.000 $430.000 $600.000 $500.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 4.000 $200.000 $330.000 $215.000 $200.000 $400.000 $195.000
MAILBOX INSTALL-D (WC-POST) TY 3
EA 4.000 $220.000 $375.000 $225.000 $230.000 $400.000 $195.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 4.000 $470.000 $655.000 $500.000 $580.000 $700.000 $750.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $620.000 $815.000 $825.000 $670.000 $900.000 $800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 3.000 $715.000 $810.000 $850.000 $730.000 $900.000 $800.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 33.000 $365.000 $475.000 $335.000 $320.000 $500.000 $500.000
INSTL OM ASSM (OM-2Z)(FLX)SRF
EA 28.000 $85.000 $90.000 $83.000 $35.000 $100.000 $225.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 7,170.000 $0.350 $0.200 $0.220 $0.210 $0.220 $0.250
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 85,890.000 $0.250 $0.200 $0.220 $0.210 $0.220 $0.250
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 92,880.000 $0.300 $0.200 $0.220 $0.210 $0.220 $0.220
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,568.000 $1.500 $1.000 $1.000 $0.680 $2.000 $1.000
WK ZN PAV MRK SHT TERM RMV (Y)(4")
LF 61,920.000 $1.000 $0.010 $0.500 $0.680 $1.500 $3.000
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 260.000 $1.000 $1.000 $1.100 $1.050 $1.100 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 432.000 $0.750 $1.000 $1.100 $1.050 $1.100 $1.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 2,390.000 $0.450 $0.600 $0.660 $0.630 $0.660 $0.700
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 28,630.000 $0.450 $0.500 $0.550 $0.530 $0.550 $0.600
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 30,960.000 $0.450 $0.500 $0.550 $0.530 $0.550 $0.700
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 108.000 $30.000 $15.000 $16.500 $16.000 $18.000 $15.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 2.000 $200.000 $200.000 $220.000 $210.000 $220.000 $250.000
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 2.000 $675.000 $400.000 $440.000 $420.000 $440.000 $400.000
PREFAB PAV MRK TY C (W) (WORD)
EA 2.000 $300.000 $300.000 $330.000 $315.000 $330.000 $300.000
REFL PAV MRKR TY I-C
EA 141.000 $3.000 $3.500 $3.850 $3.700 $4.000 $3.500
REFL PAV MRKR TY II-A-A
EA 390.000 $3.500 $3.500 $3.850 $3.700 $4.000 $3.500
ELIM EXT PAV MRK & MRKS (4")
LF 4,750.000 $0.350 $0.400 $0.440 $0.500 $0.440 $1.000
SP MIXES SP-B PG64-22
TON 4,921.000 $95.000 $95.000 $93.180 $93.000 $0.000 $0.000
SP MIXES SP-C PG70-22
TON 12,338.000 $105.000 $95.000 $100.250 $96.000 $95.000 $99.000
SP MIXES SP-C SAC-A PG70-22
TON 8,560.000 $110.000 $95.000 $95.860 $98.000 $100.000 $105.000
TACK COAT
GAL 4,669.000 $10.000 $3.650 $3.900 $4.000 $0.000 $0.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $18,000.000 $12,000.000 $10,000.000 $20,000.000 $2,000.000
TMA (STATIONARY)
DAY 62.000 $200.000 $150.000 $160.000 $220.000 $300.000 $1,500.000
TMA (MOBILE OPERATION)
DAY 13.000 $200.000 $0.010 $100.000 $100.000 $300.000 $250.000
1
SP MIXES SP-B PG64-22
TON 9,840.000 $95.000 $0.000 $0.000 $0.000 $90.000 $97.000
1
TACK COAT
GAL 4,221.000 $10.000 $0.000 $0.000 $0.000 $5.000 $5.000
Totals: $6,740,115.300 $4,885,972.001 $4,974,656.771 $5,221,911.741 $6,089,889.880 $6,402,081.101