Job Info for 0064-05-063

County: SABINE Highway: FM 1 Date: 06/04/2020 (4 years ago) Engineer's Estimate: $610,907 Control Number: 0064-05-063
Project: STP 2019(495)HES District: LUFKIN Time: 148 WORKING DAYS Type: CONSTRUCTION OF SAFETY WORK

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $610,907.10
A R BROTHERS CONSTRUCTION SERVICES, INC.   $764,437.24 1
25.13% | $153,530.14
DBI SERVICES, LLC   $888,894.70 2
45.5% | $277,987.60
16.28% | $124,457.46
EAST TEXAS BRIDGE, INC.   $911,429.80 3
49.19% | $300,522.70
19.23% | $146,992.56
2.54% | $22,535.10
SJ&J CONSTRUCTION, LLC   $923,745.00 4
51.21% | $312,837.90
20.84% | $159,307.76
1.35% | $12,315.20
LONGVIEW BRIDGE AND ROAD, LTD.   $964,119.74 5
57.82% | $353,212.64
26.12% | $199,682.50
4.37% | $40,374.74
FNH CONSTRUCTION, LLC   $1,076,903.00 6
76.28% | $465,995.90
40.88% | $312,465.76
11.70% | $112,783.26

Bid Items

Items: 41, 0 filtered
SABINE FM 1  |  LUFKIN  |  0064-05-063  |  06/04/2020  |  $610,907  |  STP 2019(495)HES  |  CONSTRUCTION OF SAFETY WORK  |  148 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate A R BROTHERS CONSTRUCTION SERVICES, INC. DBI SERVICES, LLC EAST TEXAS BRIDGE, INC. SJ&J CONSTRUCTION, LLC LONGVIEW BRIDGE AND ROAD, LTD. FNH CONSTRUCTION, LLC
100 6002 PREPARING ROW STA 32.000 $500.000 $450.000 $1,900.000 $1,800.000 $1,000.000 $2,000.000 $2,031.000
132 6019 EMBANKMENT (VEHICLE)(ORD COMP)(TY B) CY 3,674.000 $10.000 $25.000 $23.000 $18.000 $30.000 $18.000 $30.000
158 6003 SPEC EXCAV WORK (HYD EXCAVATOR) HR 32.000 $100.000 $110.000 $140.000 $125.000 $100.000 $130.000 $150.000
162 6002 BLOCK SODDING SY 372.000 $5.000 $7.000 $7.000 $7.000 $4.500 $5.500 $5.000
164 6009 BROADCAST SEED (TEMP) (WARM) SY 7,056.000 $0.300 $0.150 $0.150 $0.150 $0.500 $0.150 $1.000
164 6011 BROADCAST SEED (TEMP) (COOL) SY 7,056.000 $0.300 $0.150 $0.150 $0.150 $0.500 $0.150 $1.000
164 6021 CELL FBR MLCH SEED(PERM)(RURAL)(SANDY) SY 14,112.000 $0.500 $0.500 $0.450 $0.500 $1.500 $0.320 $1.000
168 6001 VEGETATIVE WATERING MG 572.100 $20.000 $10.000 $65.000 $10.000 $10.000 $5.000 $50.000
169 6002 SOIL RETENTION BLANKETS (CL 1) (TY B) SY 3,728.000 $2.000 $1.230 $1.250 $1.250 $4.500 $0.950 $6.500
340 6270 D-GR HMA(SQ) TY-D PG64-22 NON-MOW STRIP SY 2,017.000 $40.000 $65.000 $80.000 $55.000 $50.000 $100.000 $40.000
401 6001 FLOWABLE BACKFILL CY 20.000 $220.000 $192.000 $150.000 $300.000 $220.000 $272.000 $350.000
403 6001 TEMPORARY SPL SHORING SF 1,200.000 $20.000 $35.000 $23.000 $45.000 $35.000 $33.000 $55.000
420 6057 CL C CONC (WINGWALLS) CY 16.200 $1,000.000 $2,000.000 $1,550.000 $1,200.000 $2,500.000 $1,475.000 $1,500.000
420 6066 CL C CONC (RAIL FOUNDATION) CY 2.000 $800.000 $900.000 $525.000 $2,500.000 $3,000.000 $915.000 $1,500.000
432 6024 RIPRAP (STONE COMMON)(DRY)(12 IN) CY 11.000 $200.000 $175.000 $240.000 $250.000 $250.000 $250.000 $185.000
451 6004 RETROFIT RAIL (TY T131RC) LF 220.000 $150.000 $195.000 $150.000 $185.000 $220.000 $240.000 $150.000
