PREPARING ROW
|
STA
|
14.000
|
$2,000.000
|
$1,930.940
|
|
|
SUBGRADE WIDENING (DENS CONT)
|
STA
|
13.200
|
$3,450.000
|
$5,431.100
|
|
|
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
|
CY
|
300.000
|
$35.000
|
$92.330
|
|
|
BACKFILL (TY A)
|
STA
|
1.000
|
$300.000
|
$2,618.270
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
9,098.000
|
$5.500
|
$8.930
|
|
|
BLOCK SODDING
|
SY
|
123.000
|
$10.000
|
$16.500
|
|
|
ROLL SODDING
|
SY
|
1,537.000
|
$6.000
|
$8.250
|
|
|
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
|
SY
|
9,098.000
|
$2.000
|
$1.100
|
|
|
BONDED FBR MTRX SEED (TEMP)(WARM)
|
SY
|
4,549.000
|
$2.000
|
$1.100
|
|
|
BONDED FBR MTRX SEED (TEMP)(COOL)
|
SY
|
4,549.000
|
$2.000
|
$1.100
|
|
|
VEGETATIVE WATERING
|
MG
|
366.400
|
$30.000
|
$18.550
|
|
|
SPRINKLING (DUST CONTROL)
|
MG
|
95.500
|
$5.000
|
$71.170
|
|
|
CEM TRT (PLNT MX)(CL N)(TY A)(GR3)(12")
|
SY
|
5,323.000
|
$100.000
|
$100.290
|
|
|
ASPH (RC-250)
|
TON
|
7.000
|
$1,900.000
|
$1,577.770
|
|
|
AGGR (TY E OR L, PE OR PL GR 4)
|
CY
|
72.000
|
$250.000
|
$480.910
|
|
|
AGGR (TY E OR L GR 5)
|
CY
|
37.000
|
$250.000
|
$706.620
|
|
|
ASPH (AC-15P OR CRS-2P)
|
TON
|
12.900
|
$1,000.000
|
$1,605.310
|
|
|
PLANE ASPH CONC PAV(2" TO 4")
|
SY
|
524.000
|
$8.000
|
$23.340
|
|
|
PLANE ASPH CONC PAV (2")
|
SY
|
2,721.000
|
$5.000
|
$7.800
|
|
|
DRILL SHAFT (SIGN MTS) (24 IN)
|
LF
|
24.000
|
$300.000
|
$324.500
|
|
|
CL C CONC (COLLAR)
|
EA
|
1.000
|
$1,500.000
|
$3,300.000
|
|
|
RIPRAP (STONE TY R)(GROUT)(8 IN)
|
CY
|
11.000
|
$310.000
|
$3,300.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
52.000
|
$90.000
|
$165.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 33 IN)
|
EA
|
1.000
|
$10,000.000
|
$16,500.000
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (C)
|
EA
|
1.000
|
$1,000.000
|
$2,750.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$1,500.000
|
$3,300.000
|
|
|
REMOV STR (PIPE)
|
LF
|
43.000
|
$25.000
|
$38.500
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$155,000.000
|
$150,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
11.000
|
$3,500.000
|
$942.500
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
44.000
|
$45.000
|
$52.250
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
44.000
|
$15.000
|
$15.400
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
94.000
|
$10.000
|
$40.150
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
94.000
|
$5.000
|
$15.400
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
1,432.000
|
$5.000
|
$3.850
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
1,432.000
|
$1.500
|
$1.100
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
20.000
|
$60.000
|
$451.310
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$70.000
|
$293.660
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
20.000
|
$20.000
|
$495.370
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$20.000
|
$247.680
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
20.000
|
$20.000
|
$495.370
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$20.000
|
$247.680
|
|
|
DRIVEWAYS (ACP)
|
SY
|
637.000
|
$75.000
|
$104.490
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
287.500
|
$30.000
|
$33.000
|
|
|
MTL BM GD FEN TRANS (31"-28")(25')
|
EA
|
2.000
|
$800.000
|
$1,072.500
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
337.500
|
$5.000
|
$3.300
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
2.000
|
$3,500.000
|
$3,520.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
2.000
|
$300.000
|
$550.000
|
|
|
ALUMINUM SIGNS (TY G)
|
SF
|
198.000
|
$30.000
|
$57.750
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
8.000
|
$450.000
|
$577.500
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(T)
|
EA
|
1.000
|
$550.000
|
$771.100
|
|
|
RELOCATE SM RD SN SUP&AM TY TWT
|
EA
|
2.000
|
$700.000
|
$379.500
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
7.000
|
$110.000
|
$214.500
|
|
|
INSTALL LRSS (STRUCT STEEL)
|
LB
|
1,192.000
|
$10.000
|
$8.780
|
|
|
REMOVE LRSA
|
EA
|
1.000
|
$500.000
|
$2,750.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
4.000
|
$40.000
|
$39.600
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)SRF(BI)
|
EA
|
2.000
|
$100.000
|
$137.500
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
2,958.000
|
$0.750
|
$0.550
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
|
LF
|
8,878.000
|
$0.750
|
$0.550
|
|
|
WK ZN PAV MRK REMOV (W)6"(SLD)
|
LF
|
7,474.000
|
$2.750
|
$2.480
|
|
|
WK ZN PAV MRK REMOV (Y)6"(SLD)
|
LF
|
7,474.000
|
$2.750
|
$2.480
|
|
|
WK ZN PAV MRK SHT TERM RMV (W)(4")
|
LF
|
226.000
|
$3.000
|
$3.000
|
|
|
WK ZN PAV MRK SHT TERM RMV (Y)(4")
|
LF
|
1,143.000
|
$2.000
|
$3.420
|
|
REFL PAV MRK TY I (W)6"(DOT)(090MIL)
|
LF
|
153.000
|
$1.500
|
$3.850
|
|
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
|
LF
|
833.000
|
$1.750
|
$2.750
|
|
|
REF PROF PAV MRK TY I(W)6"(SLD)(090MIL)
|
LF
|
2,845.000
|
$1.000
|
$2.750
|
|
|
REF PROF PAV MRK TY I(Y)6"(SLD)(090MIL)
|
LF
|
5,073.000
|
$1.000
|
$2.750
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
4.000
|
$260.000
|
$385.000
|
|
PREFAB PAV MRK TY C (W) (LNDP ARROW)
|
EA
|
2.000
|
$500.000
|
$605.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
4.000
|
$325.000
|
$412.500
|
|
REFL PAV MRKR TY I-C
|
EA
|
41.000
|
$7.000
|
$8.800
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
460.000
|
$6.000
|
$8.800
|
|
|
SP MIXES SP-C PG70-22
|
TON
|
1,061.000
|
$175.000
|
$238.220
|
|
|
SP MIXES SP-C SAC-A PG70-22
|
TON
|
1,061.000
|
$175.000
|
$208.230
|
|
|
SP MIXES SP-D PG64-22 (LEVEL-UP)
|
TON
|
81.000
|
$175.000
|
$391.330
|
|
|
SP MIXES SP-D PG64-22 (EXEMPT)
|
TON
|
43.000
|
$175.000
|
$602.890
|
|
|
BONDING COURSE
|
GAL
|
1,085.000
|
$7.000
|
$8.100
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$20,000.000
|
$1,636.250
|
|
|
TMA (STATIONARY)
|
DAY
|
224.000
|
$250.000
|
$10.460
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
12.000
|
$250.000
|
$209.130
|
|
Totals: |
$1,702,275.250
|
$1,987,987.064
|