Job Info for 6466-49-001

County: SABINE Highway: FM0083 Date: 05/09/2024 (6 months ago) Engineer's Estimate: $216,780 Control Number: 6466-49-001
Project: MMC - 646649001 District: LUFKIN Time: 180 CALENDAR DAYS Type: HOT MIX/TY D/SABINE
Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5
Plans

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $216,780.00
TEXAS MATERIALS GROUP, INC.   $238,100.00 1
9.83% | $21,320.00

Bid Items

Items: 1, 0 filtered
SABINE FM0083  |  LUFKIN  |  6466-49-001  |  05/09/2024  |  $216,780  |  MMC - 646649001  |  HOT MIX/TY D/SABINE  |  180 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate TEXAS MATERIALS GROUP, INC.
8011 6001 D-GR HMA(SQ) TY D PG 64-22 (PICKUP) TON 2,000.000 $108.390 $119.050
Totals: $216,780.00 $238,100.00