462 6046 CONC BOX CULV (3 FT X 3 FT)(EXTEND) LF 20.000 $400.000 $375.000 $1,780.000 $1,000.000 $700.000 $600.000 $1,000.000
464 6003 RC PIPE (CL III)(18 IN) LF 118.000 $45.000 $50.000 $180.000 $70.000 $80.000 $55.000 $85.000
466 6196 WINGWALL (PW - 2) (HW=7 FT) EA 1.000 $18,000.000 $26,000.000 $29,000.000 $32,000.000 $12,000.000 $31,000.000 $35,000.000
466 6197 WINGWALL (PW - 2) (HW=8 FT) EA 1.000 $20,000.000 $31,900.000 $33,600.000 $35,000.000 $25,000.000 $32,000.000 $40,000.000
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 2.000 $450.000 $750.000 $2,200.000 $1,200.000 $1,500.000 $940.000 $1,850.000
480 6001 CLEAN EXIST CULVERTS EA 1.000 $600.000 $1,500.000 $7,000.000 $3,000.000 $1,000.000 $3,310.000 $1,500.000
496 6016 REMOV STR (PIPE) EA 1.000 $500.000 $175.000 $1,800.000 $500.000 $1,000.000 $662.000 $500.000
500 6001 MOBILIZATION LS 1.000 $53,000.000 $70,000.000 $80,000.000 $86,000.000 $100,000.000 $90,000.000 $100,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 $1,750.000 $1,750.000 $3,300.000 $6,000.000 $4,000.000 $2,500.000 $8,500.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 3,200.000 $2.500 $3.000 $2.000 $3.500 $4.000 $3.200 $4.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 3,200.000 $1.000 $2.000 $0.200 $1.000 $2.000 $1.000 $2.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 3,200.000 $22.000 $20.500 $21.000 $23.000 $29.000 $25.000 $25.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 16.000 $1,800.000 $1,562.000 $1,375.000 $1,500.000 $1,500.000 $1,850.000 $1,850.000
540 6017 MTL BM GD FEN (LONG SPAN SYSTEM) LF 100.000 $25.000 $40.500 $17.500 $27.000 $70.000 $32.000 $50.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 3,375.000 $2.500 $2.400 $1.000 $3.000 $4.000 $4.000 $3.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 12.000 $250.000 $354.000 $100.000 $250.000 $500.000 $400.000 $850.000
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 16.000 $300.000 $354.000 $100.000 $200.000 $1,200.000 $400.000 $850.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 20.000 $2,500.000 $2,976.000 $2,180.000 $2,750.000 $2,900.000 $3,000.000 $2,850.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 8.000 $285.000 $354.000 $100.000 $250.000 $750.000 $400.000 $1,500.000
552 6003 WIRE FENCE (TY C) LF 250.000 $11.000 $7.000 $10.000 $25.000 $27.000 $18.000 $20.000
658 6050 INSTL OM ASSM (OM-2Z)(FLX)SRF EA 14.000 $60.000 $72.000 $65.000 $75.000 $40.000 $85.000 $100.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 58.000 $40.000 $34.500 $20.000 $35.000 $90.000 $30.000 $100.000
658 6071 INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI) EA 24.000 $23.000 $28.500 $65.000 $25.000 $90.000 $30.000 $100.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 4.000 $10,000.000 $4,780.000 $7,500.000 $20,000.000 $5,000.000 $15,000.000 $12,500.000
6185 6002 TMA (STATIONARY) DAY 48.000 $300.000 $90.000 $250.000 $325.000 $150.000 $200.000 $550.000
Totals: $610,907.10 $764,437.24 $888,894.70 $911,429.80 $923,745.00 $964,119.74 $1,076,903.00